System Alteration Notification (SAN) Process Using BT’s DLE Node Consolidation Program as an example. Presentation to SCRF 07/11/03 Presented by Chris Mitchell. Action. Owner. Time Scale. Operator notified of BT’s planned network change by means of a SAN.

dante-hicks
Download Presentation

Presentation to SCRF 07/11/03 Presented by Chris Mitchell

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. www.btwholesale.com

  2. System Alteration Notification (SAN) ProcessUsing BT’s DLE Node Consolidation Program as an example. Presentation to SCRF 07/11/03 Presented by Chris Mitchell www.btwholesale.com

  3. Action Owner Time Scale Operator notified of BT’s planned network change by means of a SAN At least 7 Months before planned change (Min) BT Operator provides details and Quote of costs (if any) SAN + 1 Month (Max) Operator Joint Negotiations No Disputes Procedure Agreement ? Yes SAN + 3 Months (Max) Quote agreed in writing & signed by both Parties Operator & BT Earliest reciprocal work start Work completed, Operator invoices BT. Operator Invoice paid when presented by Operator Invoice + 1 month BT System Alteration Notification ProcessAssuming BT is the issuer. Operator & BT www.btwholesale.com

  4. Notification - 1. • BT provides generic notification of intentions to all Operators by means of a Network Briefing available at http://www.btwholesale.com/interconnect2bt/network_information/network_briefings www.btwholesale.com

  5. Notification - 2a. • Affected Operators are subsequently individually notified by means of a formal System Alteration Notification, and .... Typical System Alteration Notification This is a formal System Alteration Notification in accordance with paragraph 4. of the NETWORK CHARGE CONTROL (ANNEX 2) STANDARD INTERCONNECT AGREEMENT. Further to the Network Briefing 'DLE Consolidation Program', and information contained in NIPP DLE Consolidation will require changes to your system with respect to the BT DLEs indicated on the accompanying spreadsheet that you currently interconnect with. As per paragraph 4.2 please advise BT, within one month of the receipt of this notice, of any alterations required to your System as a result of the proposed System Alteration and supply a quotation for the cost, if any, of such alterations calculated on the basis of the minimum cost consistent with good engineering practice. A response is required by <Please insert date one month on from date of issue> www.btwholesale.com

  6. Notification - 2b. • ... a customised spreadsheet detailing the changes that affect them. www.btwholesale.com