CS3773 Software Engineering

CS3773 Software Engineering. Lecture 8 Software Planning and Estimation. Software Management. Software engineering is a managed process People management Software cost estimation Quality management Configuration management Software management activities may include Proposal writing

damara
Download Presentation

CS3773 Software Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CS3773 Software Engineering Lecture 8 Software Planning and Estimation

  2. Software Management • Software engineering is a managed process • People management • Software cost estimation • Quality management • Configuration management • Software management activities may include • Proposal writing • Software planning • Project monitoring • Personnel selection and evaluation UTSA CS3773

  3. Software Planning • Effective software management depends on thoroughly planning the progress of the project • Project planning identifies the activities, milestones, and deliverables produced by a project • Project plan guides the development towards the project goals • In planning, cost estimation is an important task, which is concerned with estimating the resources required to accomplish the project plan UTSA CS3773

  4. Project Plan • Project plan shall include the following sections • Introduction • Project organization • Risk analysis • Hardware and software resource requirements • Work breakdown • Project schedule • Monitoring and reporting mechanism • Project plan is revised during project development UTSA CS3773

  5. Milestones and Deliverables • A milestone is a recognizable end-point of a software process activity • Deliverables are milestones • Requirements specification • Architectural design • Program • Internal project results that are used by the project manager to check project progress are milestones • Software process must be broken down into basic activities with associated outputs to establish milestones UTSA CS3773

  6. Project Scheduling • Project scheduling separates the total work involved in a project into separate activities and judging the time required to complete them • Project scheduling organizes all the activities into a coherent order • Some of the activities can be carried out in parallel • Some of the activities must be organized in a sequential manner • Project activities shall last lat least a week • Project schedules are usually represented as a set of charts or diagrams UTSA CS3773

  7. Mechanics of Scheduling • We follow the three steps to produce a project schedule • Decomposing activities into subtasks and estimating the durations - produce an estimation table • Identifying dependencies on subtasks – produce a priority graph • Assigning subtasks and analyzing resulting schedule – produce a critical path diagram • Project schedule charts or diagrams show work breakdowns, activities dependencies, and staff allocations UTSA CS3773

  8. Estimation Table * We assume that the project is done by a single developer UTSA CS3773

  9. Priority Graph UTSA CS3773

  10. Critical Path Method (CPM) • CPM take as input • Estimation table • Priority graph • An assignment of each task to a programmer • An ordering on the tasks assigned to each programmer • It computes • Earliest start time of each task • Earliest completion time for all tasks • Slack time, the amount of time starting on a task can be delayed without affecting the earliest completion date UTSA CS3773

  11. CPM: Notational Convention for Tasks UTSA CS3773

  12. CPM: Ordering of Constraints UTSA CS3773

  13. CPM Example UTSA CS3773

  14. CPM Example UTSA CS3773

  15. CPM Example UTSA CS3773

  16. CPM Example UTSA CS3773

  17. CPM Example UTSA CS3773

  18. CPM Example UTSA CS3773

  19. Gantt Charts UTSA CS3773

  20. Reading Assignments • Sommerville’s Book, 8th edition • Chapter 5, “Project Management” • Sommerville’s Book, 9th edition • Chapter 22, “Project Management” • Chapter 23, “Project Planning” UTSA CS3773