1 / 28

Luminosity and time estimates

Luminosity and time estimates. Mike Lamont. Thanks for discussion: R. Assmann , R. Bailey, M. Ferro- Luzzi , S. Fartoukh , O. Bruning. Disclaimer. The future is a strange place Aim of the exercise is to establish some realistic numbers given accepted constraints

daisy
Download Presentation

Luminosity and time estimates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Luminosity and time estimates Mike Lamont Thanks for discussion: R. Assmann, R. Bailey, M. Ferro-Luzzi, S. Fartoukh, O. Bruning

  2. Disclaimer • The future is a strange place • Aim of the exercise is to establish some realistic numbers given accepted constraints • All numbers to be treated with a modicum of circumspection • Optimistic numbers can be treated as upper limits Luminosity estimates

  3. Some formulae Halving time to luminosity – 2 IPs Assume radiation damping compensates diffusion And then optimize fill length Following Ruggiero Luminosity estimates

  4. Luminosity estimates • Calculate peak luminosity given the usual inputs • Bunch current, number of bunches, emittance, beta*, crossing angle • Calculate luminosity lifetime given • Luminosity, cross-section • Beam-gas lifetime • IBS growth rates • Optimize fill length given an assumed turnaround time • Given fill length & luminosity lifetime – calculate integrated luminosity per fill • Multiply up Luminosity estimates

  5. Turn around time Physics to physics ~ 3 hour minimum. Assume 4 hours here – optimism bias Luminosity estimates

  6. Note: ramp down – precyclecombo • Perform ramp down of main bends, quads, IPQs, triplets etc. • Up to 40 minutes from 3.5 TeV values • At the same time precycle all other circuits • Sextupoles, correctors, compensators, warm magnets etc Luminosity estimates

  7. LEP • No-one ever thought it could be as smooth as: Less than one hour turn around (after 8 years’ optimization) Luminosity estimates

  8. Of course it wasn’t always as good as that Luminosity estimates

  9. Operation month/year After a year or so… • 30 days per month • 3 day technical stop & recovery • [~2 days machine development] • Absorbed into unavailability for this exercise • 60% machine availability • During which time we are dedicated to trying to do physics • 4 weeks of ions (plus one week setup) • Other requests e.g. Totem • Shutdown • Assume around 7 months proton physics per year • approx. 200 days, optimization possible with a 2 year cycle Luminosity estimates

  10. The Hubner factor • Standard method • Take schedule physics time (minus MD, scheduled stops etc.) • Take peak luminosity time number of seconds • Multiply by Hubner factor • Usually taken to be around 0.2 • Takes into account luminosity lifetime, turnaround, unplanned interventions etc • Here I have explicitly calculated luminosity lifetime, optimal fill length etc. • End up with a HF of around 0.3 • Long luminosity lifetime, long fills, 4 hour turn around • The LHC has to be good, rashly make the assumption that we can make it so. Luminosity estimates

  11. Out with the crystal ball Luminosity estimates

  12. 2010 to 2 MJ Jorg’s approved steps to 2 MJ Simple HF Luminosity estimates

  13. What you can TT40 Damage during 2004 High Intensity SPS Extraction / Goddard, B ; Kain, V ; Mertens, V ; Uythoven, J ; Wenninger, J Or what you can do with 2.9 MJ During high intensity extraction on 25/10/04 an incident occurred in which the vacuum chamber of the TT40 magnet QTRF4002 was badly damaged. The beam was a 450 GeV full LHC injection batch of 3.4 1013 p+ in 288 bunches, and was extracted from SPS LSS4 with the wrong trajectory 4.4 e12 at 3.5 TeV 88 bunches at 5 e10 Luminosity estimates

  14. 2010++ Massimo Giovannozzi et al Luminosity estimates

  15. 2011 3.5 TeV: run flat out at ~100 pb-1 per month 16% nominal Should be able to deliver around 1 fb-1 Luminosity estimates

  16. Beam beam tune shift Round beam approximation 7 e10 gives around 0.009 Luminosity estimates

  17. Constraints to 2015 • Energy • Splice consolidation 2012++ • Should open the way to 6.5/7 TeV • ~2 years at 6.5 TeV before hitting 7 TeV • Beam intensity limits from collimation phase 1 • 40% maximum – less with imperfections • 2012 + X: modification of DS • 2012 + X + 1: DS collimators buys nominal intensity • 2014/2015: Full phase 2 buys nominal and ultimate intensity • If X > 0 then assume everything done after 2014 run • Until then 40% limit holds – which is not a major disaster Luminosity estimates

  18. Collimationphase 2 NB: limit, not prediction Luminosity estimates

  19. 2015 - 2020? • Arrive at end 2014 (with a bit of luck) • 7 TeV • Around 20% nominal performance • 10 - 20 fb-1 in the bag • On the schedule: • LINAC4 (lose 6 months of proton physics) • DS collimators in – good for nominal • Collimation phase 2 – good for ultimate • Phase 1 upgrade (1 year shutdown plus re-commissioning) Luminosity estimates

  20. 2015 - 2020? • Statistical error halving time • Accumulate X fb-1 per year • A naïve 3 more years at the same rate to halve the error • Flat lining soon becomes uninteresting • However, we’re hardly flat-lining at this stage • Clear that having yet to achieve nominal performance, another major shutdown would not be optimal at this stage Luminosity estimates

  21. Plan A • 2012++ – splice consolidation and DS collimation prep. • 2013 – 6.5 TeV – ~25% nominal • 2014 – 6.5 TeV – ~40% nominal • 2015(?) – LINAC4 (6 months), collimation phase 2: • No phase 1 upgrade • Ions, 2 months recommissioning, 4 month protons • Presumably contingent on delivered integrated luminosity • 2016: 7 TeV – nominal performance • 2017 – 2020 • A) Push to nominal and then flat-line (more-or-less) • B) Push towards ultimate • 2020 – 2022 – possible upgrade • Presumably contingent on delivered integrated luminosity etc. Luminosity estimates

  22. Plan A Luminosity estimates

  23. To 2014 • 2012: splice consolidation (and DS collimator prep (?)) • 2013: 6.5 TeV ~25% nominal intensity • 2014: 6.5 TeV ~40% nominal intensity Luminosity estimates

  24. Independent estimate Courtesy of a rather pessimistic but perhaps more realistic Massi Ferro-Luzzi At least in the same ball park Hubner Factor ~ 0.2 Luminosity estimates

  25. 2015 – 2016 to nominal 2015: Take a 6 month hit for LINAC4 & collimators phase 2, say, Optimist Might hope to hit nominal in 2016 Massi Luminosity estimates

  26. Beyond 2016 • Assumptions • PS at increased injection energy plus LINAC4 are good for ultimate (after a suitable commissioning period) • ~1.7 x 1011 can be swallowed by the SPS • Give or take a long shutdown • LHC can swallow ultimate intensity • “Ultimate intensity is challenging for the LHC. Many systems at technological limits with little or no margin.” (R. Assmann – Cham 2010) Stay at or around nominal Able to push towards ultimate Luminosity estimates

  27. 2010 - 2020 Luminosity estimates

  28. Conclusions • Luminosity estimates for the next ten years presented • Biased towards the optimistic • Nominal performance by 2016 • 21st century Hubner factors • Big errors bars and numbers should be treated with care particularly after 2016 • Important to gain some operational experience!!! Luminosity estimates

More Related