CENTRAL ARIZONA PROJECT PRESENTATION TO THE CRT Planning Group October 12, 2007. CENTRAL ARIZONA PROJECT. System Features: 335 Miles of Canal Total Water Lift of 2,915 Ft. Storage in Canal and Lake Pleasant 14 Pumping Plants, 1 Pump/Generator Electrical Load of ~500 MW.

Download Presentation

CENTRAL ARIZONA PROJECT PRESENTATION TO THE CRT Planning Group October 12, 2007

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Central arizona project presentation to the crt planning group october 12 2007

CENTRAL ARIZONA PROJECT

PRESENTATION

TO THE

CRT Planning Group

October 12, 2007


Central arizona project

CENTRAL ARIZONA PROJECT

System Features:

  • 335 Miles of Canal

  • Total Water Lift of 2,915 Ft.

  • Storage in Canal and Lake Pleasant

  • 14 Pumping Plants, 1 Pump/Generator

  • Electrical Load of ~500 MW


Central arizona project presentation to the crt planning group october 12 2007

Demand @ 1,584,256 AF off the Colorado River

CAP Pumping Plants Need 2,478,050 MWh


Central arizona project presentation to the crt planning group october 12 2007

CENTRAL ARIZONA PROJECT

Electricity Supply

  • Navajo Project (547MW)

  • Hoover Power (161 MW)

  • New Waddell Power

  • CAWCD Buys and Sells


Central arizona project presentation to the crt planning group october 12 2007

NAVAJO

377 MW

24.3% - 547MW

McCULLOUGH

MEAD

PARKER DAVIS

122 MW

240 MW

NAVAJO

HOOVER – 161MW

CAP

INTERTIE

85.6 MW

(APA)

75.9 MW

(APA)

DAVIS

NEW

WADDELL

325.6 MW

73.7 MW

LIBERTY

WESTWING

PARKER

PINNACLE

PEAK

LITTLE

HARQUAHALA

HAVASU

BOUSE

HASSAYAMPA

MW of Load

SALT GILA

ED-2

Havasu

B & LH

Hassa

West Capacity

292.0

66.0

58.0

= 416.0

ED-5

ED-4

BRADY

PICACHO

SAGUARO

RED ROCK

RATTLESNAKE

Salt Gila

Brady

Picacho

Red Rock

Twin Peaks

Sandario

Brawley

San Xavier

Snyder Hill

Black Mountain

South Capacity

24.0

14.0

15.0

12.0

3.0

3.0

4.0

2.0

2.0

3.0

=82.0

TWIN PEAKS

SANDARIO

BRAWLEY

DEL BAC

SAN XAVIER

SNYDER HILL/BLACK MOUNTAIN


Central arizona project presentation to the crt planning group october 12 2007

Delivering Supply to Demand


Central arizona project1

CENTRAL ARIZONA PROJECT

  • CAP’s Interest

  • Enhanced Ability to Buy and Sell Power

  • Access to Palo Verde

  • Participate in Future Transmission Projects


Central arizona project2

CENTRAL ARIZONA PROJECT

  • QUESTIONS?

  • CONTACTS:

    • Gary Ijams

      • Power Program Manager - Central Arizona Project

      • 623-869-2362 [email protected]

    • Ken Bagley

      • Manager – Genesee Consulting Group

      • 623-748-8989 [email protected]


  • Login