An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SAP Upgrade Project Kick-Off August 2006

  2. Introduction • Project is to perform a technical upgrade from SAP version 4.6c to ECC 6.0 • Technical upgrade only – existing 4.6c production functionality tested and validated on ECC 6.0 release • During the upgrade, changes are limited to urgent bug fixes, open enrollment and year end updates • Schedule: August 2006 – February 2007 • Resources: 90 – 130 person months and 18 FTE’s • Budget: $750K – 1.25M • 30K external; 22K Training

  3. Project Objectives Project Objectives: • Avoid risk of going out of mainstream support for 4.6C • Provide ability to benefit from new functionality • Bring MIT more into alignment with peer institutions • Reduce cost and complexity of upgrading by doing now versus further delays • Capture items where standard SAP could be used • Develop reusable processes for future upgrades and or for regression testing • Process, procedures, templates, forms etc.

  4. Project Background • MIT last upgraded SAP in January 2001 • Competing business priorities delayed planned upgrades • Upgrade was Top ASPCC priority for FY07 • Quarterly reporting to ASPCC is required • Only MIT and University of Toronto are on 4.6c

  5. Project Background • MIT’s footprint has expanded enormously since the last upgrade • HR, Payroll, Plant Maintenance, EH&S, Broad • Extensive project pre-work • SAP Hardware Renewal – completed June 2005 • FM Discovery project – report published in August • FM re-implementation is not required • SAP Web Classic Migration to WAS • Development completed in August • Implementation scheduled for September • EHS ITS flow file replacement with WAS • Planned for August – November

  6. Project Scope Overview • Upgrade SAP from 4.6c to ECC 6.0 • Test all transactions that MIT uses • Test all actively used custom interfaces, reports, user exits, transactions, forms • Assess obsolete transactions • Evaluate modifications to SAP code to see if the functionality can be reproduced using standard SAP • Test new GUIs • Upgrade desktop GUI’s where needed • Update training materials for SAP GUI based community transactions • Update help documentation for SAP GUI based transactions • ASR, Reporting, Excel uploads

  7. Out of Scope • Migration of all web applications from ITS to WAS • We will move stand-alone ITS applications to the integrated ITS • Functional changes • Unicode Database upgrade • Full Solution Manager implementation

  8. SAP Business Owners & Coordinators Project Organization Project Management Kevin Lyons Jenette Simpson Sponsors/ Steering Committee Jerry Grochow Christine Meholic Business Stakeholders Jim Morgan Wayne Turner Bill Anderson Bill Van Schalkwyk Robert Nichol Frank Schimmoller Pat Fitzgerald Karen Nilsson Margaret Warner R/3 Admin (Basis) Ron Parker George Petrowsky Gee Lee Rich Katkowski Arif Khan EH&S Rob Damian Seth Seligman John Tuttle Lee Collier Test Manager Emily Cunningham HR/Payroll Bart Dahlstrom McCollin, Quern, Carloni, Diliberto, Kandel, Mullen, Ho Goodwin, Donovan, Gulen Kushkuley, Kratochwill, DeSimone Logistics Bob Romanowicz Lorraine Rappaport Ken LeVie John Barttolomeo Hao Wen Ian Bennett Elda Prudden Dave Tartaglia CSS (Training & Pubs, Help Desk SW Release Team) Data Warehouse OIS - Server Ops Lincoln Labs Quality Assurance Mary Alix Debra Wiley Sharron Sawyer Technical Drop Box & Web Wai-Ming Li David Rosenberg Allan Davidson Mark Prudden Nancy Gift Bill McAvinney Brendan Gaul Amy King Community Focus Dave Goodwin Finance Veronica DuLong Bob Casey Rob Damian Mary Ellen Gearin Carolyn Fuller Lucia Ma Red = Core Team SAP Todd Baker

  9. Business Involvement • Business involvement is essential and required • Test scripts updates • Regression/User Acceptance Testing • Functional decision making for required changes • Primary contact and updates are through the functional team leader • Understand impact of SAP development slowdown and then freeze

  10. Project Acceptance Criteria • User Acceptance Testing – Define acceptance and approval criteria with the Business • Test Scenarios • Test Execution – User Acceptance testing (regression test) • Readiness Review – Key Areas • System Functional Assessment by area – Bus. Stakeholders • System Technical - Technical Review Board • Infrastructure – Web/GUI components • Operational

  11. Multiple Kick-Offs & Updates Core Team – 8/9 Extended Team – 8/17 SAPBIZ – 8/23 Sponsors – 8/24 ASPCC Update – 9/20 IS&T Leadership Team Business Stakeholders Business Process Owners & coordinators Structured Reviews Kick-off, Post Unit Test, Pre-UAT, Approval/Readiness Meeting Frequency Core Team – weekly Extended Team – Monthly Sponsors – Monthly SAPBIZ – Monthly ASPCC – Quarterly Customer Forums – Monthly/Quarterly High Level Communication Plan

  12. Time line • Project Prep - 7/5 – 8/17 • Technical and Business Assessment - 8/18 – 9/6 • Test Scripts Inventory and evaluation • Release notes • 1st Upgrade SFK • Realization – 9/7 – 1/10/07 • SAP collisions • SF2 upgrade/unit testing • 9/15 - Dual Maintenance SF2 • 10/31- Restricted transport period “freeze”

  13. Time line • Realization – 9/7 – 1/10/07 • Test Scripts Updates • Integration Test (SH2) – 11/15 – 12/12 • Regression/User Acceptance (SF6) – 12/18 – 1/9/07 • Production Prep – 1/10 – 2/13 • Cut over planning • Trial cutover 1/11 – 1/24 • Go Live 2/17 – 3/19 • PS1 go live – 2/20 • Other Environments

  14. Project Assumptions • Testing will be performed manually • Business process coordinators will perform and sign off on user acceptance testing • Business process owners will sign-off (approve) user acceptance testing results • Business Stakeholders will participate in the readiness Go/ No Go review and make the go live decision • Business process owners and coordinators will validate the upgraded production system on cutover weekend • SAP production will be down for 3 days as part of cutover • Only emergency bug fixes can be applied to production during the upgrade • A development slow down will occur between September 15th to October 31 • QA will control PS1 transports during dual maintenance • Development freeze will occur effective October 31

  15. Authorizations • Significant change (increase) to authorizations • Need to closely evaluate impacts • Additional work required to determine scope of changes and strategy (minimal approach versus re-defining a number of roles • Functional teams have critical role

  16. SAP Upgrade Landscape

  17. Questions and Answers ?