1 / 12

sLHC sensor R&D

sLHC sensor R&D. Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu). Masks are done Fabrication is on-going p-FZ(100) p-MCZ(100) 3 wafers each Delivery April Irradiation End April 70 (or 80) MeV p. ATLAS06J fabrication. 150mm wafer p-FZ(100)

corin
Download Presentation

sLHC sensor R&D

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. sLHC sensor R&D • Module Plans (Nobu) • Manufacturing plans, including financing (Nobu) • Sensor Specs (Nobu) Y. Unno, 2007/2/26

  2. Masks are done Fabrication is on-going p-FZ(100) p-MCZ(100) 3 wafers each Delivery April Irradiation End April 70 (or 80) MeV p ATLAS06J fabrication Y. Unno, 2007/2/26

  3. 150mm wafer p-FZ(100) n-strip isolation Individual p-stop 4 segments SS: as is LS: wire-bond segments ATLAS07 Y. Unno, 2007/2/26

  4. Stereo? Y. Unno, 2007/2/26

  5. Edge stereo connection Y. Unno, 2007/2/26

  6. ATLAS07 specification Y. Unno, 2007/2/26

  7. Design 2 months+? by May? Fabrication a few months depends on quantity Financing Mask cost to be shared No. wafers=Cost share Invoices Japan: KEK Outside Japan: CERN TID My big question mark Readout ASIC? Irradiation campaign CYRIC (70-80 MeV p) (April), Aug, Nov,Mar PSI (pions) Neutrons Dummy ATLAS07 Al metal only Who are interested? How many? Financing withsame model ATLAS07 Y. Unno, 2007/2/26

  8. 2007 3-5 Design of pre-prototype (Barrels) 2007 6-9 Fabrication of pre-prototype 2007 9- Irradiation, Module fabrication and evaluation 2008 3-6 Design of prototype (Barrels, Endcaps) 2008 6-10 Fabrication of prototypes 2008 10- Irradiation, Module fabrication and evaluation, beamtests 2010 2 TDR ATLASxx plan Y. Unno, 2007/2/26

  9. 1-MeV neq /cm2 Fluence by particles Sensor parameters for ASIC Y. Unno, 2007/2/26

  10. Constraint from HV cable rating 500 V (1 kV tested) Sensor operation <500 V Parameters for ASIC at 500 V Preliminary Sensor parameters for ASIC Y. Unno, 2007/2/26

  11. Preliminary!!! Sensor parameters for ASIC Y. Unno, 2007/2/26

  12. Modules have to have ABCN when? hybrids develop along with ABCN fabrication of modules time scale uncertain Staves ? Module plan Y. Unno, 2007/2/26

More Related