An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Power Purchase Agreementfrom a Utility Perspective Are Geothermal Projects Different than Other Resources? Marilynn Semro Seattle City Light May 11, 2005

  2. Agenda • In the beginning • Minimum Information Requirements • Plan for an Agreement = MOU • Long-term PPA • Where do we go from here Seattle City Light

  3. In the beginning • There are hurdles • Integrated Resource Plan • Request for Proposals (“RFP”) • Memorandum of Understanding (“MOU”) • Letter of Intent (“LOI”) or … • Purchase and Sale Agreement (“PPA”) • Or maybe in lieu of an RFP • If the utility provides for “cost-effective renewable opportunities” they will accept unsolicited proposals Seattle City Light

  4. Min Information Requirements • Project description including generation type, location, size, expected annual energy, on-line date, term, cost, inclusion of environmental attributes • Status of leases, permits, environmental review • Shape of energy • Transmission • Interconnection point • Status of transmission service reservations or studies • Project schedule • Project ownership, financing, developer experience Seattle City Light

  5. Plan for Agreement = MOU • Typically includes: • Resource Description • Amount + Associated Environmental Attributes • Term, Extensions • Price • Point of Interconnection • “Boiler Plate” • E.g. Assignment, Good Faith, Confidentiality, Conditions Subsequent, Nature of the MOU, Governing Law & Venue Seattle City Light

  6. Plan for Agreement = MOUcont’d • Other Provisions: • Milestones for Resource Development • Obtaining exploratory drilling permits • Commence exploratory drilling • Report of sufficiency documenting quality and quantity of the resource for economic development • All required permits and regulatory approvals including EIS • Construction financing • On-line date • Defines party responsible and timeline for securing transmission • Termination provisions for failure to meet milestones • Output guaranty Seattle City Light

  7. Long-Term PPA Seattle City Light

  8. Where Do We Go From Here? • Approval • Implementation and Resource/Contract Management Seattle City Light