An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Missouri Department of Economic Development COMMUNITY DEVELOPMENT BLOCK GRANT HUD Environmental Review NEPA & 24 CFR Part 58July 8, 2011 Welcome!

  2. Goals of Environmental Review • Protect the Environment • Endangered species, wetlands, historic properties, air and water quality…. • Protect theProject • Toxic contamination, explosive operations, noise, floods, airport hazards….

  3. Tools & Resources • 24 CFR Part 58 Regulation • NEPA-related regulations • Chapter 4 CDBG Manual • PowerPoint notes • Environmental Agencies • Websites • Additional Guidebooks • CDBG Staff

  4. It’s not always rainbows, sprinkles, butterflies, unicorns, puppies, ‘n stuff…

  5. Overview of Environmental Review I. Statutory & Regulatory Structure II. Key Terms & Concepts III. Conducting the Review IV. Approval Procedures

  6. I. Statutory & Regulatory Structure

  7. Why do we conduct environmental reviews? • Avoid or mitigate environmental impacts that harm people. • Avoid or mitigate harm to the surrounding environment. • Avoid litigation that could stop project on environmental grounds. • Avoid monitoring findings & sanctions. • Secure the value of public investment. • IT’S THE LAW – Under NEPA & NEPA-related laws.

  8. What is NEPA? • National Environmental Policy Act of 1969 • Basic national charter for protection of the environment • Established Council on Environmental Quality (CEQ) (40 CFR Chapter V, 1500 - 1518) • Federal agencies implement NEPA with their own regulations • “Environmental values SHALL be given appropriate consideration in decision making”

  9. NEPA- continued • Ensures that environmental information is available to public officials and citizens BEFOREdecisions are made and BEFOREactions are taken. • Requires systematic, interdisciplinary approach. • Helps public officials make decisions with an understanding of environmental consequences.

  10. NEPA Applies To… • All proposals for Federal actions that have the potential to affect the quality of the human environment. • No “trigger level” - All levels of Federal funding and assistance are covered: including small grants and loans, loan guarantees, permitting, and so on.

  11. Consideration of Alternatives “The Heart of NEPA” Alternative Sites…Designs…Actions…Timeframes

  12. NEPA – DirectImpacts PROJECT= DIRECT IMPACT: New Sewer Plant t

  13. NEPA – IndirectImpacts New paper mill plant New residential sub-division Risks to current infrastructure Inadequate infrastructure to support growth More traffic thru town

  14. NEPA – Cumulative Impacts + + + • CUMULATIVE IMPACTS: • Regional Sewer Project: • 3 new sewer plants • 3 phases • 3 communities along river

  15. NEPA requires examination of ALL federal laws affecting the environment • Air • Water • Land • Flora • Fauna • Human Health

  16. “Environmental Review” - the examination of a project relative to NEPA and its related laws… NEPA is the umbrella under which the review is conducted….Environmental topics and concerns are spokes of the umbrella…..

  17. NEPA-Related Laws & Authorities (24 CFR Part 58.5) • Safe Drinking Water Act (1974) • Floodplain Management & Wetlands Protection E.O.s (1977) • Farmland Protection Policy Act (1981) • HUD Environ. Criteria & Standards (1984) • Environmental Justice E.O. (1994) • National Historic Preservation Act (1966) • Wild and Scenic Rivers Act (1968) • Clean Air Act (1970) • Coastal Zone Management Act (1972) • Noise Control Act (1972) • Endangered Species Act (1973)

  18. Other Requirements (24 CFR 58.6) • Flood Disaster Protection Act – flood insurance • Coastal Barrier Resource Act –coastal development • Airport Runway Clear Zone – buyer notification

  19. II. Basics of HUD Environmental Review

  20. HUD Regulation24 CFR Part 58 Regulation for HUD’s implementation of NEPA & related authorities: • 24 CFR Part 58 “Environmental Review Procedures for Entities Assuming HUD Environmental Responsibilities” Become familiar with the regulation, found at http://www.access.gpo.gov/nara/cfr/waisidx_04/24cfr58_04.html

  21. Terms & Definitions§58.2

  22. “Project”§58.2(a)(4) • PROJECT- An activity, or a group of integrally related activities, designed by the recipient to accomplish, in whole or in part, a specific objective.

  23. “Environmental Review” (ER) • Used in this program to apply to the review of: • Any HUD assisted action & its relationship to NEPA & related environmental laws. • We review “projects” not funds. Environmental approval (often called “clearance” or “release of funds”) is for theproject, not the source of HUD funds.

  24. “Responsible Entity” (RE) §58.2(a)(7) • Section 104(g) of Housing and Community Development Act of 1974 authorizes HUD Secretary to allow units of general local government and States to assume the status of federal officialunder NEPA & NEPA-related environmental laws & authorities. • This “assumption authority” allows cities, counties, states, & Indian tribes to act as Responsible Entity(RE) in lieu of HUD for the purposes of NEPA review, decision-making and action.

  25. “Assumption Authority” §58.4 • RE assumes HUD’s authority by executing grant agreement (as Recipient) and by certification of the RROF/C. • RE assumes responsibility for: • Environmental review • Environmental decision-making • Environmental actionthat would apply to HUD under NEPA and related laws

  26. “Assumption Authority” §58.4 - Continued • Responsibility - The environmental “buck” stops w/ the Responsible Entity. ER responsibilities cannot be delegated to another party/entity. • Responsible Entity - Ensures all conditions, procedures, & requirements resulting from environmental review process are incorporated into project plans & implemented.

  27. “Assumption Authority” §58.4 - continued State CDBG Programs: • Under State-administered CDBG program (e.g., Small Cities CDBG program), the State exercises HUD’s approval responsibilities (RROF).

  28. Sub-Recipient • Sub-recipients of CDBG funds may include: • Non-profits • Water/sewer districts • Ambulance districts • Fire protection districts • Main street organizations • Others in which RE (unit of local government) applies for CDBG funds on their behalf.

  29. Sub-Recipient Role • Provides RE w/ project & environmental information • Does not undertake activities prior to receiving authorization by RE & HUD • Notifies RE immediatelyabout: • changes to proposed project, or • new alternative is selected • Implements all special conditions, procedures & requirements of environmental review

  30. RE role when a project involves aSub-Recipient • RE must independently evaluate information provided by Sub-Recipient • RE performs environmental review & submits the equestforRelease of Funds/ Certification (RROF) for DED/CDBG approval, when required

  31. “Certifying Officer” §58.2(a)(2) • Chief Executive Officer of jurisdiction, or official designee (with formal, written delegation of authority) • “Responsible Federal Official” as used in section 102 of NEPA & in statutory provisions • Authorized to execute Request for Release of Funds and Certification (RROF) • Accepts jurisdiction of Federal Courts for Responsible Entity (RE) in environmental matters

  32. “Limitation on Activities Prior to Clearance”§58.22(a) • Recipient may not commitHUD/CDBG orNon-HUD/CDBG fundson an activity prior to approval if the activity would have an adverse environmental impact or limit the choice of reasonable alternatives. • This limitation is rooted in all NEPA-related authorities • Don’t take action until compliance is achieved.

  33. Importance of Early Start • Begin ER as soon as possible once project is substantially known! • Do not commit HUD/CDBGfunds on activities prior to environmental approval. • Do not commit Non-HUD/CDBG funds prior to environmental approval if activity/project would have adverse environmental impacts or limit choice of reasonable alternatives. • Projects not requiring RROF - applicable environmental review forms must be complete before starting activity or project

  34. “Limitation on Third Parties” 58.22(a) • Part 58 extends this prohibition to third parties: • “Neither a recipient nor any participant in the development process, including public or private nonprofit or for-profit entities, or any of their contractors,may commit HUD assistance [prior to RROF]. . . . or non-HUD funds. . .if the activity or project would have an adverse environmental impact or limit the choice of reasonable alternatives.”

  35. “Affirmative Responsibility” §58.22(c) • RE considering an application from a prospective sub-recipient or contractor & is aware they are about to take action prohibited by 58.22(a), RE must take “appropriate action” to ensure compliance w/ NEPA • Choice-limiting actions include real property acquisition, leasing, demolition, rehabilitation, construction & site improvements.

  36. Reducing Exposure to Legal Liability • Follow all required steps in decision-making process • Carefully document compliance w/ NEPA & related authorities • Exercise due diligence in investigations • Use reasonable approaches that are neither arbitrary nor capricious

  37. Cost of Performing the Review • Grant funds may be used for ER after execution of grant agreement • Environmental responsibility should not require significant local funds if project is well-planned • Environmental review assists in developing project budget • Others may prepare reviews, but RE remains responsible • If CDBG funds are proposed to pay any contract, Federal procurement rules apply

  38. “RE’s Capacity” §58.12 RE must develop capacity to conduct the review: • Technical Capacity = procedural expertise, use of in-house staff or outside entity • Administrative Capability = thorough record keeping & clear documentation of compliance with Part 58

  39. Interaction with Other Entities §58.14 • Consult w/ appropriate agencies (State, Federal, local) & the public. The NEPA review is an interdisciplinary process. • Cooperate w/ other agencies to reduce duplication. • May participate in a joint, lead, or cooperating agency capacity.

  40. “Environmental Review Record”(ERR) §58.38 • Written record of the ER undertaken for each project • Shall be available for public review • Shall contain all environmental review documents, public notices, determinations or findings as evidence of review, decision making & action pertaining to a particular project

  41. Contents of ERR §58.38 • PER/PAR • Project description including precise location or target area, & mapped • Photographs, site plans, elevations • Documentation of compliance w/ §58.5 authorities & HUD §58.6 requirements • Forms, reports, environmental assessments • Written determinations & findings • Public notices, RROF, correspondence, Authority to Use Grant Funds

  42. How long are ERRs current? • How old is it? • Prior project vs. what is now proposed? • What has occurred on the site since the ER? • What has changed around the site? • What is likely to occur around the site? • Everything ages – what wasn’t historic will be. • Know when to surrender & start anew.

  43. The ERR is a legal record • The ERR: • may be subpoenaed & subjected to scrutiny by a court of law • is the only proof of compliance w/ procedural provisions of Federal environmental law • is your only defense if project is challenged

  44. Conducting the Environmental Review

  45. Steps of Environmental Review • Determine scope of project • Aggregate activities into project • Determine level of review • Conduct review • Publish notices & observe comment periods • Submit RROF/C, if required • Commit funds & carry out preferred alternative • Implement & document conditions, as applicable

  46. Determining the Scope of a Project • “Project” is an activity, or group of integrally related activities, designed by the recipient to accomplish, in whole or in part, a specific objective [§58.2(a)(4)] • For purposes of environmental review, the project includes both HUD& non-HUD funds • Project may span several funding years

  47. Project Aggregation §58.32 The RE must group together & evaluate as a single project, ALL individual activities related either on a geographical or functional basis, or are logical parts of a composite of contemplated actions. ALLactivities by ALLfunding sources make up a project.

  48. Public Participation & Environmental Review • CEQ Regulation – Early and open scoping process • NEPA Regulation – Make efforts to provide meaningful public involvement • HUDRegulation– Inform affected public about NEPA-related hearings and meetings, and environmental documents • Section 106 Review - 36 CFR 800.2(d) – Involving the Public The type of public involvement depends on the nature and complexity of actions, their potential impacts, and the likely interest of the public.

  49. Field Visit Checklist & Site Evaluation Updated! • KNOW THE PROJECT AREA! • Complete one or more & attach. • Color photographs are practically a necessity • Existing Conditions – What does the site look like now? What is located on & around the site? • Access (Ingress/Egress) – How do you get to the site? How do you leave? Is it safe & easy? • Interviews – Did you talk to anyone? When? Their relationship to the project/area? What was discussed? • Existing Infrastructure – What is at the site now – water, sewer, electric, gas, roads, parking, storm water, etc. • Potential for contamination

  50. Levels of Environmental Review Environmental Impact Statement (EIS), 58.37 Environmental Assessment (EA), 58.36 Categorically Excluded -CEST (Subject To), 58.35(a) -CENST (Not Subject To), 58.35(b) Exempt Activity, 58.34(a)