自主檢查表常見缺失案例 行政院公共工程委員會

自主檢查表常見缺失案例 行政院公共工程委員會. 7.08.07 版. 常見自主檢查表缺失 -1. 檢查項目未涵蓋契約規範規定之主要施作項目 檢查表不合用且太多,造成文書之負擔,反而不切實際 檢查項目之期程跨越一週以上,如一週才填一張表,即缺乏時效性 檢查標準可量化者未量化,或比契約規範規定值還鬆. 常見自主檢查表缺失 -2. 實際檢查值未量化,或僅打勾或寫合格 檢查人未簽名而用蓋章 工地負責人未複核 承包商自主檢查表有機關或監造單位之複核欄位,權責不清 查核金額以上工程之品管人員,負責進行稽核及缺失改善複查,並非自主檢查均由品管人員執行,卻失去稽核監督之機制功能.

Download Presentation

自主檢查表常見缺失案例 行政院公共工程委員會

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 自主檢查表常見缺失案例 行政院公共工程委員會 7.08.07版

  2. 常見自主檢查表缺失-1 • 檢查項目未涵蓋契約規範規定之主要施作項目 • 檢查表不合用且太多,造成文書之負擔,反而不切實際 • 檢查項目之期程跨越一週以上,如一週才填一張表,即缺乏時效性 • 檢查標準可量化者未量化,或比契約規範規定值還鬆

  3. 常見自主檢查表缺失-2 • 實際檢查值未量化,或僅打勾或寫合格 • 檢查人未簽名而用蓋章 • 工地負責人未複核 • 承包商自主檢查表有機關或監造單位之複核欄位,權責不清 • 查核金額以上工程之品管人員,負責進行稽核及缺失改善複查,並非自主檢查均由品管人員執行,卻失去稽核監督之機制功能

  4. 1.材料 應紀錄實際抽驗每支之檢測值

  5. 2.測量 高程測量無標列設計值高程 僅以設計圖說規範為檢查之標準 不符自主檢查表之要求

  6. 3.模板 缺乏數據、標準

  7. 3.模板 1.沒有設計值 2.一張表單工作時間誇跨越一日以上 3.自主檢查非由品管人員檢查

  8. 4.混凝土 未標明設計值

  9. 是真的很認真!? 本項屬預拌廠之檢查表, 而非工地平時檢查之表格

  10. 5.鋼筋 沒有設計值

  11. 6.抽查 抽查的項目須跨越一段時日

  12. 共勉 過程用心、品質放心