1 / 83

Disaster Recovery: Lessons from Katrina

Disaster Recovery: Lessons from Katrina. Gail Ann McCreary, CRM Mississippi Power Company. Hurricane Katrina – August 29, 2005. Worst natural disaster in U.S. history Affected Alabama – Mississippi – Louisiana 250 miles wide 140 mph winds 30 ft tidal surge along coast line.

clodia
Download Presentation

Disaster Recovery: Lessons from Katrina

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Disaster Recovery:Lessons from Katrina Gail Ann McCreary, CRM Mississippi Power Company

  2. Hurricane Katrina – August 29, 2005 • Worst natural disaster in U.S. history • Affected Alabama – Mississippi – Louisiana • 250 miles wide • 140 mph winds • 30 ft tidal surge along coast line

  3. Were Dealing With… • Rain and wind damage • Tornadoes • Flooding • “Coal water” • Submerged records • Bio-hazard

  4. Determined Priorities • Damage incurred • Business unit and function • Criticality to restoration effort • Building access issues

  5. The Plan…. • Identify records needing to be dried • Pack into boxes • Stage on pallets • Shrink wrap • Load into freezer truck

  6. First Priorities • Substation Construction • Powerco • Plant Watson

  7. Plan Changed • Downtown buildings had to be vacated • All dry records • All PCs, printers, phones • Employee personal effects • Undamaged furniture and modular • Office supplies • 400 employees

  8. New Issues • Needed more boxes!!!! • Needed temporary office space for 400 employees • What to do with all the “stuff” • Employees still on storm duty • 2-3 weeks

  9. Plan B DR would stay and pack dry records too • I did not have the manpower • DR was experienced • Had supply and manpower resources in place

  10. Determined Numbering Scheme • Building ID • Floor number • Location number 202-101 = General Office 2nd floor cubicle #202 SI221-106 = G&SI 2nd floor location #221 842-102 = Hancock Bank 8th floor location #842

  11. Challenges Faced • Locked doors • On-going building clean-up & restoration • No elevators • No electricity • Storage for 7700+ boxes

  12. Back to “Normal”

  13. Phase II • Multiple temporary offices • No storage in temporary offices • No file cabinets • Delivery issues • Palletized boxes not in order by location

  14. Phase II • Employees would have to review • Coordinate with occupancy schedule • Named coordinators for each site • Small volumes delivered where possible

  15. Location No. ______818 _________ Name _Lateral file __

  16. Options • Take • Destroy • Interim • Records center storage

  17. Lessons Learned - Disaster Recovery Process • Utilize document recovery contractor

  18. Lessons Learned -Disaster Recovery Process • Utilize document recovery contractor • Understand the process / clarify costs

  19. Lessons Learned - Disaster Recovery Process • Utilize document recovery contractor • Understand the process / clarify costs • Utilize multiple people

  20. Lessons Learned - Disaster Recovery Process • Utilize document recovery contractor • Understand the process / clarify costs • Utilize multiple people • Work closely with contractor

  21. Lessons Learned - Disaster Recovery Process • Utilize document recovery contractor • Understand the process / clarify costs • Utilize multiple people • Work closely with contractor • Walk-thru after packing completed

  22. Lessons Learned - Disaster Recovery Process • Utilize document recovery contractor • Understand the process / clarify costs • Utilize multiple people • Work closely with contractor • Walk-thru after packing completed • Have floor plans for all buildings

  23. Lessons Learned - Disaster Recovery Process • Utilize document recovery contractor • Understand the process / clarify costs • Utilize multiple people • Work closely with contractor • Walk-thru after packing completed • Have floor plans for all buildings • Document! Document! Document!

More Related