An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIM Health Check Raj Chudgar Program Director for Market Redesign TPTF

  2. 2 As indicated in the CIM Health check progress report at last TPTF, Major challenge for Nodal is the successful integration of CIM data 1 2 3 4 3 CIM critical dependency is on successful model integration of EMS, MMS and NMMS TPTF

  3. 2 Current progress is as represented in the bubbles 1 2 3 4 NMMS Exchanging model with EMS and MMS to finalize schema 3 EMS CIM Importer currently in Pre-FAT • MMS • MMS4 will begin FAT 4/22/08 CIM critical dependency is on successful model integration of EMS, MMS and NMMS TPTF

  4. CIM Impacts on the Nodal Early Delivery Systems (EDS) 1 4 2 3 EMS Zonal Exporter NMMS Exporter EMS Importer MMS Importer TPTF

  5. CIM Exporter/Importer still under development – listed below is the current state 1 2 3 CIM Component Measurement Items TPTF

  6. NMMS - Mitigation items to get to Green 1 • Design and Build • Network Model exchange with multiple vendors on-going. Task targeted to be completed by May 2nd, 2008 to allow time for data load and validation prior to Single Entry Go Live • Testing • ERCOT NMMS will be completed with FAT for NMMS 3 on April 30th, 2008 • Data Model Validation • Base-case comparison between Zonal and Nodal Network Models • Dependent on downstream applications. Currently working with EMS and MMS to provide full set of classes and attributes that are needed for their files • Data Validation • TSPs validation of data in Network Model underway, will be an on-going item post Go Live • Market Trials • NOMCR Market Trials underway. Will be completed May 20th TPTF

  7. MMS - Mitigation items to get to Green 2 • Design and Build • Initial design is complete. • Regular conversations on the status of CIM importer occurring between ERCOT & ABB. • Testing • ERCOT involved in definition and execution of the CIM importer tests.   • CIM Importer is part of MMS4 testing • MMS4 Pre-FAT - CIM importer testing completed 15Apr08 • MMS4 FAT - CIM importer testing will begin 22Apr08 • Data Model Validation • NMMS, EMS, MMS coordinating to finalize CIM Schema. • ERCOT is working with ABB, who is maintaining a detailed, prioritized spreadsheet with all modeling and data issues. • ERCOT is performing due diligence of all CIM attributes necessary to execute all functions in MMS. • NMMS & MMS will review and confirm all data modeling requirements no later than 25Apr08 • Data Validation • On-going ERCOT activity that includes MMS, EMS, NMMS, System Operations, RARF Folks, etc. • Market Trials • EDS 4 Release 9.3 will be using CIM. TPTF

  8. EMS - Mitigation items to get to Green 3 • Design and Build • ERCOT escalation to AREVA Management minimize schedule delay • ERCOT personnel on-site at AREVA • ERCOT proactively addressing open issues • Completing build will move to Green • Testing • ERCOT doing preliminary testing in parallel to reduce testing cycle • ERCOT developed a comparison database to support validation • Data Model Validation • NMMS, EMS, MMS coordinating to finalize CIM Schema • EMS currently in Pre-FAT for CIM Importer; expected to be in FAT on 28Apr08 • Data Validation • Plans to compare the data between the Zonal Habitat Databases (source) and the Nodal Habitat Databases (generated via CIM XML) • Data validation continues as code matures with increased functionality TPTF

  9. CIM Integration Plan • Given the criticality of CIM, ERCOT has assigned Linda Clarke to facilitate/coordinate CIM integration between key vendors (MMS, EMS and NMMS) • CIM integration meetings are held on a weekly basis to monitor progress/expedite problem resolution • The team is developing an integrated plan that drives NMMS, MMS, EMS, and EDS applications to use same version of CIM and data • Plan includes tasks necessary to successfully perform • NOMCR Checkout and Network Model Verification • LFC Testing ERCOT system • Other EDS activities • Also includes activities to support multi-vendor interoperability test at ERCOT • ERCOT will continue to provide periodic updates to TPTF on progress to date TPTF