Forward pass rules
This presentation is the property of its rightful owner.
Sponsored Links
1 / 1

Forward Pass Rules PowerPoint PPT Presentation


  • 45 Views
  • Uploaded on
  • Presentation posted in: General

Forward Pass Rules. Rule 1: The initial project event is assumed to occur at time zero Rule 2: All activities are assumed to start as soon as possible, that is, as soon as all the predecessor activities are completed.

Download Presentation

Forward Pass Rules

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Forward pass rules

Forward Pass Rules

Rule 1: The initial project event is assumed to occur at time zero

Rule 2: All activities are assumed to start as soon as possible, that is, as soon as all the predecessor activities are completed.

Rule 3: The early finish time of an activity is merely the sum of its early start date and the estimated activity duration.