Townsend schools biomass project
Download
1 / 21

Townsend Schools Biomass Project - PowerPoint PPT Presentation


  • 108 Views
  • Uploaded on

Townsend Schools Biomass Project. Project Overview. Project Beginning. December 16, 2003 Superintendent attends Bio-Energy workshop in Helena, Montana September 3, 2004 CTA Architects completes pre-feasibility assessment February 15, 2005 School District applies for Fuels For Schools Grant

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Townsend Schools Biomass Project' - chogan


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

Project beginning
Project Beginning

December 16, 2003 Superintendent attends Bio-Energy workshop in Helena, Montana

September 3, 2004 CTA Architects completes pre-feasibility assessment

February 15, 2005 School District applies for Fuels For Schools Grant

April 26, 2005 School Receives Fuels For Schools Grant


Project construction the big dig starts august 16 2006
Project Construction-TheBig Dig Starts August 16, 2006


Project construction pellet silo install photos inside out
Project Construction- Pellet Silo install, photos inside & out


Project construction hopper boilers drop in
Project Construction-Hopper& Boilers Drop In


Project construction hook ups and connections
Project Construction-Hook-ups and Connections


Project construction doors and building connects
Project Construction-Doors and Building Connects


Project construction pellets arrival unloading
Project Construction-Pellets Arrival & Unloading












System costs funding
System Costs & Funding

* Other costs to the project included interim loan interest (until USDA loan became active), asbestos abatement, hot water heater relocation, purchase of a used auger to load pellets, etc. The majority of these costs were covered by the project contingencies and the $30,000 USDA grant.


Problems addressed time line for project
Problems Addressed & Time Line for Project

• Asbestos discovered & removed

• Water heater had to be relocated

• Pellet “Clinkers”

• Ash removal system needed

• Stack Extension needed

• Time Line – Two (2) years

Grant was filed in Feb. 05, ribbon cutting ceremony March 07


District savings with system
District Savings with System

The Silos will hold 60 tons of pellets.

Expected use by school: 250 tons of pellets per year

1st year predicted annual savings using pellets - $23,000.00

(This increases as non-renewable fuel costs increase, predicted savings to be $35,000 per year in 10 years)

Savings in fuel costs are predicted to pay for system within seven to eight years

Predicted savings to the school over 30 year period - $1.2 Million

(These are the predicted savings AFTER the district cost of the system has been repaid)


ad