Protocol Revision Subcommittee. Tom Burke July 2, 2013. Summary of Revision Requests. 3 NPRRs Recommended for Approval 1 NPRR Rejected. Items for a Vote. Unopposed Recommendations NPRR538 , Clarification of the Non-Spin Energy Offer Curve Requirements for QSGRs*

Download Presentation

Protocol Revision Subcommittee

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Protocol Revision Subcommittee

Tom Burke

July 2, 2013


Summary of Revision Requests

3 NPRRs Recommended for Approval

1 NPRR Rejected


Items for a Vote

Unopposed Recommendations

NPRR538, Clarification of the Non-Spin Energy Offer Curve Requirements for QSGRs*

Recommendations with Opposing Votes

NPRR539, Amend Wholesale Storage Load Definition*

NPRR519, Exemption of ERS-Only QSEs from Collateral and Capitalization Requirements

Rejected Revision Requests

NPRR544, Energy Offer Curve Requirements for Generation Resources Assigned Non-Spin Responsibility

(* denotes no impacts)


NPRR Descriptions

NPRRs Recommended for Approval


NPRR519, Exemption of ERS-Only QSEs from Collateral and Capitalization Requirements


NPRR538, Clarification of the Non-Spin Energy Offer Curve Requirements for QSGRs


NPRR539, Amend Wholesale Storage Load Definition


NPRR Descriptions

NPRRs Rejected


NPRR544, Energy Offer Curve Requirements for Generation Resources Assigned Non-Spin Responsibility


Additional PRS Items

  • PRS completed updating the “Guiding Principles for ERCOT Project Prioritization” which is posted on the PRS website.