APX Project Plan. Kickoff 6 November 2001. Table of Contents. Contractual Milestones Project Timeline Project Deliverables APX Project Organization Communication/Contact Plan NEPOOL & NE-ISO Personnel Requirements REC System Test Drive. Contractual Milestones.

Download Presentation

APX Project Plan

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Apx project plan

APX Project Plan

Kickoff

6 November 2001


Table of contents

Table of Contents

  • Contractual Milestones

  • Project Timeline

  • Project Deliverables

  • APX Project Organization

  • Communication/Contact Plan

  • NEPOOL & NE-ISO Personnel Requirements

  • REC System Test Drive


Contractual milestones

Contractual Milestones


Project timeline phase 1

Project Timeline - Phase 1


Project timeline phase 2 3

Project Timeline - Phase 2/3


Project deliverables

Project Deliverables

Delivery DateFeedback By

  • Bi-Weekly Status Report1st - Nov 12, 2001

  • Project PlanNov 26, 2001

  • Statement of WorkNov 26, 2001Dec 3, 2001

  • System Requirements DocumentDec 10, 2001Dec 17, 2001

  • SDR AgendaDec 31, 2001Jan 10, 2002

  • SDR PackageJan 8, 2002

  • System Design DocumentJan 14, 2002Jan 24, 2002

  • System Test PlanJan 18, 2002Jan 25, 2002

  • Training PlanMar 18, 2002Apr 25, 2002

  • System Test ReportMar 29, 2002

  • Training Documentation Mar 29, 2002

  • Operational Acceptance Test ReportApr 19, 2002


Apx project organization

APX Project Organization

  • Business/Site Manager – Gary Zielanski

  • Project Manager - Tom Hickey

  • System Requirements - Michael Rucker

  • Lead Engineer - Hung Chau

  • System Test Engineer – Charles Kominczak

  • Quality Assurance Lead – Roy Gvirtsman

  • Software Engineer - Welock Kam

  • Director, Information Technology - Mike Johnson


Apx project organization1

APX Project Organization


Communication contact plan

Communication/Contact Plan


Nepool ne iso personnel requirements

NEPOOL/NE-ISO Personnel Requirements

Phase 1 – Definition & Design

  • Working Group Support

  • NEPOOL MSS Interface Design

  • Document Feedback

  • SRR & SDR Attendance & Involvement

    Phase 2 – Development

  • Working Group Support (As needed)

  • Document Feedback

  • Integration to the NEPOOL MSS

    Phase 3 – Training & Operations

  • Feedback on Training Documentation

  • Support for Training Logistics

  • Feedback on Training

  • Operational Acceptance Test Attendance & Involvement


Apx project plan

REC System Test Drive


Test drive the rec system

Test Drive The REC System

http://testrec.apx.com/Login Name = apx2 - apx250

Passwords = txrec


  • Login