APX Project Plan. Kickoff 6 November 2001. Table of Contents. Contractual Milestones Project Timeline Project Deliverables APX Project Organization Communication/Contact Plan NEPOOL & NE-ISO Personnel Requirements REC System Test Drive. Contractual Milestones.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' APX Project Plan' - chancellor-wheeler


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Apx project plan

APX Project Plan

Kickoff

6 November 2001


Table of contents
Table of Contents

  • Contractual Milestones

  • Project Timeline

  • Project Deliverables

  • APX Project Organization

  • Communication/Contact Plan

  • NEPOOL & NE-ISO Personnel Requirements

  • REC System Test Drive





Project deliverables
Project Deliverables

Delivery DateFeedback By

  • Bi-Weekly Status Report 1st - Nov 12, 2001

  • Project Plan Nov 26, 2001

  • Statement of Work Nov 26, 2001 Dec 3, 2001

  • System Requirements Document Dec 10, 2001 Dec 17, 2001

  • SDR Agenda Dec 31, 2001 Jan 10, 2002

  • SDR Package Jan 8, 2002

  • System Design Document Jan 14, 2002 Jan 24, 2002

  • System Test Plan Jan 18, 2002 Jan 25, 2002

  • Training Plan Mar 18, 2002 Apr 25, 2002

  • System Test Report Mar 29, 2002

  • Training Documentation Mar 29, 2002

  • Operational Acceptance Test Report Apr 19, 2002


Apx project organization
APX Project Organization

  • Business/Site Manager – Gary Zielanski

  • Project Manager - Tom Hickey

  • System Requirements - Michael Rucker

  • Lead Engineer - Hung Chau

  • System Test Engineer – Charles Kominczak

  • Quality Assurance Lead – Roy Gvirtsman

  • Software Engineer - Welock Kam

  • Director, Information Technology - Mike Johnson




Nepool ne iso personnel requirements
NEPOOL/NE-ISO Personnel Requirements

Phase 1 – Definition & Design

  • Working Group Support

  • NEPOOL MSS Interface Design

  • Document Feedback

  • SRR & SDR Attendance & Involvement

    Phase 2 – Development

  • Working Group Support (As needed)

  • Document Feedback

  • Integration to the NEPOOL MSS

    Phase 3 – Training & Operations

  • Feedback on Training Documentation

  • Support for Training Logistics

  • Feedback on Training

  • Operational Acceptance Test Attendance & Involvement



Test drive the rec system