1 / 12

Evaluation of LH e C Ring-ring Installation Issues

Discussions with : Helmut Burkhardt Miriam Fitterer Max Klein Karl-Hubert Mess Yvon Muttoni John-Andrew Osborne Stefan Roesler Many thanks to all . Evaluation of LH e C Ring-ring Installation Issues . Overview. Ring-Ring Geometry

celina
Download Presentation

Evaluation of LH e C Ring-ring Installation Issues

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Discussions with: Helmut Burkhardt Miriam Fitterer Max Klein Karl-Hubert Mess Yvon Muttoni John-Andrew Osborne Stefan Roesler Manythanks to all Evaluation of LHeC Ring-ring Installation Issues Sylvain Weisz - CERN/DG-DI-DAT

  2. Overview • Ring-Ring Geometry • Junction of the e-ring by-passes with LHC tunnel • Integration challenges • Machine protection • Installation schedule Sylvain Weisz - CERN/DG-DI-DAT

  3. Geometry of the LHeC Ring-Ring option Two by-passes foreseen in the CDR CMS LHCb ATLAS Need to consider a 3rd by-pass Sylvain Weisz - CERN/DG-DI-DAT

  4. LHeC Ring-Ring Geometry: compensation for additional by-pass lengths e beam offset of 61cm / LHC mean axis 3rd by-pass length compensation would move the beam ~30cm furtherinto the transport reserved area Spaceoriginallyallocated to a future e ring Sylvain Weisz - CERN/DG-DI-DAT

  5. Geometry of the LHeC Ring-Ring option • Compensation of the by-passes lengths brings the e-ring into the LHC transport area; • Sliding supports required to move out the e-ring will be very delicate (precision, stability); • Integration in the existing installation has to cope with all intermediate positions; • Need to separate elements or synchronize movements along un-interrupted sections. There is a strong incentive to review the requirement of equal lengths of the proton and electron rings Sylvain Weisz - CERN/DG-DI-DAT

  6. Junction of the e-ring by-passes with LHC tunnel The bending radius of the LHC dipoles is 2804 m  an electron beam going straight needs 75 m to move 1 m sideway from the proton trajectory Sylvain Weisz - CERN/DG-DI-DAT

  7. Junction of the e-ring by-passes with LHC tunnel LHC main tunnel Injection line at Point 8 Thickness of separation wall is about 1 m Sylvain Weisz - CERN/DG-DI-DAT

  8. Integration challenges Sylvain Weisz - CERN/DG-DI-DAT

  9. Integration challenges and Machine protection • Access to equipment for maintenance and repair has to be maintained; • Many areas will be highly activated as LHC luminosity increase:  Interventions need to be optimized to keep workers expositions below acceptable threshold; • LHC beam loss monitors will be sensitive to synchrotron radiation from the e-beam:  Shielding of monitors means extra space, extra material activated and also extra difficulties/time for interventions. Sylvain Weisz - CERN/DG-DI-DAT

  10. Installation schedule: Interference with LHC operation • CE for new shafts and klystron galleries can probably proceed while LHC is running; • However, it is not the case of the by-passes:  we need 7m of earth to shield a working area from an accidental LHC beam loss; • Need to dismount LHC in the junction areas to be digged: • The cryo-magnets would be disconnected and stored on surface, • The cryo-line would also be dismounted, • All services have to be removed, • The CE work-site has to be sealed for dust, but ventilation must be maintained in the LHC to control temperature/dew point.  Assume ~6 months before CE can start in the junction areas Sylvain Weisz - CERN/DG-DI-DAT

  11. Installation schedule: Interference with LHC operation • CE to complete the first junction areas (digging, water-proofing, concreting) would take ~6 months; • The completion of the 3 by-passes (1km each) and of the 6 junction areas would take another year (see John Osborne) • The installation of services for the e-ring can be evaluated to last 2 years (LEP and LHC experience), out of which 1 year overlaps with civil engineering; • The installation of the e-ring elements would also take 2 years, out of which half could overlap with the services:  ~1 year of installation on the critical path  the re-installation and commissioning of LHC could occur in // (managing of co-activities will be challenging) Sylvain Weisz - CERN/DG-DI-DAT

  12. Summary • The LHeC CDR is very complete and adresses most of the issues presented • The complete integration study will be challenging: • Number of by-passes must be reviewed • Constraints on e-ring circumferences must be clarified • Interventions must be optimized in light of RP requirements • The installation of the e-ring in the LHC tunnel will have a strong impact on the LHC operation Sylvain Weisz - CERN/DG-DI-DAT

More Related