Sears Point Restoration Project Update – Napa-Sonoma Marshes Planning Group November 10, 2009

Sears Point Restoration Project Update – Napa-Sonoma Marshes Planning Group November 10, 2009. John Brosnan Baylands Program Manager. Planning to date. 2004-2007 Conceptual Plan, comment response Preliminary plans, technical peer review 2007-2009 Draft EIR/EIS, begin permitting

casper
Download Presentation

Sears Point Restoration Project Update – Napa-Sonoma Marshes Planning Group November 10, 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sears Point Restoration Project Update – Napa-Sonoma Marshes Planning GroupNovember 10, 2009 John Brosnan Baylands Program Manager

  2. Planning to date 2004-2007 • Conceptual Plan, comment response • Preliminary plans, technical peer review 2007-2009 • Draft EIR/EIS, begin permitting • Stakeholder consultation, fundraising

  3. The past 5 years Project Management • SLT: John Brosnan, Wendy Eliot, Bob Neale • Restoration Planning: Wetlands and Water Resources, FarWest, Peter Baye, Vollmar Consulting, Hildie Spautz, Lisa Bush, Northgate Environmental, Markus Niebanck, Larry Daniels, Hultgren-Tillis, Questa Engineering, Moffatt & Nichol • CEQA/NEPA: Jones & Stokes, Ducks Unlimited • Design/Construction: Ducks Unlimited

  4. Sears Point Restoration Project Team

  5. Seasonal wetlands and farming

  6. California red-legged frog enhancement • 15.5 acres total • Exclusion fencing • Breeding ponds • Frogs are present

  7. Planning CEQA/NEPA/Permits Construction 2008 2009 2011 2007 2012-2013 2010 Planning timeline ahead 2009 Draft NEPA/CEQA and fundraising 2010 FEIR/EIS, permits, design refinement 2011-2013 Final specs and construction