An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Coach House Restaurant / Bar Cuong Le MSIT 573 IT Upgrade Project

  2. Background of the Coach House • Oldest restaurant located in Scottsdale, Arizona • a quality small-sized restaurant/bar • An excellent place for food • A great place for socializing or relaxing

  3. Problems Statements • to maintain and to bring the restaurant to a new business level • to increase its profits • Ordering process is still heavily depended on human factors • Unwanted loss due to theft • Restaurant is not a place for relaxing after a day of hard work.

  4. Project Objectives & Scopes • Strategic goals of the Coach House are to guarantee its continuing growth and to increase profitability • A Computerized Ordering System • Security Cameras • Table-to-table Wireless Messaging along with game playing capability • Computer system and monitor at each table

  5. Cost/Benefits Analysis (1) • Increase customer satisfaction  an increase of $60,000/year • Internal cost reduction  6 employees or $78,000/year • Advertisement revenue  $36,000/year

  6. Cost/Benefits Analysis (2) • Computerized ordering system  $20,000 • Security Cameras  $2,000 • Cost of installing monitors  $36,000 • Labor cost: 3 weeks  $8,840 • Cost of maintenance  $4,200/year

  7. Cost/Benefits Analysis (3) • NPV is $393,816 • ROI is 400%  This is a very promising IT project and is worthy to implement

  8. Projected Timelines • Project is to be completed in 3 weeks • Research and ordering can be done on the day time. • Implemented in 4 phases: • Wireless network • Computerized ordering system • Security cameras & Monitor installation • Integration testing and system release

  9. PROJECT TIMELINE MAJOR MILESTONES (DATE) Start Date 07/18/2005 Project Start 07/18/05 Finish Date 08/07/2005 Construction of Wireless network 07/29/05 Duration in Days 3 weeks Completion of Computerized Ordering System 08/02/05 Total Work Hours 213 hours Completion of Terminals & Monitors & Security Cameras 08/05/05 Number of tasks 41 tasks Closing Celebration 08/07/05 ProjectWork Breakdown Structure

  10. Risk Analysis • Lack of interest from employees and customers • Users’ input • Help them realize the potential benefits • Use of no fancy technology Technical risks are minimal • Main business risk: investing lots of effort without realizing potential benefits.

  11. Project Implementation • Project will be implemented in using a parallel methodology • All phases of this project will be assigned to the project team led by project managers • Thorough testing at each phase and a final integration test • New system is scheduled to release.

  12. Questions ????