Northwest Huntersville Transportation Study. Mecklenburg-Union TCC August 4, 2011. Overview Objectives. Project history Alternatives overview Decision process Citizen input Remaining issues Schedule. 1988- Vance Rd Ext added to Thoroughfare Plan.

Download Presentation

Northwest Huntersville Transportation Study

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Northwest Huntersville Transportation Study

Mecklenburg-Union TCC

August 4, 2011


Overview Objectives

  • Project history

  • Alternatives overview

  • Decision process

  • Citizen input

  • Remaining issues

  • Schedule


1988- Vance Rd Ext added to Thoroughfare Plan


May 2004, Vance Rd Ext alignment defined


Sept 2004, NC 73 Corridor Study recommends alternate intersection


Suggested alternative intersection


Recommended NC 73 cross-sectionwest of Vance Rd Ext.

Source: NC 73 Transportation/Land Use Corridor Plan


Sept 2007, Beatties Ford Rd SAPnew road alignments


Public Workshops

  • December 2007, general area discussion

  • April 2008, Option 1 displayed

  • October 2008, Options 1,2, & 3 displayed

  • May 2011, Options 1, 3 (revised), & 4 displayed


Citizen Comments

  • Displayed verbatim on website

  • Generally, favor option that moves road away from them

  • Concerns about property values, impacts to Lake Norman, hazard to Southlake Christian school

  • Concern about “choke point” at river


Traditional Impact Measures


Remaining Issues

  • McGuire Nuclear Station

    • Intersection with old NC 73 under Option 3

    • Equipment crossing of NC 73

  • Shopping Center access @ Beatties Ford Rd under Option 3.

  • Access management along new road under Options 3 & 4.

  • Hubbard Road intersection and impact to Hubbard Road under Option 3.

  • Alteration of NC 73 Corridor Plan

  • Justification of new road on new alignment if that is the better option (CTP problem statement)


Schedule

  • August 4 TCC overview

  • August 23 Huntersville Planning Board recommendation

  • September 1 TCC recommendation

  • September 6 Huntersville Town Board recommendation

  • September 19 optional Huntersville recommendation

  • September 21 MUMPO presentation and possible decision

  • November 16 Optional MUMPO decision date