LCLS
Download
1 / 1

LCLS Injector Commissioning Dates (2006 - 2007) - PowerPoint PPT Presentation


  • 55 Views
  • Uploaded on

LCLS Injector Commissioning Dates (2006 - 2007). Dec 22: PPS Certified Dec 20-Jan 1: Holidays Jan 2: VVS’s switched on for PEP-II (RF power available) Jan 15: L0a, L0b, L1 RF processing begins Feb. 1: X-band RF processing begins Feb 20: GTL beamline installation complete

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' LCLS Injector Commissioning Dates (2006 - 2007)' - camille-vaughn


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

LCLS Injector Commissioning Dates (2006 - 2007)

Dec 22: PPS Certified

Dec 20-Jan 1:Holidays

Jan 2: VVS’s switched on for PEP-II (RF power available)

Jan 15: L0a, L0b, L1 RF processing begins

Feb. 1: X-band RF processing begins

Feb 20: GTL beamline installation complete

Mar 6: Virtual cathode fully characterized (ready to install gun)

Mar 7: RG gun installation begins – laser rate to 30 Hz

Mar 16:First laser UV-light on cathode!

Mar 17: Electrons in GTL and gun-spectrometer

Apr 9: Beam through L0a, L0b and down to 135-MeV spectrometer

Apr 24: Beam into main linac (to TD11 dump)

~July: Take beam down full linac (to BSY SL2 stopper)

Aug 31: Shutdown