An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BTS OFF-Line commissioningProcedure OF ALCATEL BTS using B10 Prepared By: Umair Akram Warraich Bss Engineer Project Manager 3G ALU MC-RRH Project North Region Turnotech Solutions Turnotech Solutions

  2. Switch OFF the BTS cabinet and disconnect Abis connectors from DDF before offline start Turnotech Solutions

  3. Disconnect the Abis connector from The DDF Turnotech Solutions

  4. Switch ON the BTS cabinet breakers and connect the Laptop with BTS Turnotech Solutions

  5. User Name “COMMTE” Password “COMMTE” Turnotech Solutions

  6. Communication Port setting Turnotech Solutions

  7. After connecting this window will be appear Turnotech Solutions

  8. Go to Configuration-> BTS-SW Download-> to download BTS software Turnotech Solutions

  9. After BTS-SW download this window will appear Turnotech Solutions

  10. Go to offline Files and select First File of Master File. Turnotech Solutions

  11. Go to offline Files and select First File of DDL file. Turnotech Solutions

  12. Click ok to start downloading SW Turnotech Solutions

  13. BTS software starts to download. Turnotech Solutions

  14. All these Files are downloaded Turnotech Solutions

  15. Go to Configuration BTS commissioning Turnotech Solutions

  16. Click start commissioning Turnotech Solutions

  17. Edit Qmux Address Turnotech Solutions

  18. Edit sector Mapping Turnotech Solutions

  19. Check All Twin TRE’s. Turnotech Solutions

  20. Click End Commissioning Click << arrow to move selected modules to available modules Turnotech Solutions

  21. All modules Shifted to update modules. Turnotech Solutions

  22. Click No to end Turnotech Solutions

  23. Reconnect the Abis connector at DDF by verifying the TX/RX cables properly Turnotech Solutions

  24. Give Hard Reset to BTS cabinet as the OML has established to put the site on Downloading. Turnotech Solutions

  25. OFF Line Commissioning Completed Successfully. Turnotech Solutions

  26. BTS ON-Line commissioningProcedure using B10 Go to configuration>> Hardware setting>>Begin HW modification Turnotech Solutions

  27. Go to configuration> BTS commissioning Go to start commissioning> Edit Q1 Address, Edit Sector Mapping and Twin TRA setting as in offline. Turnotech Solutions

  28. Go to configuration> Hardware setting>“End Modification” to end online commissioning Turnotech Solutions

  29. Online commissioning steps • Connect the Abis connector at DDF by verifying Tx/Rx cable properly. • OML will be established after primary Abis has connected to DDF. • Give hard reset to BTS after OML has established. • Put site on Downloading from OMC. • O&M will be established as downloading completes. • Connect Laptop to BTS MMI port. • Go to configuration>Hardware setting>Begin Hardware modification. Turnotech Solutions

  30. Online commissioning steps • Go to configuration>BTS commissioning>start commissioning. • Edit Qmux Address • Edit sector mapping • Check all Twin TRA setting. • Click end commissioning and shift all modules from selected modules to available modules. • Go to configuration>Hardware setting>End Hardware modification. • Click “yes” when an automatically hardware modification window appears. • Hw Audit will be run and all Hardware will be shown after sometime. Turnotech Solutions

  31. ON Line Commissioning Completed Successfully. Turnotech Solutions

  32. Software components combiner Fan Unit Hardware Shown in software window Tre’s clock Alarm card Turnotech Solutions

  33. Alarms window Turnotech Solutions

  34. Transceivers Shown in window Turnotech Solutions

  35. Transceivers Types • Four type of Transceivers in Alcatel Equipment • TRAGE>Gsm Single TRE • TRADE>Dcs single TRE • TGT09>Gsm Twin TRE • TGT18>DCS Twin TRE • TAGHE>High power TRE Turnotech Solutions

  36. VSWR Shown in window Turnotech Solutions

  37. Sectors Shown In window Turnotech Solutions

  38. Station units Turnotech Solutions

  39. BSC SBLs (security block levels) BTS OM & Sectors.Sec RSLs can be unlock from local Terminal. Turnotech Solutions

  40. Troubleshooting • If a TRE or combiner is in “Not Operational” or “FOS” state then disable it then initialize it by using “init” command. • If TRE or combiner can not operational by doing above command then remove it by using the following method. • Go to configuration>>Hardware setting>>Begin HW modification. • Go to Configuration>>Hardware setting>>Remove. • Remove the Hardware from BTS. • Window will be appear of Hardware removal, select the module to remove. • Go to Configuration>>Hardware setting>>End Modification. • Click ”yes” when configuration changes window appears. Turnotech Solutions

  41. Hardware Removal Method Step:1 Turnotech Solutions

  42. Hardware Removal Step:2 Turnotech Solutions

  43. Hardware Removal Step:3 Turnotech Solutions

  44. Troubleshooting cont.. • When a module goes in “FOS” state then it must be disable by using ”disable” command before initializing it by using “init” command otherwise it will not goes to operational state. • When a module is in “Not Operational” state with color white then it means it has not got it’s RSL number still. Reload BTS data by going to “configuration>Reload Bts data” or using a method of “Begin Hardware then End Hardware” as discussed earlier. It will take some time to become operational. • When a module is in “MSD” or “MSA” state then it will not get any command because its maintenance has seized for a while. • When TRE RSL has locked then then its RSL will not be stable, so unlock the TRE from OMC. Turnotech Solutions

  45. Troubleshooting cont.. • Sometime there is some faulty hardware in Bts that’s why other sectors or TRE’s can effect and can not work properly. Due to these faulty hardware other sectors or TRE’s can be down so simply remove this hardware. By this method other hardware become in operational state. • Some time “SUMA” can not work properly that’s why whole Bts effects so change the slot of “SUMA” and give hard reset to Bts. • If modules in a shelf can not powers up then check it’s power cable at the back ports of Bts or check it “RI” cable. Also check the power switch for the concern shelf. • If a “EACB” card is Not operational or “FIT” state then initialize it from software. If it again goes in “FIT” state then Alarm card is faulty. Turnotech Solutions

  46. Troubleshooting cont.. • Some time Primary Abis is stable by showing LED on Suma card but OML can not become stable, It means that Abis LED is fake. So check the Tx/Rx cable from both Bts end and microwave end and make sure that it is correctly connected. Also check Tx/Rx patching on DDF by using LED. Make sure that LED blinks on every pair on DDF. Also check the BNC and Abis connectors. Abis cable which is connected from Suma card to Bts board can be faulty so also verify it. • If a TRE or combiner can not operational than change its slot then verify it. • Vswr issues can be resolved by checking connectors from Bts end and feeder end. • The last option for Alcatel equipment to become operational is the “Hard reset of Bts”. Turnotech Solutions

  47. External Alarms of MBO2 Turnotech Solutions

  48. ALCATEL GLOSSARY A AN Antenna Network B BCB BTS Control Bus BSII Base Station Controller BSS Base Station Subsystem BTS Base Station Transceiver BTSW BTS-Terminal for Windows C CCF Cabinet Cooling Fan CDM Configuration Data Message CLEI Common Language Equipment CLLK Clock Link CPF Configuration Parameter File CRC Cyclic Redundancy Check CU Carrier Unit Turnotech Solutions

  49. ALCATEL GLOSSARY D DC Direct Current DMA Deferred Maintenance Alarm E EQU Equipped F FIA Format Identifier for Application part of RI FIM Format Identifier Manufacturing FIT Faulty In Traffic FLT Faulty FOS Faulty Out of Service ICS Item Change Status IT In Traffic L LDA Local Defence Action LRA Local Recovery Action M MI Maintenance Information MSA MSD Auto MSD Maintenance Seized Turnotech Solutions

  50. ALCATEL GLOSSARY N NEQ Not Equipped NOP Not Operational O O&M Operation and Maintenance OMU Operation and Maintenance Unit OMUA OMU A RIT OMUB OMU B RIT OP Operational OPR Operator P PADD Physical Address PMA Prompt Maintenance Turnotech Solutions