An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Summary Session 4 – Quench Detection R. Denz, D. E. Rasmussen

  2. Part 1: Jens and the “impressive” list … Firmware upgrades by EP section, concerning QPS supervision Firmware upgrades quench detection R2E mandatory for re-start Upgrades for enhanced diagnostics

  3. The list continued … • List represents a major challenge with respect to hardware upgrades with limited contingency • Possible bottleneck can be the production especially the assembly of circuit boards • Major parts of electronic components ordered and partially delivered • Some activities are not mandatory to re-start (DQAMS600, DQGPU type A,B …) • Some activities like the potential CSCM upgrade are not yet specified • Firmware upgrades are well under control as EP internal • Strong recommendation to treat nQPS (DQLPU type S) part separately • Avoids to install racks DYPB in specific position • Allows flexibility with respect to an eventual CSCM upgrade • Standard transport and intermediate storage represent a non-negligible risk for the sophisticated DQLPU type S

  4. Part 2: Arek, software development for QPS regarding LS1 • The upgrade of the QPS will bring many new features requiring high level software tools to make the best use out of it. • Concerns as well a long list of activities: • Configuration database • CSCM data analysis • Enhanced quench heater supervision analysis tools • Power cycle tools • EE maintenance service • … • Necessary resources clearly identified (within SCRUM framework) • First applications already available, e.g. power cycle tools

  5. Numbers and resources 0 • 134story points with 16 Before LS1 • 50story points with 10 Before LS1 A. Gorzawski, TE-MPE LS1 preparation workshop • Total team work capacity: ~350 StPuntil end of LS1(Shared between 9 projects) • QPS & Systems Management: • 184 StP required • ~ 52% of budget