Lmg forum november 2010
Download
1 / 10

LMG Forum November 2010 - PowerPoint PPT Presentation


  • 210 Views
  • Uploaded on

LMG Forum November 2010. Christopher Croft, LMGS Rob Gillies, LMA Philip Godwin, Lloyd’s. Agenda. Modernisation this month Endorsements pilot update Claims Transformation Programme. ECF2 Current Status. Document File Viewer Bulk Conversion. LOAD. EXTRACT. PDF & OCR CONVERSION. DFV

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' LMG Forum November 2010' - caldwell-douglas


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Lmg forum november 2010

LMG ForumNovember 2010

Christopher Croft, LMGSRob Gillies, LMAPhilip Godwin, Lloyd’s


Agenda
Agenda

  • Modernisation this month

  • Endorsements pilot update

  • Claims Transformation Programme



Document file viewer bulk conversion
Document File Viewer Bulk Conversion

LOAD

EXTRACT

PDF & OCR

CONVERSION

DFV

STORE

IMR

4.5 million

Documents

extracted

2.814 million

Converted

As of 12/11/10

ADOBE

AUTONOMY

CAPITAL CAPTURE

Due to start week beginning 15/11/10

% in error = 0.2%

(majority were zip files which are now resolved)

% in error <1%

(majority are password protect errors)



Eaccounts
eAccounts

  • eAccounts Release 1B (R1B)

  • 67% of all MAT test steps are complete

  • MAT with Miller is tracking to completion in week beginning 15/11

  • Aon preparing begin Broker Acceptance Testing in December - dependent on Miller passing MAT

  • eAccounts Release 2 (R2)

  • No immediate R2 dependency on completing R1b

  • Work has started – detailed planning and review of functional specs and requirements


2011 workplan
2011 Workplan

  • Draft workplan approved by LMG

  • Ensuring targets are challenging but sensible

  • Final sign off 9th December


Non bureau business

insurers

insurers

brokers

brokers

re

re

-

-

insurers

insurers

industry utility

industry hub

services

services

Non bureau business

  • Group in place with representatives from:

    • Aon

    • Willis

    • Marsh

    • Ace

    • Chartis

    • Chubb

    • XL Re

    • RSA

  • Seeking to become the London Rüschlikon Steering Group

  • Plan to LMG 9th December


Future processing model
Future Processing model

  • Consultation document at Steering Group tomorrow

  • Then to LMG 9th December

  • Published thereafter…