Full Depth Shoulders In Wisconsin – Follow-Up

Full Depth Shoulders In Wisconsin – Follow-Up. Steve Krebs and Jed Peters– DTSD-Bureau of Technical Services July 29, 2013. Requests from Previous Meeting . Non-Conservative Costs 4 Policy Options with Implementation Costs FDM Work Zone Delay Restricted Corridors

caelan
Download Presentation

Full Depth Shoulders In Wisconsin – Follow-Up

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Full Depth Shoulders In Wisconsin – Follow-Up Steve Krebs and Jed Peters– DTSD-Bureau of Technical Services July 29, 2013

  2. Requests from Previous Meeting • Non-Conservative Costs • 4 Policy Options with Implementation Costs • FDM Work Zone Delay Restricted Corridors • High Volume Arterials (color coded peak hour volume map) • TOIP • Freight Network

  3. FDS Construction and Cost Considerations - Review • 10 Projects Analyzed • 8 Concrete Mainline • 2 HMA Mainline • As-built and Estimated FDS Costs

  4. Shoulder Construction Cost Summary (Non-Conservative) • Concrete Mainline Projects • As-built average (avg) cost: $182,920/mile • FDS HMA avg cost: $346,430/mile • FDS concrete avg cost: $265,000/mile • HMA Mainline Projects • As-built avg cost: $123,320/mile • FDS HMA avg cost: $171,600/mile

  5. Non-Conservative LCCA– Summary (Estimated Shoulder Reconstruct at 28 Years) • Concrete Mainline Projects • As-built avg net present value (NPV) life-cycle 50 year cost: $354,120/mile (Original Value: $276,720) • FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile • FDS concrete avg NPV life-cycle 50 year cost : $345,140/mile • HMA Mainline Projects • As-built avg NPV life-cycle 50 year cost : $250,230/mile (orig: $198,050) • FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile * NPV calculated with 3.5% discount rate

  6. Non-Conservative Benefit Cost Analysis– Summary

  7. IH-39 Case Study Cost Summary • Estimated As-Built Construction Cost/Mile • Estimated 10” FDS Construction Cost/Mile • Life Cycle Adjusted to Reflect True Life-To-Date • Minimal/Negligible maintenance costs • 2012 Project (Year 28 of life cycle)- 8” Shoulders Let Cost/Mile • $333,850/mile • Adjusted LCCA Costs • As-built NPV = $519,200/mile • FDS NPV = $483,850/mile

  8. Previous Recommendations • Selective Application of FDS • High-Volume Arterial Corridors • Mass Evacuation Routes • Incorporate FDS (Existing and Future) into Emergency Planning

  9. Recommendations/Policy Options Investigated at Request of Committee • Selective Application of FDS • FDM Delay Corridors • High Volume Arterials • TOIP • Freight

  10. FDM Delay Restricted Corridors 1670 Miles

  11. High-Volume Arterial Corridors :1580 Miles :1270 Miles Volumes Estimated For Highest Direction in 30th Highest Hour in 2013 : 1180 Miles : 1070 Miles : 850 Miles

  12. TOIP Priority Corridors: 1190 Miles

  13. OSOW Not Investigated as Stand-Alone

  14. Weighted Freight Map ~Equivalent to Backbone System

  15. Policy Cost Implications • High Volume Arterials ($0.89 – $1.3 Billion) • $350 - $518 Million More than Conventional HMA • $89 - $98 Million Less than Minimum Concrete • TOIP Priority Corridors ($985 Million) • $390 Million More than Conventional HMA • $99 Million Less than Minimum Concrete • FDM Delay Restricted Routes ($1.4 Billion) • $548 Million More than Conventional HMA • $139 Million Less than Minimum Concrete • Freight Routes = Backbone System ($1.3 Billion) • $518 Million More than Conventional HMA • $131 Million Less than Minimum Concrete

  16. Final Policy Recommendation • Factor of All (High Volume Arterials, TOIP, Freight, and FDM Delay Corridors) • Driving Need: Traffic Demand • 1000 VPH (2013 data)

  17. Recommended Applications 1180 Miles

  18. Policy Cost Implications • Total Cost • FDS: $977 Million • HMA Conventional: $590 Million • Minimum Concrete: $1.1 Billion • FDS Average Annual Cost (Average of 30 Reconstruct or Pavement Replacement projects with 18 Miles/Year) • FDS: $14.9 Million • HMA Conventional: $9 Million • Minimum Concrete: $16.4 Million • Nearly 150 Miles ($119 Million) Completed or Planned • N-S Freeway, Zoo Freeway, IH-39, USH 41

  19. Questions?