This plan outlines the development process for six firmware versions, including individual, probe, ITB, beam, Phase-2 sector, and the final version. The readout software is backwards compatible, and the command generator can generate commands for all tests. The control commands are the same between DDL and USB.

bryckman
Download Presentation

Xiangming Sun

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Xiangming Sun L. Greiner, H. Matis T. Stezelberger M. Szelezniak C. Vu H. Wieman … …

  2. Firmware and software development plan there are six firmware versions: individual test probe test ITBtest beam test Phase-2 sector test final version most modules are shared among all these versions. readout software is backwards compatible the command generator for the final version can generate commands for all tests. readout software source codes are portble between linux and windows the control commands are the same between DDL and USB

  3. task description • individual test • single sensor are connected. • probe test • sensor are put on probe station and power supply are controlled • ITB test • 10 sensor are connected in parallel, long cable are used • beam test • sensers are built into a telescope. Trigger is included • Phase-2 sector test : • more than 2 sectors are connected. Trigger is included • final version: • 40 sensors are connected. Long cables are used. Trigger is included

  4. Firmware status finished on-going JTAG ADC IO delay I2C ADC System control Frame fifo Info machine Event machine SRAM fifo DDL USB

  5. Firmware and software status for all stages individual test finished on-going probe test ITB test In ITB test, event mode functionality is working and implemented in the IOdelay function. This is the first test of event machine module. beam test Phase-2 sector test final version readout software is ready for individual test,probe test, ITB test. event mode readout software is on-going.

  6. Future tasks Finish event mode readout Optimize final version by removing unused function Functional simulation