97 年度施政計畫先期作業 個案計畫. 海汕國小新校區校舍新建工程 報告人 : 張宏仁校長 李明鍾主任 計畫期程 : 自 95 年 1 月 ~97 年 12 月. 高雄市小港區海汕國民小學報告. 計劃名稱:新校區校園整體規劃暨校舍新建工程 ( 配合紅毛港遷村遷校計畫 ) 遷校地點:前鎮區中安段 ( 中安路捷運機廠旁 ). 新校區. 工程區位圖. 海汕國小 新校區. 捷運站. 計畫期程 :95~97 年. 基地: 2.15 公頃 ( 南向中安路,西鄰捷運機廠 ). 高雄市小港區海汕國民小學報告.

Download Presentation

97 年度施政計畫先期作業 個案計畫

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


97

97年度施政計畫先期作業個案計畫

海汕國小新校區校舍新建工程

報告人: 張宏仁校長 李明鍾主任

計畫期程:自95年1月~97年12月


97

高雄市小港區海汕國民小學報告

  • 計劃名稱:新校區校園整體規劃暨校舍新建工程

    (配合紅毛港遷村遷校計畫)

  • 遷校地點:前鎮區中安段

    (中安路捷運機廠旁)

新校區


97

工程區位圖

海汕國小

新校區

捷運站


97

計畫期程:95~97年

基地:2.15公頃(南向中安路,西鄰捷運機廠)


97

高雄市小港區海汕國民小學報告

計劃名稱:新校區校園整體規劃暨校舍新建工程

執行情形:96.1 完成建築工程發包

96.3 完成水電工程發包

96.4 完成建照核發

96.5 假設工程

目前進度:96.5 假設工程,預定96年度執行至總工程進

度46% (約可執行經費1億元)

97年經費估算執行:1億2仟萬元

97計畫執行重點:主體三樓結構體、水電工程配合屋

頂結構體、內部裝設和雜項工程等


97

高雄市小港區海汕國民小學報告

  • 計劃名稱:新校區校園整體規劃暨校舍新建工程

    預期效益:1.預定97年8月完成校舍新建工程並開始招生

    2.規模為普通班24班,1班資源班,行政服務中

    心,圖書館,視聽中心及景觀,運動設施等.

    3.通過9項綠建築標章,為永續校園之示範學校

    4.可容納約840位學童,為一所現代化,設備

    新穎之中小型學校


97

國中預定地

捷運南機廠

中 安 路

打造孩子知識探索的學習樂園


97

高雄市小港區海汕國民小學報告

  • 計畫名稱:新校區校園整體規劃暨校舍新建工程

打造孩子知識探索的學習樂園