FY 2006-2008 County Manager’s Recommended Capital Budget. July 18, 2006. Overview. Overview FY2006-2008 Capital Budget Summary Capital Budget Principles and Strategies Project Prioritization Criteria Recommended Capital Projects. Overview.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' FY 2006-2008 County Manager’s Recommended Capital Budget' - brina


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

Overview
Overview

  • Overview

  • FY2006-2008 Capital Budget Summary

  • Capital Budget Principles and Strategies

  • Project Prioritization Criteria

  • Recommended Capital Projects


Overview1
Overview

  • Manager’s Recommendation is based on projects requiring funding in FY2007

  • A bond referendum is not recommended this fall

  • Certificates of Participation and Paygo funds are utilized to fund projects


Recommendation summary
Recommendation Summary

  • Government Facilities $ 17,207,000

  • Court Facilities 6,062,000

  • Law Enforcement Facilities 1,755,000

  • Park and Recreation 0

  • Library 14,823,000

  • CMS 171,832,000

  • Total $ 211,679,000

Note: Numbers rounded to the $1,000.



Three key funding strategies
Three Key Funding Strategies

Capital investments should:

  • Meet legal mandates for facilities

  • Emphasize health and safety considerations for employee and customer safety

  • Ensure critical space needs of County departments are met

    Projects not requiring FY07 funding were deferred to FY08 capital budget year.


Selecting project priorities
Selecting Project Priorities

  • Meets legal mandates

  • Advances the Board’s goals or objectives

  • Removes or reduces hazards

  • Maintains or improves service quality

  • Improves service efficiency

  • Supports economic development

  • Offers convenience to residents

  • Improves quality of life or aesthetic value for residents



Government facilities 17 207 000
Government Facilities$17,207,000

  • Strategy – fund through Paygo and COPs. Projects selected based on CIP evaluation criteria.

  • Projects

    • Medical Examiner Equipment

    • County Files and Equipment

    • Freedom Mall – IST Phase 2 and RES

    • Freedom Mall outparcel (e.g., DSS Sr Enrichment Ctr)

    • Land Acquisition Government Facilities

Note: √ = Recommended; — = Deferred; X = Not Recommended.


Court facilities 6 062 000
Court Facilities$6,062,000

  • Strategy – Meet needs of court system over two years.

  • Projects*

    • DA Expansion – Phase I

    • DA Expansion – Phase II

    • Public Defender Relocation

*DA expansion projects replace three projects originally submitted.


Law enforcement facilities 1 755 000
Law Enforcement Facilities$1,755,000

  • Strategy – Postpone consideration of jail expansion for one year to address three policy questions (1. Housing of Federal inmates, 2. Federal support of construction, 3. Expansion of the DA staff)

  • Projects

    • Jail Central Intake Renovation

    • Jail North Expansion


Park and recreation land
Park and Recreation/Land

  • Strategy – Two-fold. 1) Land costs should be incorporated into specific projects. 2) Long-term land acquisition costs for greenspace should be considered as one request and funded through G.O. bonds.

  • Projects

    • Land Acquisition (Mt. Island Lake watershed, Other watershed, and Nature Preserves, Greenways, and Park and Recreation)


Library facilities 14 821 501
Library Facilities$14,821,501

  • Strategy – based on maintaining 0.7 sq. ft. per capita.

  • Projects

    • Hickory Grove Community Library relocation

    • Scaleybark Library Relocation

    • Sharon Road West Community Library relocation

    • Highland Creek Community Library – New

    • Ballantyne Community Library – New

    • Systemwide Merchandising and Signage


School building solutions
School Building Solutions

  • Recommended 18 Projects totaling $171,832,000

  • Funded through Certificates of Participation

  • Remaining $9 million in lottery funds will be used to pay associated debt service




A look ahead
A Look Ahead

  • Several projects not recommended for funding because did not require funding until FY2008 or beyond.

  • Potential FY08 projects include:

    • CMS projects

    • Land Acquisition

    • Jail Expansion

    • Additional Libraries

    • Court System Needs

  • Bond referendum likely needed in Nov. 2007


Other capital issues
Other Capital Issues

At least one known funding need for an existing capital project:

  • New courthouse $2 million

    Issue on the agenda as item 6c

    Should we become aware of other funding needs, we will bring them before the Board.


Thank you
Thank You

  • Citizens’ Capital Budget Advisory Committee

  • School Building Solutions Committee

  • Finance Department

  • Real Estate Services

  • Departmental Staff

  • Strategic Organizational Improvement Staff