East fork of fountain creek mandatory pre bid meeting
This presentation is the property of its rightful owner.
Sponsored Links
1 / 15

East Fork of Fountain Creek Mandatory Pre Bid Meeting PowerPoint PPT Presentation


  • 76 Views
  • Uploaded on
  • Presentation posted in: General

East Fork of Fountain Creek Mandatory Pre Bid Meeting. 14 May 2013. East Fork of Fountain Creek. Aerial of Flood Insurance Rate Map (FIRM). East Fork of Fountain Creek Floodplain Hazard Development Permit. Aerial View of Existing Creeks. Photos looking North – Upstream. April 11, 2013.

Download Presentation

East Fork of Fountain Creek Mandatory Pre Bid Meeting

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


East fork of fountain creek mandatory pre bid meeting

East Fork of Fountain CreekMandatory Pre Bid Meeting

14 May 2013


East fork of fountain creek mandatory pre bid meeting

East Fork of Fountain Creek

Aerial of Flood Insurance Rate Map (FIRM)


East fork of fountain creek floodplain hazard development permit

East Fork of Fountain CreekFloodplain Hazard Development Permit

Aerial View of Existing Creeks


April 11 2013

Photos looking North – Upstream

April 11, 2013


Photos looking south downstream

Photos looking South - downstream


April 11 20131

Confluence of Main Stem and East Fork of Fountain Creek

April 11, 2013

South of the Confluence of Fountain Creek


Administrative notes

Administrative Notes

  • Bid Opening will be 3:00 PM, Thursday 30 May 2013 at City Hall

  • Bid Bonds required

  • Please include completed CDOT Forms 605, 606 and 621

  • CDOT funded project

  • DBE & OJT Goal = zero

  • Davis Bacon wages not required

  • Substantial completion by 30 Sep 2013

  • All RFI’s should be in writing and sent via e-mail to: [email protected] or [email protected]

  • Staging area – TBD and negotiated between the Contractor and property owner


Channel fill and reclamation

Channel Fill and Reclamation

  • Within the Easement:

    • Per plans and specs

    • City Engineering Specs (Title 7; Section 7.5.2.1. Utility Mains – available on line)

    • 95% Modified Proctor (ASTM D-1557) unless otherwise directed

    • Contractor is responsible for all QC & soils testing

    • City may do some QA testing

  • Outside the Easement:

    • Will require special attention

    • See supplemental plans


Alternative pipe materials

Alternative Pipe Materials

  • Proposals will be evaluated separately

  • Decision to use alternative pipe materials will be collaboratively evaluated and approved by the City, the property owner and CDOT

  • Must include:

    • Recent experience with similar 72” and 84” pipe diameters

    • Crew shall also have recent experience with large diameter pipe installations (i.e. Project Superintendent, Foreman, etc.)

    • Provide references

    • Provide QC plan


East fork of fountain creek mandatory pre bid meeting

Trail Ridge Apartments – Grading Plan


  • Login