Navajo County Public Works

Navajo County Public Works. Navajo County Public Works. Major Capital Improvement Projects. Porter Mountain Road - $2.7 Million Realign, Replace and Reconstruct 1.7Miles of Existing Roadway to Apache County Line – under way Lone Pine Dam Road and Bridge - $ 5.0 Million

brand
Download Presentation

Navajo County Public Works

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Navajo County Public Works

  2. Navajo County Public Works Major Capital Improvement Projects Porter Mountain Road - $2.7 Million • Realign, Replace and Reconstruct 1.7Miles of Existing Roadway to Apache County Line – under way Lone Pine Dam Road and Bridge - $5.0 Million • Realign Existing Roadway • Construct New Bridge South of Dam • Hope to be out to construction this fall or next spring Obed Bridge - $2.6 Million • Replace Bridge Truss System and Deck with new Bridge

  3. Navajo County Public Works Porter Mountain Road

  4. Navajo County Public Works Porter Mountain Road

  5. Navajo County Public Works Porter Mountain Road • Project Details • Upgrade Roadway & Existing Drainage System • Coordinate with Local USFS District • Federal Land Exchange Issues • Selected Design-Build Team • Plans and GMP completed at $2.27 M. • Construction well underway, to be done in October, 2008

  6. Navajo County Public Works Lone Pine Dam Road and Bridge

  7. Navajo County Public Works Lone Pine Dam Road and Bridge Roadway Alignment Study

  8. Navajo County Public Works Lone Pine Dam Road and Bridge • Project Details • 1 Mile of Roadway Construction • Realignment and Reconstruction • 440 ft Bridge Span • 100% Plans completed and submitted to ADOT in August, 2008 • Construction hopefully to bid in late 2008

  9. OBED BRIDGE In final Design -Estimated cost $2.6 million

  10. Navajo County Public Works Roadway Maintenance Surry Seal • Completed 20 miles this summer Double Chip Seal • Completed 5 miles near Taylor AC Overlay • Rejected Bids, will re-bid in Spring 2009

  11. Navajo County Public Works Subdivisions • Currently Processing 45 Subdivisions • Lot Sizes from .5 to 10 acres

  12. Navajo County Public Works Transportation Study • Sub-Regional Study Completed in late 2007 • Pinetop-Lakeside • Show Low • Snowflake • Taylor • Vernon • Concho • Now Expanding study to include remainder of County, Winslow and Holbrook with ADOT support.

  13. Transportation Study Navajo County Public Works

  14. Transportation Study Navajo County Public Works

  15. Transportation Study Navajo County Public Works

  16. Navajo County Public Works Transportation Study • Summary: • Study Completed July 2007 – Provides Traffic Impact Projected to 2030 • Additional Study Areas to be Incorporated (Holbrook, Heber/Overgaard, Winslow) • Began additional study January 23, 2008 • Coordination with Statewide Study • Interim Projection to 2015

  17. Navajo County Public Works Planning and Zoning • Total New Roads added to Book of Maintained Roads: 15 Miles (2007) • Propose Development Impact Fees; • Study on hold till new President elected • Implementation may be delayed due to economic concerns

  18. Navajo County Public Works Flood Control • Preliminary DFIRM received Sep 2007 • Digital GIS Format • Mapping Process - 27 miles of levees • Ruby Wash • Winslow • Holbrook • Met with public in November • Asked for additional time for review • County Flood Control Audit – Feb 2007 • Rating Improvement from Level 9 to 8 • 10% Discount in Flood Insurance Rates • Revised Subdivision and Drainage Policy • Requires 100-year, 2-hour Detention • Complies with Applicable State Standards

  19. Navajo County Public Works Current Vacancies • Our positions are pretty well frozen for the time being, until the economy turns around. • Eliminated Deputy Planning Director position • Have position open for County Engineer (P.E.)

  20. Navajo County Public Works Current Projects • On-Call Engineering Services, 2007 - Retained four firms – kept them for 08-09 • On-Call Soils Testing Services, 2007 - retained one firm – may expand in 09 • Obed Road Bridge final Design - under contract (Transystems) • Selected one firm to perform Mountain View ID and one small ID (North Whistle Stop Loop) • Selected one firm to do Hilltop Lane ID • Two new IDs in formation stage