Draft nprr for revisions to gredp and nsrs performance criteria
Download
1 / 6

Draft NPRR for Revisions to GREDP and NSRS Performance Criteria - PowerPoint PPT Presentation


  • 135 Views
  • Uploaded on
  • Presentation posted in: General

Draft NPRR for Revisions to GREDP and NSRS Performance Criteria. S. Looney, March 7, 2011. Summary of Protocol Revisions. In 6.5.7.6.2.3, changed the performance criteria from “at an output level at least equal to the Resource’s LSL” to “released to SCED”.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha

Download Presentation

Draft NPRR for Revisions to GREDP and NSRS Performance Criteria

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript



Summary of protocol revisions
Summary of Protocol Revisions Criteria

  • In 6.5.7.6.2.3, changed the performance criteria from “at an output level at least equal to the Resource’s LSL” to “released to SCED”.

  • Added the definition of released to SCED as net Generation greater than or equal to ninety percent of its LSL and telemetering the correct Resource Status (RST)


Protocol revisions
Protocol Revisions Criteria

  • Section 6.5.7.6.2.3, added the requirement for ERCOT to provide a notification to all QSEs via the ERCOT MIS Certified Area when Non-Spin is deployed to any QSE on the ERCOT system showing the time, MW quantity and duration of the deployment.

  • Section 8.1.1.2, added language to specify that if the QSGR receives a second Base Point lowering generation, the QSGR will be expected to perform to the subsequent appropriate Base Point.


Protocol revisions1
Protocol Revisions Criteria

  • Section 8.1.1.4.1, added the definition for Generation Resource released to SCED at 90% of LSL to GREDP calculation criteria.

  • Section 8.1.1.4.1, added the following: . If a Generation Resource or DSR Portfolio has less than 15 five-minute clock intervals scored during a month, it must have a GREDP less than the greater of X% or Y MW for all but two intervals.


Protocol revisions2
Protocol Revisions Criteria

  • Section 8.1.1.4.1, added a 5 MW deadband for over generation on wind where only a percentage was included previously.

  • Section 8.1.1.4.1, added the following for low number of scoring intervals in a month: If an IRR has less than 15 five-minute clock intervals scored during a month, it must have a GREDP less than the greater of Z% or 5 MW for all but two intervals.


Protocol revisions3
Protocol Revisions Criteria

  • Section 8.1.1.4.1, added requirement that GREDP would only be calculated for 5 minute clock intervals where the WGR was curtailed for the entire interval.

  • Section 8.1.1.4.3, added language to NSRS energy deployment criteria to be consistent with 6.5.7.6.2.3 language specifying requirement to be released to SCED and definition of released to SCED.

  • Need for clarification of MW output level at 25 minutes after NSRS deployment?


ad
  • Login