Video Conferencing Planning Certification DoIT PCC

Video Conferencing Planning Certification DoIT PCC. December 19, 2007. Project Director Timothy Oakeley Infrastructure Manager. Executive Sponsor Lawrence C. Pacheco Chief Information Officer. Project Manager Bryan Gill, PMP. Funding / Certification History.

bona
Download Presentation

Video Conferencing Planning Certification DoIT PCC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Video Conferencing Planning Certification DoIT PCC December 19, 2007 Project DirectorTimothy OakeleyInfrastructure Manager Executive SponsorLawrence C. PachecoChief Information Officer Project ManagerBryan Gill, PMP

  2. Funding / Certification History Note: NMCD has provided the DoIT documentation for fund reauthorization for the remaining amount above.

  3. Project Governance Steering Committee: Larry Pacheco, CIO Charlene Knipfing, Director – PPD Tim Oakeley, ITD Infrastructure Manager Dr. Sign, Tele-Medicine/Tele-Health Sherrry Stevens, Parole Board Lawrence Jarmillo, APD Josh Ruden, Legal Bryan Gill, Project Manager

  4. Project Accomplishments • Drafted PMP • Identified IV & V Vendor • Negotiated draft IV & V Contract • Submitted IV & V Contract to DoIT for review • Held discovery meeting with DoIT (12/7/2007) • Defined Governance Structure • Identified Steering Committee

  5. Discovery with DoIT • Met with DoIT on Friday December 7 to discuss NMCD’s proposed video network architecture • Discussed Qwest QMOE vs. Qwest DS3 technology • Discussed current and future Qwest QMOE locations • Awaiting final pricing from DoIT for QMOE solution including MPLS layer costs

  6. IV & V Vendor Identified and Contract negotiated. Currently in review at DoIT • Working with the State Agency and its Project vendor(s) to define and obtain agreement on Project deliverables and expectations. • Finding key areas that pose risk to the Project and recommending mitigation strategies to reduce those risks. • Leveraging experienced resources who know where to focus to perform targeted reviews of Project deliverables and practices. • Monitoring the progress of the Project. • Maintaining a project-wide focus on critical issues, milestones and objectives. • Documenting and delivering clear, factual analyses of Project deliverables and actual practices.

  7. Project Risk • Currently Project has not identified any risks that are showstoppers requiring Steering Committee activity. As of December 13, 2007