1 / 39

Class Update

Class Update . Exam 2 Schedule – Need evening hours (6-8PM). April 13, 14, or 15. Extra Credit Field Trip – Bluegrass Army Depot – April 2 nd Afternoon. CE 403 Extra Credit Opportunity. Groups who volunteer to present on April 22nd will receive 4 points added to Exam 1. .

bill
Download Presentation

Class Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Class Update • Exam 2 Schedule – Need evening hours (6-8PM). • April 13, 14, or 15. • Extra Credit Field Trip – Bluegrass Army Depot – April 2nd Afternoon

  2. CE 403 Extra Credit Opportunity • Groups who volunteer to present on April 22nd will receive 4 points added to Exam 1.

  3. CE403 Construction Methodology Concrete Construction

  4. Concrete’s Origins • 690 B.C. – The Assyrians used a mixture of one part lime, two parts sand, and four parts limestone aggregate to create a crude concrete for the Bavian Canal • 1824 – Joseph Aspdin files a patent in England on “Portland Cement” • 1825 – Erie Canal, used the first modern concrete to be manufactured in the USA

  5. Concrete Materials & Properties • Components: • Water • Cement • Aggregate • Additives

  6. Water • Primary reason is to provide the moisture for hydration of the portland cement. • Hydration is the chemical reaction between the cement and the water that produces hardened concrete. • The heat produced is called the heat of hydration – exothermic. • The desired characteristics are related to the water-to-cement ratio • (ranges from 0.30 to 0.70 by weight).

  7. Portland Cement

  8. Aggregates • 60 to 80% of the mixture. • Free of Fines • Angularity increases strength

  9. Additives • Air-Entraining agents increase resistance to freezing and thawing and scaling. • Good for pavements. • Plasticizers - increase the slump and workability of a concrete mix • Retarder slow the rate of hardening of concrete. Used sometimes to offset high temperatures. • Accelerators decrease the setting time and increase the high early strength of concrete. • Calcium Chloride is most common, and corrosive to steel. • Pozzolans, i.e. fly ash, • Replace some cement in mix • increases the workability

  10. Distribution of Concrete Construction Costs • Formwork • Labor & Equipment 39% • Material 10% • Concrete • Labor & Equipment 24% • Material 8% • Reinforcing Steel • Labor & Equipment 7% • Material 12%

  11. Cast-In-Place Concrete Walls & Wall Footings

  12. One-way Slabs • Advantages Low cost formwork Fast • Disadvantages Low shear capacity Low Stiffness (notable deflection)

  13. Two-way Slab • Advantages Carries heavy loads Attractive exposed ceilings Fast • Disadvantages Formwork with panels is expensive

  14. Pre-Cast Concrete • Subsets: pre-stressed, tilt-up, lift slab • Applications: lots!! • Advantages: quality control, all-weather construction, fast-track concurrency (no form-work req’d – concrete already cured) • Disadvantages: fab plant overhead (more cost), transport cost, lifting equipment (larger cranes), and require economic quantities (need to exploit repetition)

  15. Precast Beam Shapes

  16. Pre-Cast Concrete • 3 types of joints (concrete to concrete) • Exposed, lapped rebar • Dowels, sleeves, & grout • Topping Slab

  17. Prestressed Concrete • Concrete in compression state before load is applied • 2 types: • Pretensioned • Tension cables tensioned in the concrete form before concrete is placed • After concrete hardens, tensioning devices are removed • Done in fab shop – can be difficult to transport • Post tensioned • Tension cables tensioned after the concrete member has been erected • Done in field – QC can be challenging

  18. Prestressed Concrete Beam

  19. Prestressed Concrete • Concrete in compression state before load is applied • 2 types: • Pretensioned • Tension cables tensioned in the concrete form before concrete is placed • After concrete hardens, tensioning devices are removed • Done in fab shop – can be difficult to transport • Post tensioned • Tension cables tensioned after the concrete member has been erected • Done in field – QC can be challenging

  20. Tilt-Up Construction • Vertical wall elements are cast horizontally and then tilted into place • Advantage: save formwork expense • Lifting stresses may control geometry of design.

  21. Tilt Wall Construction • Ideal for projects where time and budget are critical • Appropriate for large, horizontal projects with three stories or less

  22. Tilt Wall Construction • Engineering Intensive • Tilt-up structures require less maintenance (mason blocks are likely to crack and leak water) • Safer to build – more work at grade

  23. Lift Slab Construction • Floor slabs cast one on atop another • Slabs raised with column-mounted jacks.

  24. Lift Slab Construction • Advantages: minimize form costs & speed up construction • 1987 failure L’Ambiance Plaza (Connecticut) • 28 fatalities • Cause: column to slab connection

  25. Lift Slab Construction

  26. Steel Fiber Reinforced Concrete • Fiber Content: 0.5 to 0.2% by weight • Added paste (needs more cement and sand) needed to coat fibers • Advantages: resistance to impact, cracking, thermal shock, and fatigue • Applications: cavitations exposures (foot of dam, tunnel lining) • Problems: loose fibers

  27. Transporting & Handling • Equipment commonly used: • Wheelbarrows, • small amounts; max distance ~ 200’ • Buckets • good for low slump • Buggies, • Manual or powered • Powered can carry up to 14 cf & traverse up to 1000’ • Chutes, Swivel over large area • Conveyors, • Horz. or Vert.; optimum slump 2.5” to 3” • Pumps, • can move material up to 5000’ horizontally and 1000’ vertically

  28. Placing & Consolidating • The movement of plastic concrete into its final position is called ”PLACING”. ”NOT POURING” • Avoid Segregation when handling. • Height of free fall should be limited to 5ft. • Forms should be clean & tight, and the interior of forms should be oiled or coated with a parting agent for later form stripping. • When placed directly on the subgrade, the subgrade should be moistened, or provided with a moisture barrier.

  29. Typical Wall Form

  30. Gang Forms • AKA prefabricated forms

  31. Maturity Method

  32. Maturity Method Calibrate Mixture

  33. Maturity Method

  34. Reinforcing Steel, “ReBar” Also welded wire fabric and spirals

More Related