An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Port of Everett MASTER PLAN UPDATE April 8, 2008

  2. THREE STEP PROCESS • Step 1: Comprehensive Plan – Set the Vision • Establish guiding principles and land uses • Identify alternatives Step 2: Project Review – Weigh Project Benefits • Community • Trails & Open Space • Community Service • Community Activities • Financial Analysis • Market Demand • Financial Performance • Economic Impacts • Job Creation • Development Catalyst • Tax Generation Step 3: Project Implementation • Design • User Needs • Site Conditions • Environmental Issues • Implement • Environmental Review & Permit • Avoid / Minimize Impacts • Mitigate

  3. WHY PLAN NOW – Facility Capacity

  4. 1995 COMPREHENSIVE SCHEME

  5. PLANNING AREA South Terminal Pacific Terminal

  6. MARINE TERMINAL TRAFFIC 2005 - 2007

  7. MARINE TERMINAL TRAFFIC 2005 - 2007 • In 2007 container TEU’s were more than four times year 2005 level. • General cargo traffic in 2007 was at 100, 000 ton level. • Dry bulk traffic in 2007 was at 125, 000 ton level. • Vessel calls increased from 48 in 2005 to 124 in 2007.

  8. MARINE TERMINAL MASTER PLAN LAYOUT – plan view Reserved For Expansion

  9. MASTER PLAN UPDATE Expansion at South terminal to accommodate Panamax vessels. Wallenius Lines Fidelio – panamax roro ship APL Malaysia – panamax container ship Panamax size ships have a width of 106 ft (32.8 m), length of 750 ft +/- (230 m), and draft of 40 ft +/- (12 m).

  10. MASTER PLANNING HIGHLIGHTS • Road access from North . • Truck gate from North (two lanes in, one lane out). • Rail access from South (from Access Recovery Spur). • Yard tracks (two at 1,100 ft each, with expansion potential). • Deep sea berth for Panamax size vessel (900 ft long, 100 ft wide, 45 ft minimum depth of water). • Potential to add second berth – long term.

  11. MASTER PLANNING HIGHLIGHTS • Multi purpose open storage areas for containers and breakbulk cargoes (strengthen and improve pavement). • Relocate or retain maintenance/operations facility. • Pulp shed removed. • Construct operations building. • Upgrade utilities as required.

  12. TERMINAL EQUIPMENT Consideration is being given to a variety of alternatives : • Relocate one of the existing cranes from Pacific Terminal. • Mobile Harbor cranes. • New and/or second hand gantry cranes designed for Panamax vessels. • Yard equipment : reach stackers, top picks, hostlers and chassis for moving boxes within the yard.

  13. MARINE TERMINAL MASTER PLAN LAYOUT – cross section