ConocoPhillips Transportation Emergency Response Program Transportation EPR&S Rob Yarbrough Director – EPR&S. COP ER Program. Key Facts Pipelines and Terminals 5 Division offices Own ~24,000 miles pipeline Operate 12,156 miles (3,869 mi. HCA) Own and operate 46 terminals

Download Presentation

ConocoPhillips Transportation Emergency Response Program Transportation EPR&S Rob Yarbrough

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Conocophillips transportation emergency response program transportation epr s rob yarbrough

ConocoPhillips Transportation Emergency Response Program

Transportation

EPR&S

Rob Yarbrough

Director – EPR&S


Cop er program

COP ER Program

  • Key Facts

    • Pipelines and Terminals

      • 5 Division offices

    • Own ~24,000 miles pipeline

      • Operate 12,156 miles (3,869 mi. HCA)

    • Own and operate 46 terminals

      • Operate and maintain 1,125 tanks

      • 1.3 MMBD operated rack capacity

    • Polar – based in Houston

      • 5 tankers - 4.5 million barrels capacity

    • ~8,900 rail cars & 121 active truck carriers

    • 1,500 employeesat 120 locations

      • 70 locations with 5 or less employees

Transportation has operations in 20 states


Cop er program1

COP ER Program

  • EPR&S

    • 50+ ER Plans, 500+ first responders

    • 25+ facilitated worst case drills/training annually

    • 25+ self-facilitated table top drills annually

    • Major drills annually with IMAT deployment

  • Background

    • April 2009 Re-org

      • P&T – 14 Districts to 5 Divisions

      • Support Staffs in Houston


Conocophillips transportation emergency response program transportation epr s rob yarbrough

COP ER Program


Cop er program2

COP ER Program

  • Emergency Response Teams, Tier 1

    • P&T – 5, Polar – 1

    • Incident initial response (within Division)

      • Safety, isolation, containment, assessment

      • Incident Command

    • Incident Support Team at Division office

      • Determine appropriate level of response

      • Assist field staff

      • Provide/assist with resources

      • Assist with notifications

      • Prepare for transition to Tier 2 if required


Cop er program3

COP ER Program

  • Houston Support Team

    • Assist the Division Teams

    • Provide technical and business related support as requested or required

      • Support staff (Eng & Projects, Logistics, HSE, Communications, etc)

    • Transition to CMST roles in the event of CMST activation


Cop er program4

COP ER Program

  • 2010 Training

    • Held at 5 Division offices and Houston

    • ~100 people

      • 12 - 15 per division

      • 15 Houston

    • Division Training – 6 hours

      • Classroom training

        • ICS

        • Support team function

        • Initial IAP software

      • Tabletop drill

  • Houston Staff Training

  • Classroom trainingNov - Worst Case discharge drill

  • Richmond Terminal - Worst Case discharge drill

  • Division and Houston supported

  • Credit from CA OSPR


Cop er program5

COP ER Program

Houston Staff Training

Classroom trainingNov - Worst Case discharge drill

Richmond Terminal - Worst Case discharge drill

Division and Houston supported

Credit from CA OSPR


Conocophillips transportation emergency response program transportation epr s rob yarbrough

Transportation Incident Support Team

IST Members

Division Staffing

IST Members

Houston &

Virtual Connection

ICP

IAP Software

  • IAP Software can be utilized with Outlook “Meeting Place” tool to conduct:

  • IST Briefing

  • 201 Briefing

Initial IAP

(Incident Action Plan)

can be printed to network printer at ICP if available

IST Briefing

201 Briefing


Conocophillips plan integration

ConocoPhillips Plan Integration

CM Plan

Crisis Management Team & Crisis Management Support Team

Tier 3

Regional Response Teams (IMATs)

Tier 2

Transportation Tier One Teams

Tier 1

Site Plans & Facility Response Teams

Planning & Preparedness


Ist process

Transportation Tier One Teams

Site Plans & Facility Response Teams

IST Process

Transportation Tier 1 Responders

Transportation IST SME’s

Transportation Tier 1 Division Support

Transportation Tier 1 Team (VRP)

Transportation IST

Includes Co-Located or Nearby COP BU Team Members


Cop er program6

COP ER Program

Questions?