SMMPA Attachment O 2016 Annual Meeting

SMMPA Attachment O 2016 Annual Meeting. Transmission Formula Rate Update August 18, 2016. Background. SMMPA is a not-for-profit, political subdivision of the State of Minnesota SMMPA supplies power to its 18 member municipal utilities SMMPA is governed by its members

beulahboyd
Download Presentation

SMMPA Attachment O 2016 Annual Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SMMPAAttachment O 2016 Annual Meeting Transmission Formula Rate Update August 18, 2016

  2. Background • SMMPA is a not-for-profit, political subdivision of the State of Minnesota • SMMPA supplies power to its 18 member municipal utilities • SMMPA is governed by its members • For more information on SMMPA and its members visit SMMPA’s website at: • http://www.smmpa.org

  3. Background Attachment O • SMMPA became a Transmission Owning member of MISO April 1, 2006 • As a Transmission Owner (TO) SMMPA must annually establish rates for open access use of its transmission assets • SMMPA filed with FERC in 2006 for its own Cash Flow Attachment O historical template • SMMPA utilizes the Cash Flow Attachment O historical template approved by FERC based on data from EIA 412

  4. Attachment O Timeline • June 1st, 2016 publish Attachment O and supporting documentation based on calendar year 2015 actual data • September 1st, 2016 deadline to hold annual stakeholders meeting on formula rate update • December 1st, 2016 deadline for interested parties to submit information requests • January 10th, 2017 deadline for TO to respond information requests • January 31st, 2017 deadline for interested parties to submit informal challenges

  5. Attachment O Timeline Continued • February 28th, 2017 deadline for TO to respond to informal challenges • March 15, 2017 submit informational filing to FERC • March 31, 2017 deadline for interested parties to submit formal challenge to FERC

  6. 2015 Attachment O Summary • Transmission plant $143,348,606 • Intangible – Direct Transmission $ 19,461,271 • Transmission Revenue Requirements: • Operation & Maintenance $ 6,151,589 • Debt Service $ 20,257,350 • Other Taxes $ 2,102,801 • Margin Requirement $ 3,662,931 • Attachment GG Revenue Credits ($ 6,513,859) • Revenue Credits ($ 1,739,050) • Net Revenue Requirements $ 23,921,763 • Transmission Rate $7.895/kW-month

  7. Historical Comparison 2014 Actual2015 Actual • Transmission plant $117,924,226 $143,348,606 • Intangible – Direct Transmission $ 32,047,312 $ 19,461,271 • Transmission Revenue Requirements: • Operation & Maintenance $ 5,754,152 $ 6,151,589 • Debt Service $ 18,791,748 $ 20,257,350 • Other Taxes $ 1,843,295 $ 2,102,801 • Margin Requirement $ 3,397,033 $ 3,662,931 • Attachment GG Revenue Credits ($ 1,260,782) ($ 6,513,859) • Revenue Credits ($ 1,711,011)($ 1,739,050) • Net Revenue Requirements $ 26,814,435 $ 23,921,763 • Transmission Rate $5.105/kW-month $7.895/kW-month

  8. 2015 Net Revenue Requirements Per MISO Pricing Zone • SMMPA has transmission assets and load in 4 different pricing zones in MISO • SMMPA has entered into Joint Pricing Zone Agreements with GRE, ITCM and Xcel which have been filed at FERC • GRE pricing zone - SMMPA has revenue requirements of $1,555,530 and a load of 42.30 MWs • ITCM pricing zone – SMMPA has revenue requirements of $3,541,644 and a load of 28.40 MWs • SMMPA/DPC pricing zone – SMMPA has revenue requirements of $7,680,154 and a load of 55.60 MWs – there was a load reduction of 183.30 MWs for inclusion in RPU’s Attachment O load • Xcel pricing zone – SMMPA has revenue requirements of $11,144,434 and a load of 126.20 MWs

  9. Contact Information • John Winter • Jd.winter@smmpa.org • Laura Sandwick • Lm.sandwick@smmpa.org • Richard Hettwer • rj.hettwer@smmpa.org MISO Attachment O Rate Data Webpage: https://www.misoenergy.org/MarketsOperations/TransmissionSettlements/Pages/TransmissionOwnerRateData.aspx