Sw project management project schedule and budget l.jpg
This presentation is the property of its rightful owner.
Sponsored Links
1 / 32

SW Project Management Project Schedule and Budget PowerPoint PPT Presentation


  • 212 Views
  • Updated On :
  • Presentation posted in: General

SW Project Management Project Schedule and Budget. INFO 420 Glenn Booker. Grand finale. Developing the project schedule and budget is the grand finale of the project planning process – our ultimate goal We just defined the tasks and estimated their duration (effort)

Download Presentation

SW Project Management Project Schedule and Budget

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Sw project management project schedule and budget l.jpg

SW Project ManagementProject Schedule and Budget

INFO 420

Glenn Booker

Chapter 7


Grand finale l.jpg

Grand finale

  • Developing the project schedule and budget is the grand finale of the project planning process – our ultimate goal

    • We just defined the tasks and estimated their duration (effort)

    • Now identify the sequence of tasks, interdependencies, and staffing needs

Chapter 7


Project cost management l.jpg

Project cost management

  • The budget is determined from the project schedule, the cost assigned to tasks, and other indirect costs or resources

  • Project cost management includes

    • Cost estimating for tasks and their resources

    • Cost budgeting for the whole project

    • Cost control – define processes

Chapter 7


Rolling up costs l.jpg

Rolling up costs

  • Since our tasks were organized into phases and deliverables, we can roll up (summarize) costs to any level desired

    • Cost per deliverable

    • Cost per phase

    • Cost of the whole project

  • The sponsor needs to approve these costs

Chapter 7


Developing project schedule l.jpg

Developing project schedule

  • A key sanity check is that each of the estimates for each task is really reasonable according to the experts in that activity

    • GIGO applies here, not just to programming!

Chapter 7


Project schedule tools l.jpg

Project schedule tools

  • Tools to show a project schedule include

    • Gantt chart

    • Project network diagram

      • Activity On the Node (AON) diagram

      • Critical path analysis

      • PERT charts

      • Precedence diagramming method (PDM)

    • Critical chain project management (CCPM)

Chapter 7


Gantt chart l.jpg

Gantt chart

  • The Gantt chart is probably the most widely used project management tool

    • Time is the X axis, from days to years

      • The current date is readily visible

    • Tasks are on the Y axis

      • Bars represent WBS tasks

      • Milestones are diamond shapes

      • An inset bar can show actual work progress

Chapter 7


Basic gantt chart l.jpg

Basic Gantt chart

Chapter 7


Project network diagram l.jpg

Project network diagram

  • Project network diagrams are also based on the WBS, but also show more info on task sequence or dependencies

    • Many also show when tasks must start or stop in order not to affect project completion date

    • This can help decide resource assignments needed for critical tasks

Chapter 7


Activity on the node l.jpg

Activity On the Node

  • Activity On the Node (AON) diagrams represent the flow of tasks needed to complete the project

    • Tasks are nodes (boxes)

    • Arrows show the order in which they occur

  • The duration of tasks isn’t directly visible under AON, only time order

Chapter 7


Activity on the node11 l.jpg

Activity On the Node

  • Tasks can be predecessors, successors, or in parallel

    • Predecessor tasks must occur before another task

    • Successor tasks must occur after another task

    • Parallel tasks may occur at the same time as another task

Chapter 7


Critical path analysis l.jpg

Critical path analysis

  • Given an AON, critical path analysis determines which activities are directly connected to achieving the project schedule

    • They are the critical path, which can change

  • Analytically, find the duration of each path through the AON diagram

Chapter 7


Critical path analysis13 l.jpg

Critical path analysis

  • The path with the longest duration is the critical path (and the project duration)

    • If any tasks on the critical path are delayed, the overall project completion will be delayed

    • Tasks not on the critical path may have a non-zero amount of slack or float, which is the amount of duration they can slip without affecting the project

Chapter 7


Critical path analysis14 l.jpg

Critical path analysis

  • A manager might add resources to tasks on the critical path, if that will actually help finish them sooner

    • This technique can be called expediting or crashing the project

  • Fast tracking the project is done by making tasks parallel that weren’t

Chapter 7


Pert charts l.jpg

PERT charts

  • PERT is the program evaluation and review technique, developed in the 50’s

    • Often seen with CPM, or critical path method

  • A PERT chart also uses the AON graphic notation, but uses a different approach for estimation

Chapter 7


Styles of pert nodes l.jpg

Styles of PERT nodes

Chapter 7


Pert charts17 l.jpg

PERT charts

  • For each task, estimate the lowest (optimistic), most likely, and highest (pessimistic) durations, then use

    • estimate = (low + high + 4*likely)/6

  • The critical path analysis can be done based on these estimates

Chapter 7


Precedence diagramming method l.jpg

Precedence diagramming method

  • The precedence diagramming method (PDM) adds to AON by showing the key sequence relationships

    • Finish to start (most common, sequential)

    • Start to start

    • Finish to finish

    • Start to finish

Chapter 7


Pdm node relationships l.jpg

PDM node relationships

From Fig. 7.5

Chapter 7


Slide20 l.jpg

PDM

  • PDM can also show lead and lag times for activities

    • Lead time is an amount of time a task can start before the end of its predecessor

    • Lag time is the amount of time a task must start after the end of its predecessor

      • Hence lag time = negative lead time

Chapter 7


Critical chain project management l.jpg

Critical chain project management

  • Critical chain project management (CCPM) is a newcomer (Goldratt, 1997)

  • It assumes that all estimates are inflated

  • We still finish projects late because

    • We wait until the last minute (student syndrome)

    • Projects fill the time available (Parkinson’s law)

    • Resource contention

Chapter 7


Slide22 l.jpg

CCPM

  • CCPM takes that buffer from each task, and puts in in larger blocks where needed

    • How? Estimate tasks so that you only have a 50% chance of completing them on time

    • Then take half of the difference in task time, and put that into a buffer at the end of the project

Chapter 7


Slide23 l.jpg

CCPM

  • Yes, you have to estimate each task twice

    • Once normally, and once for 50% chance completion

  • CCPM also accounts for resource limits, by identifying the resources for each task and buffers for each type of resource

Chapter 7


Pm software tools l.jpg

PM software tools

  • There are several project management software tools for developing and managing schedules

    • Microsoft Project is the de facto standard

    • Planner and OpenWorkBench are open source tools

  • Ok, so Project doesn’t have much competition…

Chapter 7


Pm software tools25 l.jpg

PM software tools

  • Often projects are planned in detail only a few months in the future, a rolling wave approach

  • There’s an outline of the rest of the project, particularly for planning long lead time items

Chapter 7


Project budget l.jpg

Project budget

  • The budget is straightforward to develop, once the schedule has been determined

    • Determine the type of resource(s) needed for each task, and how many of them are needed for its duration (0.1, 2.5, whatever)

    • Find the cost of each resource type ($/hr), and multiply that by how many and the duration = cost per task

Chapter 7


Project budget27 l.jpg

Project budget

  • Check for overuse of resources – often not recommended to use 155% of a person’s time

  • To find the cost of each resource*, assess their typical annual salary**, divide by 2000 (hours per work year), and multiply by 2.5 (to account for overhead expenses)

* This is a heuristic. ** You could look for salary surveys.

Chapter 7


Project budget28 l.jpg

Project budget

  • So if a software engineer averages $60k/year, their hourly rate is about $30/hr

    • Actually, a normal work year is 40*52 = 2080 hours, but we’re just getting a rough estimate

  • Multiply by 2.5 to get a labor rate of $75/hr

    • This is the ‘true cost’ in the text

Chapter 7


Other costs l.jpg

Other costs

  • Labor is the biggest cost on most projects, but other costs should be considered

    • Indirect costs – are admin assistants, facilities, insurance, etc. paid by the project, or from overhead?

    • Sunk costs – from previous bad projects

    • Learning curve – might be covered by prototypes

Chapter 7


Other costs30 l.jpg

Other costs

  • Reserves – most projects keep back a 10-15% reserve from the total actual budget, in anticipation of some cost overruns

  • Project-specific hardware and software – plan for infrastructure costs (servers, network equipment, software) which aren’t part of normal office & facility environment

  • Travel, e.g. to the customer?

Chapter 7


Resource allocation l.jpg

Resource allocation

  • Again, make sure that individuals aren’t scheduled for over 100% of their time

  • Also consider resource leveling

    • Are there times when people are needed, then not, then needed again?

    • What will those people do in the middle?

Chapter 7


Baseline plan l.jpg

Baseline plan

  • Once all these issues have been identified and agreed upon, you have the baseline project schedule, which feeds the project plan

  • All measurements of ‘planned versus actuals’ hinge upon this plan!

Chapter 7


  • Login