An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NORMIRANJE ANALIZA JEDINIČNE CENE POZICIJE RADA

  2. ANALIZA JEDINIČNE CENE POZICIJE RADA Primer: oblaganje zidova pločicama

  3. ANALIZA JEDINIČNE CENE POZICIJE RADA Primer: izrada sloja kolovoza od šljunka

  4. Primer: Izvršiti analizu cena za izradu AB grede dimenzija 100*40 cm. Obračun se vrši po m3. Beton se nabavlja u fabrici betona po ceni od 5700 din/m3. Transport se vrši sopstvenim automešalicama. Angažovane su 2 automešalice sa ukupnim učinkom od 10,50 m3/h. Koeficijent rastresitosti betona je 0,96, a koeficijent korišćenja radnog vremena je 0,80. Unutrašnji transport betona vrši se kranom. Up krana za prenos betona je 9 m3/h. Od građevinskih radnika za unutrašnji transport angažovani su: 1 radnik V kategorija, 1 radnik IV kategorije i 2 radnika III kategorije. Ugrađivanje betona se vrši sa 2 pervibratora sa ukupnim učinkom od 10 m3/h. Na jednom pervibratoru angažovana su dva radnika: III i V kategorije. Oplata je sistemska metalna. Normom je predviđeno 200 upotreba oplate. Cena nove oplate je 6500 din/m2. Za prenos oplate koristi se kran uz pomoć 2 građevinska radnika III kategorije. Učinak krana je Up=35 m2/h oplate zidova.

  5. Primer: Izvršiti analizu cena za izradu AB grede dimenzija 100*40 cm. Obračun se vrši po m3. Iz normativa se očitavaju sledeći podaci: Normativza oplatu: Za uljenje oplate koristi se "oplatol" ulje sa normom 0,09 l/m2. Cena ovog ulja je 250 din/l. Režijski faktori: za radnu snagu je 2,5; za materijal 1,07; za mehanizaciju 1,20 Radnasnaga: Koštanje mehanizacije: automešalica 2300din/h; toranjski kran 3170din/h; pervibrator 420din/h

  6. Analiza jedinične cene pozicije rada Obračun: 1m3

  7. Analiza jedinične cene pozicije rada Obračun: 1m3

  8. Analiza jedinične cene pozicije rada Obračun: 1m3

  9. Analiza jedinične cene pozicije rada Obračun: 1m3

  10. PRORAČUN DIREKTNIH TROŠKOVA ZA RADNU SNAGU

  11. Proračun direktnih troškova radne snage

  12. Proračun direktnih troškova radne snage Kpbeton= 1

  13. Proračun direktnih troškova radne snage

  14. Proračun direktnih troškova radne snage =(1/Upt.k.) *2=1/9*2

  15. Proračun direktnih troškova radne snage =(1/Upt.k.) =1/9

  16. Proračun direktnih troškova radne snage =(1/Upt.k.) =1/9

  17. Proračun direktnih troškova radne snage =(1/Uppv.) =1/5=1/(10/2)

  18. Proračun direktnih troškova radne snage =(1/Uppv.) =1/5=1/(10/2)

  19. Proračun direktnih troškova radne snage Kpoplata= (1/0,4) * (1+0,4+1) = 6

  20. Proračun direktnih troškova radne snage =Kp*Norma = 6*0,14

  21. Proračun direktnih troškova radne snage =Kp*Norma = 6*0,26=

  22. Proračun direktnih troškova radne snage =Kp*Norma = 6*0,14

  23. Proračun direktnih troškova radne snage =Kp*Norma = 6*0,26=

  24. Proračun direktnih troškova radne snage =Kp*Norma = 6*0,10 =

  25. Proračun direktnih troškova radne snage =Kp*Norma = = Kp * (2*1/Up(t.k.prenos oplate)) )

  26. Proračun direktnih troškova radne snage =6 * (2*1/35)

  27. Proračun direktnih troškova radne snage Suma

  28. Proračun direktnih troškova radne snage Potreban broj norma sati radnika III kat. da bi se obavilo betoniranje i radovi na oplati, za 1m3 AB grede.

  29. Proračun direktnih troškova radne snage

  30. Proračun direktnih troškova radne snage = 1,365 * 320 = 436,8 = = direktni troškovi za radnika RIII po 1m3 AB grede

  31. Proračun direktnih troškova radne snage Ers = Direktni troškovi r.s. = = Suma direktnih troškova za radnike svih kategorija za 1m3 AB grede

  32. PRORAČUN DIREKTNIH TROŠKOVA ZAMATERIJALE

  33. Proračun direktnih troškova za materijale

  34. Proračun direktnih troškova za materijale

  35. Proračun direktnih troškova za materijale = (potrebna količina + rastur materijala) * Kpbeton

  36. Proračun direktnih troškova za materijale

  37. Proračun direktnih troškova za materijale = Kpoplata

  38. Proračun direktnih troškova za materijale = (Cena oplate po m2) / (broj upotreba oplate)

  39. Proračun direktnih troškova za materijale = Troškovi oplate za izradu 1m3 AB grede

  40. Proračun direktnih troškova za materijale = Norma *Kpoplata= =0,09*6

  41. Proračun direktnih troškova za materijale Emat = Direktni troškovi materijala = = Suma direktnih troškova svih materijala potrebnih za izradu 1m3 AB grede

  42. PRORAČUN DIREKTNIH TROŠKOVA ZAMEHANIZACIJU

  43. Proračun direktnih troškova za mehanizaciju

  44. Proračun direktnih troškova za mehanizaciju

  45. Proračun direktnih troškova za mehanizaciju =(1/Upa.m.) * Kpbeton= =1/5,25 *1 = 1/ (10,5/2) *1

  46. Proračun direktnih troškova za mehanizaciju =(1/Upt.k.(prenos betona)) * Kpbeton= =1/9 *1

  47. Proračun direktnih troškova za mehanizaciju =(1/Upt.k.(prenos betona)) * * Kpbeton= =1/9 *1 =(1/Upt.k. (prenos oplate)) * * Kpoplata= =1/35 *6

  48. Proračun direktnih troškova za mehanizaciju Suma

  49. Proračun direktnih troškova za mehanizaciju Potreban broj sati rada toranjskog krana za prenos betona i opate za 1m3 AB grede.

  50. Proračun direktnih troškova za mehanizaciju Th= direktni troškovi rada toranjskog krana za 1 h = = Jt / hgr + Ee + Eos