An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Municipal Infrastructure Grant (MIG) Expenditureas at end April 201304 June 2013

  2. Outline of the Presentation • National Overview of MIG Expenditure as at 30 April 2013 • Challenges • Annexure MIG expenditure per municipality per province – end of April 2013

  3. National Overview of MIG Expenditure as at 30 April 2013

  4. National Overview of MIG Expenditure as at 30 April 2013 • As at 30 April 2013, R13,8 billion or 99.98 percent of the total MIG allocation was transferred to 247 municipalities (21 districts and 226 local) in the 9 provinces (transfers were made during July 2012, November 2012 and March 2013). • Only 99.98% of the 2012/13 MIG funds were transferred to Limpopo municipalities as some funds (R2,471,000) were not transferred to Bela Bela Local Municipality. • Municipalities spent 53 percent of the funds transferred between July 2012 and April 2013 representing 53 percent expenditure on the total MIG allocation of R13,8 billion. • The Eastern Cape is the best overall spender having spent 64.9 percent of their total MIG allocation followed by the Free State which spent 61 percent of their total MIG allocation. • KwaZulu-Natal, Limpopo and Northern Cape had by the end of April 2013, spent less than 50 percent of their overall allocations. • Some of the municipalities spending on the MIG funds are also spending on the 2011/12 approved funds, for example, 3 of the municipalities in the Free State that spent less than 50 percent of the 2012/13 allocations at the end of March 2013 were also spending on the 2011/12 approved rollovers.

  5. Challenges – Monthly DoRA Report • Summary Report :- • Insert explanations for variance from payment schedules, transfers and expenditure and other matters • Remedial measures (if any) e.g.: • One on One will be on the 1st week of March 2013 (reflected in April Report), • No report received • Expenditure zero (no reasons for variance, no remedial measures)

  6. ANNEXURE MIG EXPENDITURE PER MUNICIPALITY PER PROVINCE– END OF APRIL 2013

  7. MIG Expenditure Per Municipality Per Province (EASTERN CAPE) – April 2013

  8. MIG Expenditure Per Municipality Per Province (EASTERN CAPE) – April 2013

  9. MIG Expenditure Per Municipality Per Province (EASTERN CAPE) – April 2013

  10. MIG Expenditure Per Municipality Per Province (EASTERN CAPE) – April 2013

  11. MIG Expenditure Per Municipality Per Province (EASTERN CAPE) – April 2013

  12. MIG Expenditure Per Municipality Per Province (FREE STATE) – April 2013

  13. MIG Expenditure Per Municipality Per Province (FREE STATE) - April 2013

  14. MIG Expenditure Per Municipality Per Province (GAUTENG) – April 2013

  15. Municipal Infrastructure Grant Expenditure Per Municipality Per Province (KWAZULU NATAL) – April 2013

  16. MIG Expenditure Per Municipality Per Province (KWAZULU NATAL) – April 2013

  17. Municipal Infrastructure Grant Expenditure Per Municipality Per Province (KWAZULU NATAL) – April 2013

  18. MIG Expenditure Per Municipality Per Province (KWAZULU NATAL) – April 2013

  19. Municipal Infrastructure Grant Expenditure Per Municipality Per Province (KWAZULU NATAL) – April 2013

  20. Municipal Infrastructure Grant Expenditure Per Municipality Per Province (LIMPOPO) - April 2013

  21. MIG Expenditure Per Municipality Per Province (LIMPOPO) – April 2013

  22. MIG Expenditure Per Municipality Per Province (LIMPOPO) – April 2013

  23. Municipal Infrastructure Grant Expenditure Per Municipality Per Province (MPUMALANGA) - April 2013

  24. MIG Expenditure Per Municipality Per Province (MPUMALANGA) – April 2013

  25. Municipal Infrastructure Grant Expenditure Per Municipality Per Province (NORTHERN CAPE) – April 2013

  26. MIG Expenditure Per Municipality Per Province (NORTHERN CAPE) – April 2013

  27. MIG Expenditure Per Municipality Per Province (NORTH WEST) – April 2013

  28. MIG Expenditure Per Municipality Per Province (NORTH WEST) – April 2013

  29. MIG Per Municipality Per Province (WESTERN CAPE) – April 2013

  30. MIG Expenditure Per Municipality Per Province (WESTERN CAPE) – April 2013

  31. Challenges (1/4) • The challenges which are outlined in the following 3 slides are based on the experiences and lessons from interactions with 92 MIG under spending municipalities during the 2012/13 financial year.

  32. Challenges (2/4) • Institutional (administration and governance) • A large number of municipalities are faced with key positions vacant (e.g. Municipal Manager, CFO, Director – Technical Services) for a long time or others have people acting in these positions resulting in lack of decision making and accountability thus significantly delaying progress on projects • Municipalities are characterized by high staff turnover making the retention of institutional memory impossible and thereby necessitating the re-training of key staff members and resulting in further delays • Some municipal officials are totally lacking in accountability and delay progress by not following up on necessary processes pertaining to project implementation

  33. Challenges (3/4) • Planning and Procurement • Municipalities fail to prioritise projects and get necessary documents to initiate projects on time. • e.g. technical reports not submitted or inputs by sector departments not considered timeously • Often the lack of understanding of Supply Chain Management procedures and lack of commitment to processes and timelines result in further delays. • e.g. Bid evaluation committees and bid adjudication committees are not sitting regularly thereby negatively impacting on decision making processes and delaying project initiation and implementation.

  34. Challenges (4/4) • Project and Financial Management • There is often no oversight or management of consultants/contractors on the part of the relevant municipal officials.

  35. Supporting Municipalities (1/2) • Some HR issues impacting on the institutional (administration and governance) matters include the following: • Supporting municipalities to develop and implement recruitment and retention strategies. • Monitoring municipalities to fill vacancies in terms of the Municipal Structures Act. • Planning and Procurement: • District Appraisal sessions convened by the MIG national unit help municipalities to commit their allocations well in advance of the forthcoming financial year in order to get projects in construction at the commencement of the municipal financial year. • MISA is deploying engineers to assist with infrastructure planning in municipalities (this deployment is done following the diagnostic conducted, which revealed challenges of infrastructure delivery) • The Provincial Treasuries will be requested to provide support around procurement issues.

  36. Supporting Municipalities (2/2) • Project and Financial Management: The DCoG to continue providing advise to those municipalities (in the context of MIG) to appropriately manage their projects from both project and financial management perspectives.