SYSTEM RESTORATION. SYSTEM RESTORATION PROCEDURE FOR NORTHERN REGIONAL GRID March 2001. SYSTEM RESTORATION LOAD GENERATION BALANCE. During system restoration for the security of operation of the restored subsystems as well as for ease of synchronization

Download Presentation

SYSTEM RESTORATION

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


System restoration

SYSTEM RESTORATION

SYSTEM RESTORATION PROCEDURE

FOR NORTHERN REGIONAL GRID

March 2001


System restoration load generation balance

SYSTEM RESTORATIONLOAD GENERATION BALANCE

During system restoration for the security of operation of the restored subsystems as well as for ease of synchronization

---the load generation balance is to be maintained in each sub-system and

---all efforts be carried out to maintain the system parameters near the nominal values


System restoration

LOAD GENERATION BALANCE DURING

SYSTEM RESTORATION

EASTERN U.P. SUBSYSTEM

S No.

Sources of Start-up Power

Quantum

MW

a

WR - on 400 KV Vindhyachal AC By-Pass link

100

b

Rihand (Hy) - Self start

250

c

Obra (Hy)-Start-up from Rihand(Hy)

50

Total

400

Requirement of Start-up Power

Quantum

MW

a

Start up power at Singrauli

70

b

Start up power at Rihand

50

c

Start up power at Anpara

70

d

Start up power at Unchahar

40

e

Start up power at Obra(Th)

40

f

Start up power at Tanda

20

g

Railway Traction

110

Total

400


System restoration operation of ac bypass link

SYSTEM RESTORATIONOPERATION OF AC BYPASS LINK

Since the time taken for extending the start-up power from westeren region to northeren region is extremely vital for normalisation of the grid

---the operations for closing of AC bypass link should be done in quickest possible time.


System restoration eastern up subsystem

SYSTEM RESTORATIONEASTERN UP SUBSYSTEM

For fast build-up of the sub-systems in UP area and to regulate the system parameters, the early start-up of the units at Rihand (Hydro) is extremely essential.

Furthermore in order to stablize the units at Rihand(Hydro) these must be synchronized with a stable source like western grid at the earliest opportunity.


System restoration

S No.

Sources of Start-up Power

LOAD GENERATION BALANCE

BBMB-DELHI SUBSYSTEM

a

Bhakra(Right)

300

b

Bhakra(Left)

200

c

Auraiya(Gas)

110

d

Dadri(Gas)

130

e

I.P.Extn

50

f

Pong

120

g

Faridabad(Gas)

140

h

Salal HEP

105

i

Uri HEP

40

j

Lower Jhelum

30

Total

1225

Requirement of Start-up Power

a

Panipat(Th)

40

b

Ropar

50

c

Bhatinda

30

d

Lehra Mohabbat

50

e

BTPS

40

f

Dadri(Th)

50

g

IP+Rajghat

40

h

Faridabad(Th)

20

i

Railway Traction

220

j

Other Essential Loads

685

Total

1225

Quantum MW

Quantum MW


System restoration bbmb delhi subsystem

SYSTEM RESTORATIONBBMB-DELHI SUBSYSTEM

A strict load generation balance shall have to be maintained while developing the sub-system.

The voltages at different sections/buses are to be maintained within normal range by use of bus/line reactors and operating the units in synchronous condenser mode wherever possible.


System restoration

S No.

Sources of Start-up Power

Quantum

MW

a

RPS-Self Start

150

b

JS HEP

100

c

Anta(Gas)

80

Total

330

Requirement of Start-up Power

Quantum

MW

a

Start-Up at Kota

30

b

RAPS(A) & RAPS(B)

50

c

Railway Traction

70

d

Emergency Loads

180

Total

330

LOAD GENERATION BALANCE

RAJASTHAN SUBSYSTEM


System restoration rajasthan subsystem

SYSTEM RESTORATIONRAJASTHAN SUBSYSTEM

In case of survival of RAPS(A)/RAPS(B) islands, these must be synchronized with the supply of R.P.Sagar / Kota (S) at the earliest opportunity.

In case, Kota(S) has availed start-up power from Ujjain and RP Sagar has been started up separately, then the two supplies are to be synchronized at Kota (S) / RP Sagar for stability and then the supply be extended further to other stations.

The start-up of Anta is to be closely monitored. In case of its self-start, the supply from Anta must be synchronized with supply at Kota (S) at the earliest opportunity.


System restoration

S No.

Sources of Start-up Power

Quantum(MW)

a

Chibro-Self start

150

b

Ramganga Self start

100

c

Remaining hydro stations

150

Total

400

Requirement of Start-up Power

Quantum(MW)

a

Start-Up to NAPS

40

b

Railway Traction

30

c

Other Essential Loads

70

Total

400

LOAD GENERATION BALANCE

WESTERN U.P. SUBSYSTEM


System restoration

START UP POWER TO NAPS (Narora)

Ist Option:The units at Ramganga shall be self-started and the supply

extended upto NAPS through

--132 kV Ramganga

--132 kV Nehtaur

--220 kV Nehtaur

--220 kV Moradabad

--220 kV NAPS

IInd Option:The hydro units at Yamuna Complex (Chibro, Khodri, Dhakrani, Dhalipur and Kulhal) shall be self started and the supply shall be extended upto Muradnagar 220kV. From Muradnagar the supply shall be extended upto NAPS through Muradnagar-Khurja-NAPS link.

IIIrd Option :In case there is in-ordinate delay in the above two operations and by that time the Delhi-BBMB sub-system has been stablised and supply is available at Agra/Sikandara then the supply to NAPS is to be extended through Agra-Agra(new)-Harduganj-NAPS link.


System restoration western up subsystem

SYSTEM RESTORATIONWESTERN UP SUBSYSTEM

In the event of survival of NAPS island, UPPCL has to take necessary steps to extend the stabilized supply from the built up Western UP subsystem to NAPS at the earliest.

After synchronizing the Western UP subsystem with NAPS, all care is to taken by UPPCL to avoid any sudden variation in the load in the Western UP subsystem which may otherwise result in collapse of the subsystem and poisoning out of the nuclear units.


System restoration power supply to railway traction

SYSTEM RESTORATIONPOWER SUPPLY TO RAILWAY TRACTION

In the event of black start, initially the different subsystems shall be of small size and the running generating units shall have a limitation in regard to the ramp up rates.

Therefore, as soon as the power is made available for the purpose of traction, it would be ensured by Railways that

--- the load shall be kept restricted to bare minimum and

---the movements of trains in different sections would be co- ordinated for avoiding sudden jerks / ramp ups on the system.


System restoration1

SYSTEM RESTORATION

In the event of a total blackout, the initial moments are extremely precious and a desired action taken at first instance can help in speedy restoration of the system while a small delay or lapse in taking the initial action may prove to be extremely costly.

It is therefore extremely essential that:

---all essential loads and start-up sources alongwith the cocerned circuits be clearly identified and

---operating personnel associated with the system operation are thoroughly acquainted with the restoration procedures