DIRECCION GENERAL DE CARRETERAS. TERCER CINTURON. RONDA DE LA HISPANIDAD. PRESUPUESTO : 67,57 M€ (11.242,7 MPts) LONGITUD : 10,5 kms . FECHA DE INICIO : 12 DE ENERO DE 1999 FECHA DE TERMINACION : 31 DE AGOSTO DE 2002. 3 er CINTURON. RONDA HISPANIDAD. 3 er CINTURON. RONDA HISPANIDAD.

Download Presentation

DIRECCION GENERAL DE CARRETERAS

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


DIRECCION GENERAL DE CARRETERAS

TERCER CINTURON. RONDA DE LA HISPANIDAD

PRESUPUESTO: 67,57 M€ (11.242,7 MPts)

LONGITUD: 10,5 kms.

FECHA DE INICIO: 12 DE ENERO DE 1999

FECHA DE TERMINACION:31 DE AGOSTO DE 2002


3 er CINTURON. RONDA HISPANIDAD


3 er CINTURON. RONDA HISPANIDAD


3 er CINTURON. RONDA HISPANIDAD


3 er CINTURON. RONDA HISPANIDAD


3 er CINTURON. RONDA LA HISPANIDAD

PUENTE SOBRE EL RIO EBRO


DIRECCION GENERAL DE CARRETERAS

CUARTO CINTURON. (RONDA SUR)

PRESUPUESTO: 82,91 M€ (13.795,1 MPts)

LONGITUD: 13,9 kms.

FECHA DE INICIO: 28 DE DICIEMBRE DE 1999

FECHA DE TERMINACION: 28 DE JUNIO DE 2003


4º CINTURON ENLACE CON LA N-II


4º CINTURON ENLACE CON LA N-II


4º CINTURON. PASO SOBRE RIO HUERVA


4º CINTURON. PASO SOBRE RIO HUERVA


4º CINTURON. PASO SOBRE RIO HUERVA


DIRECCION GENERAL DE CARRETERAS

ZARAGOZA- EL BURGO DE EBRO

PRESUPUESTO: 21,21 M€ (3.529,1 MPts)

LONGITUD: 10,8 kms.

FECHA DE INICIO: 23 DE JULIO DE 2001

FECHA DE TERMINACION: 28 NOVIEMBRE 2003


EL BURGO DE EBRO-ZARAGOZA


EL BURGO DE EBRO-ZARAGOZA


DIRECCION GENERAL DE CARRETERAS

CONEXIÓN N-232 CON A-68 AL ESTE DE CASETAS

PRESUPUESTO: 15,35 M€ (2.554,03 MPts)

LONGITUD: 2,7 kms.

FECHA DE INICIO: 18 DE ABRIL DE 2002

FECHA DE TERMINACION: 18 DE ENERO DE 2004


CONEXION N-232 CON A-68 AL ESTE DE CASETAS


CONEXION N-232 CON A-68 AL ESTE DE CASETAS


DIRECCION GENERAL DE CARRETERAS

CONEXIÓN A-68 CON N-232

PRESUPUESTO: 4,00 M€ (665,5 MPts)

LONGITUD: 1,3 kms.

FECHA DE INICIO: PENDIENTE

FECHA DE TERMINACION: 12 MESES


CONEXIÓN A-68 CON N-232 EN ZARAGOZA


CONEXIÓN A-68 CON N-232 EN ZARAGOZA


DIRECCION GENERAL DE CARRETERAS

ADECUACION DE LA VIA DE LA HISPANIDAD

PRESUPUESTO: 11,32 M€ (1.883,5 MPts)

LONGITUD: 2,3 Kms.

FECHA DE INICIO: PENDIENTE

FECHA DE TERMINACION: 18 MESES


ADECUACION DE LA VIA DE LA HISPANIDAD


ADECUACION DE LA VIA DE LA HISPANIDAD