An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 3Economic Order Quantity

  2. Defining the economic order quantity

  3. Background to the model The approach is to build a model of an idealized inventory system and calculate the fixed order quantity that minimizes total costs. This optimal order size is called the economic order quantity (EOQ).

  4. Assumption for a basic model • The demand is known exactly, is continuous and is constant over time. • All costs are known exactly and do not vary. • No shortages are allowed. • Lead time is zero – so a delivery is made as soon as the order is placed.

  5. Other assumptions implicitly in the model • We can consider a single item in isolation, so we cannot save money by substituting other items or grouping several items into a single order. • Purchase price and reorder costs do not vary with the quantity ordered. • A single delivery is made for each order. • Replenishment is instantaneous, so that all of an order arrives in stock at the same time and can be used immediately.

  6. The most important assumption here is that demand is known exactly, is continuous and constant over time (Fig. 3.2) • The assumptions give an idealized pattern for a stock level. (Fig. 3.3)

  7. Variables used in the analysis • Four costs of inventory • Unit cost (UC) • Reorder cost (RC) • Holding cost (HC) • Shortage cost (SC)

  8. Three other variables: • Order quantity (Q) • Cycle time (T) • Demand (D)

  9. Derivation of the economic order quantity • Three steps: • Find the total cost of one stock cycle. • Divided this total cost by the cycle length to get a cost per unit time. • Minimize this cost per unit time.

  10. Amount entering stock in cycle = amount leaving stock in cycle So Q = D x T Total cost per cycle = unit cost + reorder cost + holding cost (component)

  11. The optimal time between orders is: To = Qo/D =500/6,000 = 0.083 years = 1 month The associate variable cost is: VCo = HC × Qo = 6 × 500 = $3,000 a year This gives a total cost of: TCo = UC × D + VCo = 30 × 60000 + 3000 = $183,000 a year

  12. Summary • We have built a model of an idealized inventory system that relates order size to costs and demand. This shows that large, infrequent orders have a high holding cost component, so the total cost is high: small, frequent orders have a high reorder cost component, so the total cost is also high. A compromise finds the optimal order size – or economic order quantity – that minimizes inventory costs.

  13. Adjusting the economic order quantity Moving away from the EOQ • The EOQ suggests fractional value for things which come in discrete units (e.g. an order for 2.7 lorries) • Suppliers are unwilling to split standard package sizes. • Deliveries are made by vehicles with fixed capacities. • It is simply more convenient to round order sizes to a convenient number.

  14. How much costs would rise if we do not use the EOQ Example: D = 6000 units a year Unit cost, UC = £30 a unit Reorder cost, RC = £125 an order Holding cost, HC = £7 a unit a year

  15. Order for discrete items This suggests a procedure for checking whether it is better to round up or round down discrete order quantities: • Calculate the EOQ, Qo. • Find the integers Q’ and Q’-1 that surround Qo. • If Q’×(Q’-1) is less than or equal to Qo2, order Q’. • If Q’×(Q’-1) is greater than Qo2, order Q’-1.

  16. Uncertainty in demand and costs Error in parameters • Few organizations know exactly what demand they have to meet in the future. • The variable cost is stable around the EOQ and small errors and approximations generally make little difference.

  17. Adjusting the order quantity

  18. or

  19. or

  20. Adding a finite lead time • Time for order preparation • Time to get the order to the right place in suppliers • Time at the supplier • Time to get materials delivered from suppliers • Time to process the delivery

  21. Reorder level The amount of stock needed to cover the lead time is also constant at: Lead time × demand per unit time Reorder level = lead time demand = lead time × demand per unit time ROL = LT × D

  22. (b) Substituting value LT = 2 and D = 100, gives ROL = LT × D = 2 × 100 = 200 units As soon as the stock level declines to 200 units, Carl should place an order for 250 units.