Rajasthan northern area development projects contractors suppliers presentation january 2006
This presentation is the property of its rightful owner.
Sponsored Links
1 / 27

Rajasthan Northern Area Development Projects Contractors / Suppliers Presentation January 2006 PowerPoint PPT Presentation


  • 41 Views
  • Uploaded on
  • Presentation posted in: General

Rajasthan Northern Area Development Projects Contractors / Suppliers Presentation January 2006. Northern Field Developments. Contents Cairn India Field Development Plans Mangala Field Development Status Contracting Strategy Local Content strategy Execution strategy Cairn team

Download Presentation

Rajasthan Northern Area Development Projects Contractors / Suppliers Presentation January 2006

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Rajasthan northern area development projects contractors suppliers presentation january 2006

Cairn India

Rajasthan Northern Area Development Projects

Contractors / Suppliers Presentation

January 2006


Northern field developments

Cairn India

Northern Field Developments

  • Contents

  • Cairn India

  • Field Development Plans

  • Mangala Field Development

    • Status

    • Contracting Strategy

    • Local Content strategy

    • Execution strategy

  • Cairn team

  • Payment for work done

  • Project objectives

  • Core issues

  • Strategic view

  • Expectations


Cairn india

Cairn India

Cairn India

  • In India since 1995

  • Head Quartered at Gurgaon, Haryana

  • Two Existing producing assets at Ravva, CB-OS/2 including Lakshmi and Gauri

  • With New World Class Resource Base in Rajasthan where :-

  • Cairn has 100% interest during Exploration Phase

  • 70% interest during Development & Production Phase with ONGC as JV partners having 30% interest


Cairn india1

Cairn India

Cairn India

Ravva – Facilities

  • Opex <$1/boe

  • ISO 14001 certified - Zero flaring

  • Uptime of Equipment : >96%


Cairn india2

Cairn India

Cairn India

CB-OS/2 : Lakshmi & Gauri Facilities

  • ISO 14001 certified

  • Uptime of Equipment : >96%


Cairn india3

Cairn India

Cairn India

CBOS/2 – Future Development

CB-X

Lakshmi & Gauri

FDP approved in March 2006

Development for gas is ongoing

4 well drilling programme in 2007 to access untapped natural gas & apprise further crude oil potential

SuvaliTerminal

Lakshmi

Shell /TotalLNG Terminal

Ambe

North Tapti

Hazira

Gauri

Ambe

Declaration of commerciality Jan 2006

FDP under preparation


Cairn india4

Cairn India

Total original

block area

= 11,108 km2

Cairn India

Rajasthan – Block Overview

  • Major discoveries in Rajasthan

  • ~130 wells drilled, 20 discovers to date

  • Significant discoveries are Mangala, Aishwariya and Bhagyam

  • New oil province established – resource base around1 billion barrels

  • Over US$600m (net risked capital) investment to date

  • Target Block Production ~150,000bopd


Northern field developments1

Cairn India

Northern Field Developments

  • Field Development Plans

  • We are aiming for Saraswati and Raageshwari oil fields to be on stream in 2007 subject to GOI approval and finalisation of an oil sales agreement. As of today some wells are available for export of oil

  • Mangala oil field, including Raageshwari gas field and the Thumbli water aquifer, is the first major field to be developed

  • Next in line will be Bhagyam / Shakti and Aishwariya oil fields, 6 and 12 months behind Mangala respectively. Detailed design and engineering is being run in parallel

  • A single MPT (Main Process Terminal) will be constructed to accommodate these fields


Northern field developments2

Cairn India

Northern Field Developments

  • Field Development Plans (cont)

  • Other smaller fields will be looked at on a case by case basis as the infrastructure surrounding the larger discoveries are completed e.g. Raageshwari Oil

  • Cairn continue to appraise further areas of the existing Rajasthan blocks


Rajasthan development schedule

Cairn India

2005

2006

2007

2008

2009

FIELD / ITEM

MANGALA / RAAG GAS

Land Acquisition / Clearances

Project Definition (Concept/FEED)

Detailed Design & Engineering

Fabrication / Construction

Procurement start

Wells

Commissioning / Start Up

l

BHAGYAM / SHAKTI

Land Acquisition / Clearances

Project Definition (Concept/FEED)

Detailed Design & Engineering

Fabrication / Construction

Wells

Commissioning / Start Up

AISHWARIYA

Land Acquisition / Clearances

Project Definition (Concept/FEED)

Detailed Design & Engineering

Fabrication / Construction

Wells

Commissioning / Start Up

SARASWATI

Land Acquisition / Clearances / Eng.

Legend:

Fabrication / Construction / Wells

CGWA

appr

. rec.

Commissioning / Start Up

EC granted

RAAGESHWARI OIL

FDP approved

Land Acquisition / Clearances / Eng.

DOC app. expected

Fabrication / Construction / Wells

Commissioning / Start Up

FDP app. expected

Rajasthan – Development Schedule


Northern field developments3

Cairn India

Northern Field Developments

  • Current Status

  • Sanction

  • Funding in place

  • Target for Mangala oil at 100,000 Boe/day is 2009

  • Procurement

    • EOI’s issued expect complete early 2007

    • RFQ’s issued expect complete end 2007


Northern field developments4

Cairn India

Northern Field Developments

  • Current Status (cont)

  • Engineering

  • Mangala and Raageshwari gas detailed design at 20%

  • Bhagyam, Shakti, Aishwariya concept selection complete FEED in progress and due to complete April 2007

  • Site

  • Pioneer Camp (site office) in place

  • Site fence erection in progress at Terminal site


Northern field developments5

Cairn India

Northern Field Developments

  • Current Status (cont)

  • Still to be developed

  • Raageshwari Oil Field

  • Raageshwari deep gas

  • Other small fields following main infrastructure completion

  • Other Projects

  • X-port Pipeline – FEED/concept select in progress – to complete January 2007

  • Expected value $340m (Rs 1,500 crore)


Northern field developments6

Cairn India

Northern Field Developments

Approvals Status


Mangala processing facilities

Cairn India

Mangala Processing Facilities

Animated views of Mangala processing facilities

Slug Catcher


Mangala field development

Cairn India

Mangala Field Development

  • Contract Strategy

  • Detailed Design Work

  • Man hour reimbursable at rates

  • Existing contract for Mangala with Mustang Engineering Houston. Work subcontracted to L&T Valdel in Bangalore and JPK Triune in Delhi

  • Procurement

  • Lump sums supply – currently by Cairn, option for main contractors to procure for and on behalf of Cairn

  • Main Contracts

  • Based on cost reimbursable rates measurable using RHICOMS

  • (Rider Hunt International Common Norms)

  • Bill of quantities with agreed measure on a monthly basis

  • Commissioning and Start-up will be by Cairn with contractor support at reimbursable man hour rates


Mangala field development1

Cairn India

Mangala Field Development

  • Local Content Strategy

  • We are committed to maximising local content levels. Main contractors will be required to meet the minimum local content requirements.

  • We intend to nominate subcontractors where we feel confident that a local contractor would have the required experience and quality standards required


Mangala field development2

Cairn India

Mangala Field Development

  • Execution Strategy

  • Site living and sleeping accommodation will be provided by Cairn through a separate sub-contract. We would expect any site offices to be provided by the individual contractors. Cairn will provide and give access to any land required for offices and storage of materials.

  • We would expect personnel to be rotated out of site

  • Procurement of key long lead equipment is being carried out by Cairn from their India HQ at Gurgaon.

  • Manufacturing and materials will be based on preferred Indian content


Mangala field development3

Cairn India

Mangala Field Development

  • Execution Strategy (cont)

  • Main Contracts, preferred Indian JV or partner contractors with experience and capability, execution to mechanical completion, bulk procurement

  • Contact split as follows

    • Main Civil Contractor

    • Main Mechanical

    • Main Instrument and Electrical

    • Pipeline (s)

    • Camp Provider

    • Freight forwarding

    • ICS(integrated Control System)


Mangala field development4

Cairn India

Mangala Field Development

  • Execution Strategy (cont)

  • Main Civil Work Scope

    • All civil engineering work with in the development area. To include roads, all building, tank, plant and process equipment and pipe work foundations, excavations, underground concrete tanks and separation pits and the like.

  • Main Mechanical Work Scope

    • All mechanical equipment installation, hook-up and mechanical commissioning to hand over. To include all site erected tanks and associated pipe work.


Mangala field development5

Cairn India

Mangala Field Development

  • Execution Strategy (cont)

  • Main E& I work Scope

    • To include all HV and LV cable installation terminations, transformers, JB’s and testing to mechanical completion. Includes all security installation work and telecommunications. Include inter field HV transmission lines

  • Pipeline

    • To include all interconnecting pipelines from Thumbli Field to Mangala and from Raageshwari to Mangala. To include all excavation, rail and road crossings, welding and backfilling. To include commissioning to mechanical completion.


Mangala field development6

Cairn India

Mangala Field Development

  • Execution Strategy (cont)

  • Camp Contractor

    • Provision of 130 client accommodation and 2500 construction accommodation camps. To include provision of all hotel services for multi cultural work force. Provision of camp to include provision of water and sewage management and waste disposal.

  • ICS Contractor

    • Provision of all hard ware and software associated with the development of a fully integrated process control system. Provision will include the function testing and commissioning of the system. Contract to include provision for ongoing maintenance work


Mangala field development7

Cairn India

Mangala Field Development

  • Execution Strategy (cont)

  • Note

  • All contracts will have potential for the extension of the work to include the development of the Bhagyam, Aishwariya and Shakti fields currently in FEED design.


Northern field developments7

Cairn India

Northern Field Developments

  • Payment

  • Cairn Finances are in place as widely reported.

  • Work will be carried out on RHICOMS. Work will be measure monthly and appropriate valuation submitted for payment.

  • Mobilisations and de-mobilisations to site are Lump Sum

  • Cairn are implementing a SAP financial system such that all payments will be expedited effectively


Northern field developments8

Cairn India

Northern Field Developments

  • Project Objectives

  • Schedule – to meet 2009 production target

  • Quality - to meet international standards and achieve greater than 98% reliability of the process plant in continuous operation

  • Safety – zero fatalities and a TCRF of less than 0.7

  • Environmental – to have zero releases and minimal long term environmental impact

  • Cost - to meet approved budgets


Northern field developments9

Cairn India

Northern Field Developments

  • Core Issues

  • Remote location little or no infrastructure

  • Low indigenous skill base in Rajasthan but who have high expectations

  • Water supply currently aim to develop water aquifers at Thumbli but this will be in parallel with construction work

  • Safety is always a challenge but zero fatalities is a must


Northern field developments10

Cairn India

Northern Field Developments

  • Expectations

  • We expect to have RFQ’s for Mangala developments issued by the end third quarter of 2007. Long lead items by end first quarter 2007

  • We expect to place all main contracts by end of 2 Q 07

  • Expected start dates on site as follows :

  • Civil End 2Q 2007

  • Mechanical End 3Q2007

  • E&I End 3Q 2007

  • Pipeline (infield) End 4Q 2007