An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LARP QXF plan G. Ambrosio Lab Coordination Meeting March 21, 2013

  2. Assumptions • We need the first short model ASAP • All US labs start QXF work by making short coils (critical path) • Use as much as possible available infrastructure and equipment • Assembly of SQXF1 at LBNL • LQXF test facility not available before 2016 • LQXF plans delayed for SQXF work • LQXF plans delayed by 6 months • Limited budget • No need of new infrastructure • SQXF structure can be procured by CERN

  3. Plans for SQXF1 • Coil fabrication: • Winding & curing at FNAL • Reaction & Impregnation at BNL and LBNL • One coil at FNAL in preparation for LQXF coils • Trace development at LBNL • First “good coil” tested in mirror structure (FNAL) • CERN: W&C, R&I • Structure assembly at LBNL • Two structures procured by CERN: one for LARP one for CERN • Test at FNAL • At 2.2 K with present set-up • Need top-head upgrade for 1.9 K

  4. Plans after SQXF1 • SQXF: • Coil Winding & Curing at CERN (FNAL as backup) • Coil Reaction & Impregnation at LBNL and CERN • Structure assembly at LBNL or CERN • Test at FNAL or CERN • LQXF: • Coil Winding & Curing at FNAL • Coil Reaction & Impregnation at BNL and FNAL • Structure assembly at LBNL • Test at FNAL (horizontal test facility)

  5. Schedule • We need the first short model ASAP • All US labs start QXF work by making short coils (critical path)

  6. Schedule Milestones • SQXF coil fabrication start: 03/14 • SQXF mirror test: 01/15 • SQXF1 test: 05/15 • SQXF1b test: 12/15 • LQXF coil fabrication start: 01/15 • LQXF1 test: 01/16 • LQXF1b test: 07/16 • LQXF2 test: 01/17 • LQXF2b/3 test: 0717