Testing Approach Proposal - 3 Test Phases. Phase 1: ERCOT and TDSPs 1 st Phase of testing will be between ERCOT and the TDSPs 3 week duration 1 week of initial testing 1 week for rework 1 week for retest. TESTING ENTITY. ERCOT. Phase 2: ERCOT and CRs

Download Presentation

Testing Approach Proposal - 3 Test Phases

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Testing approach proposal 3 test phases

Testing Approach Proposal - 3 Test Phases

  • Phase 1: ERCOT and TDSPs

  • 1st Phase of testing will be between ERCOT and the TDSPs

  • 3 week duration

  • 1 week of initial testing

  • 1 week for rework

  • 1 week for retest

TESTING ENTITY

ERCOT

  • Phase 2: ERCOT and CRs

  • 2nd Phase of testing will be between ERCOT and the CRs

  • 6 week duration

  • 3 weeks of initial testing

  • 1 week for rework

  • 2 weeks for retest

TDSPs

CRs

  • Phase 3: TDSPs and CRs

  • 3rd Phase of testing will be between the TDSPs and the CRs

  • 6 week duration

  • 3 weeks of initial testing

  • 1 week for rework

  • 2 weeks for retest


Naesb 1 6 timeline milestones

NAESB 1.6 Timeline/Milestones

MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB

03 03 03 03 03 03 03 03 04 03

  • Initiation

  • Initial strategy sessions

  • Draft survey compiled

  • Draft guideline compiled

  • High-level time line identified

  • Project sourced at ERCOT

  • Planning

  • Survey issued; results gathered

  • Guideline approved and published

  • Schedules & dependencies identified

  • Project Charter approved

  • Plan finalized and approved

  • Vendor SW available

7/7 Initial Charter & High-level Project Plan developed

6/27 Timeline, Survey, & Imp. Guide Review

9/5 Survey Results back from Market

10/01: Signed Charter Docs Returned/ Plan Finalized/ Testing Schedules Approved/ Vendor SW Available

7/31FERC NAESB Standard Decision

7/14 Implementation Guide Sent to Market for Review

8/25 Survey, Guide, and Project Charter published to Market

Continued on Next Slide


Naesb 1 6 timeline milestones1

NAESB 1.6 Timeline/Milestones

OCT NOV DEC JAN FEB MAR APR MAY JUN JUL

03 03 03 04 04 04 04 04 04 04

  • Execution

  • ERCOT chges implemented

  • MP changes implemented

  • Cycled Testing

  • Scheduled Migrations

  • Closure

  • Lessons Learned

  • Operations support

11/14 TCW Forms Ret- urned

12/01 Phase 1 Test Start: ERCOT-TDSP’s

10/01 Market Dev Start

1/05 Phase 2 Test Start: ERCOT-CR’s

2/13 Phase 2 Test End

4/05 Migration Start

4/26 TX SET 2.0 Connectivity Test Start for New MPs

12/19 Phase 1 Test End

10/27 TCW form sent to Market for Completion

2/16 Phase 3 Test Start: TDSP’s-CR’s

3/26 Phase 3 Test End

4/16 Migration End

4/23 Lessons Learned Mtg

Mid-May: Close Project