Project Communication, Tracking, and Reporting

Project Communication, Tracking, and Reporting. Importance of Good Communications. The greatest threat to many projects is a failure to communicate Our culture does not portray IT professionals as being good communicators

baris
Download Presentation

Project Communication, Tracking, and Reporting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Communication, Tracking, and Reporting

  2. Importance of Good Communications • The greatest threat to many projects is a failure to communicate • Our culture does not portray IT professionals as being good communicators • Research shows that IT professionals must be able to communicate effectively to succeed in their positions • Strong verbal skills are a key factor in career advancement for IT professionals

  3. PMBOK – Project Communications Management Processes • Communications Planning — attempts to answer: • How will information be stored? • How will knowledge be stored? • What information goes to whom, when, and how? • Who can access what information? • Who will update the information and knowledge? • What media of communication is best?

  4. PMBOK – Project Communications Management – Continued • Information Distribution—getting the right information to the right people in the right format • Performance Reporting—collection and dissemination of project information to the various project stakeholders. • Administrative Closure—verifying and documenting the project’s progress.

  5. Project Communications Plan • can be formal or informal, depending on the needs of the project stakeholders and the size of the project • communications plan should determine: • Who has specific information needs? • What are those information needs? • How will a particular stakeholder’s information needs be met? • When can a stakeholder expect to receive this information? • How will this information be received?

  6. Project Communications Plan

  7. Project Communications Plan

  8. Media Choice Table

  9. Project Metrics • Project Metric - qualitative measurement of some attribute of the project. • Project metrics should focus on the following key areas: • Scope • Schedule • Budget • Resources • Quality • Risk

  10. Project Metrics

  11. A good project metric should be:Edberg, 1997 • Understandable • Quantifiable • Cost Effective • Proven • High Impact

  12. Project Measurement PrinciplesMeyer, 1994 • A measurement system should allow the team to gauge its progress. • The team should design its own measurement system. • Adopt only a handful of measures. • Measures should track results and progress.

  13. Dashboard Metric

  14. Monitor And Control Progress • Purpose of Control • To track progress • To detect variance from plan • To take corrective action

  15. Monitor And Control Progress • Tracking Techniques • Conducting periodic project status meetings in which each team member reports progress and problems • Evaluating the results of all reviews conducted throughout the software engineering process • Determining whether formal project milestones have been accomplished by the scheduled date. • Comparing actual start date to planned start date for each project task listed in the project table • Meeting informally with practitioners to obtain their subjective assessment of progress to date and problems.

  16. Monitor And Control Progress • Graphical Reporting Tools • Gantt Charts • Milestone Charts • Metrics • Cost Schedule Control(Earned Value)

  17. Gantt Chart Project Status Report

  18. Earned Value • Suppose you just signed a contract with a consulting firm called Dewey, Cheatem, and Howe for developing an IS. • Project Budget, Schedule, Tasks • $40,000 • 4 months • 20 Tasks (evenly divided over 4 months) • $2,000 per task • 5 tasks per month • Therefore , you plan to pay $10,000/month. This is called budgeted cost of work scheduled (BCWS).

  19. Planned Budget-Budgeted Cost of Work Scheduled (BCWS)

  20. End of Month 1 Dewey, Cheatem, & Howe Amount Due: $8,000 Payment due immediately! page 1 of 2 Actual Cost of Work Performances (ACWP) Invoice

  21. BCWS Versus ACWP Is your project ahead of budget $2,000 ?

  22. Dewey, Cheatem, & Howe Work Completed for Month 1 Task A - $2,000 Task B - $3,000 Task C - $3,000 page 2 of 2 Complete only 3 from 5 tasks Invoice Spent $8,000 to achieve only $6,000 of actual work 6,000 is Earned Value

  23. Comparison of BCWS, ACWP, and Budgeted Cost of Work Performed (BCWP)

  24. Definitions • Budgeted Cost of Work Scheduled (BCWS) • Planned expenditure cash flows based on the completion of tasks in accordance with the project’s budget and schedule • Actual Cost of Work Performed (ACWP) • Actual Project Expense based on completed tasks • Earned Value or Budgeted Cost of Work Performed (BCWP) • The amount of the budget that we should have spent for a given amount of work completed

  25. Cost/Performance Indicators

  26. Cost Metrics • Cost Variance (CV)-The difference between a task’s estimated cost and its actual cost: • CV = BCWP - ACWP • Negative Value = over budget and/or behind schedule • Positive Value = under budget and/or ahead of schedule • Cost Performance Index (CPI)-percentage of work completed per dollar spent • CPI = BCWP  ACWP • ratio > 1 = ahead of schedule and/or under budget • ratio < 1 = behind schedule and/or over budget

  27. Cost Variance

  28. Schedule Metrics • Schedule Variance (SV) – the difference in terms of cost between the current progress and our originally scheduled progress • SV = BCWP – BCWS • Schedule Performance Index (SPI) – a ratio of the work performed to the work scheduled. • SPI = BCWP  BCWS • ratio > 1 = ahead of schedule and/or under budget • ratio < 1 = behind schedule and/or over budget

  29. Schedule Variance

  30. Earned Value Metrics • Minimum Funds Needed if things do not get worse • Minimum funds = Original total budget  CPI • Funds Needed if things continue to get worse at the same level of slippage • Funds Needed = Original total budget  (CPI x SPI)

  31. Reporting Performance and ProgressReporting Categories • Reviews • Formal & informal meetings with stakeholders • May focus on specific deliverables or milestones • Used to get acceptance, surface problems or issues, or make key decisions

  32. Reporting Performance and ProgressReporting Categories • Status Reporting • Describes present state of the project • Compares actual progress to baseline plan • Scope, schedule, and budget • Like a snap shot of the project at a specific time

  33. A run up or down of four or more successive data points

  34. A Change of More Than Three Standard Deviation

  35. Reporting Performance and ProgressReporting Categories • Progress Reporting • What activities or tasks has the team accomplished? • Actual versus planned • Forecast Reporting • Predicting the project’s future status or progress • Example: trend analysis

  36. Information Distribution • Face-to-Face Meetings (F2F) • Telephone, email, other wireless technology • Collaboration technology • NetMeeting, Groove, Notes, Exchange

  37. Running Effective Meetings • Determine if a meeting can be avoided • Define the purpose and intended outcome of the meeting • Determine who should attend the meeting • Provide an agenda to participants before the meeting • Prepare handouts, visual aids, and make logistical arrangements ahead of time • Run the meeting professionally • Build relationships

  38. Using E-Mail Effectively • Make sure that e-mail is an appropriate medium for what you want to communicate • Be sure to send the e-mail to the right people • Use meaningful subjects • Limit the content to one main subject, and be as clear and concise as possible • Limit the number and size of attachments • Delete e-mail you don’t need, and don’t open it if you question the source • Make sure your virus software is up to date • Respond to and file e-mails quickly • Learn how to use important features

  39. Using Templates for Project Communications • Many technical people are afraid to ask for help • Providing examples and templates for project communications saves time and money • Organizations can develop their own templates, use some provided by outside organizations, or use samples from textbooks • Recall that research shows that companies that excel in project management make effective use of templates

  40. Sample Template for a Monthly Progress Report

  41. Sample Template for a Letter of Agreement for a Class Project

  42. Outline for a Final Project Report

  43. Communication and Collaboration Matrix

  44. The BITTC KMS Extranet

  45. BITTC Project Team’s Learning Cycle