1 / 52

NBS-M017 – 2013 CLIMATE CHANGE: GOVERNANCE AND COMPLIANCE

NBS-M017 – 2013 CLIMATE CHANGE: GOVERNANCE AND COMPLIANCE. Transmission issues for the Future Mechanisms to Promote Renewable Energy Non Fossil Fuel Obligation Renewable Obligation Feed in Tariffs Renewable Transport Fuel Obligation Renewable Heat Incentive? An Integrated Obligation?.

aysel
Download Presentation

NBS-M017 – 2013 CLIMATE CHANGE: GOVERNANCE AND COMPLIANCE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NBS-M017 – 2013 CLIMATE CHANGE: GOVERNANCE AND COMPLIANCE • Transmission issues for the Future • Mechanisms to Promote Renewable Energy • Non Fossil Fuel Obligation • Renewable Obligation • Feed in Tariffs • Renewable Transport Fuel Obligation • Renewable Heat Incentive? • An Integrated Obligation?

  2. 2006 - 2007 2012 - 2013 40271759 27501565 2268 1165 SHETL SHETL SPT SPT Upper North Upper North 2513 3912 578711092 600511191 5708 4380 6205 4561 1320 7834 7264 6100 6612 North Netherlands North 11709 9223 Midlands Midlands 11274 11258 7804 9374 8480 8992 Central Central 6818 5305 5186 5900 32416751 27926704 Estuary 29271153 31971999 Estuary 1774 1188 1988 1988 South West South West 14332 25720 16537 28267 France France 2

  3. Transmission Network in the UK 400 kV 275 kV 132 kV Scotland Historically transmission networks have been different in England and Wales compared to Scotland Beauly Denny Line is a constraint – upgrade has raised over 18000 objections England and Wales Англия и Уэльс Transmission throughout England, Wales and Scotland became unified on April 1st 2005 3

  4. AC : DC transmission of electricity 1000 MW over 100 km 5 AC cables each with 3 cores required Equivalent DC AC Transmission current flows in skin – much of cable is not used DC Transmission current flows in whole of cross section 4

  5. AC : DC transmission of electricity • DC transmission is purely resistive and decreases slowly with distance • AC transmission is inductive and resistive and power falls off rapidly even when compensation is provided 5

  6. Existing Interconnectors Shetland Orkney Lewis Dounreay Peterhead Torness DockingOffshore Killingholme Walpole East Claydon Sundon Grain 2020 Offshore DC Network Norway Offshore Marine Node Onshore Node Germany Netherlands 300 MW 700 MW 1000 MW 6

  7. Costs of East Coast DC Network • Stage 1 Core Network: £1.6b • Stage 2 full Network: £4.8b • Average cost £750 per MW-km • Would be built in sectors: • Typical Segment costs: • Peterhead to Walpole: £381M (1000 MW cable – 608 km) • Peterhead to North Scotland Offshore Marine Hub £412M (2000 MW cable – 245 km) • For details see WEB Links West Coast DC Links from North Scotland to Mersey are also being examined

  8. Mechanisms to Promote Renewable Energy NBS-M017/NBSLM04D – 2011 CLIMATE CHANGE: GOVERNANCE AND COMPLIANCE • Non Fossil Fuel Obligation • The Renewable Obligation • Feed in Tariffs • The Renewable Transport Obligation • Renewable Heat Incentive • An Integrated Obligation? 8

  9. Non Fossil Fuel Obligation: NFFO-1 • Introduced at time of Privatisation in 1990 • Initially seen as a subsidy for nuclear, but later termed NFFO with separate tranche for Renewables • NFFO became associated only with Renewables and was subdivided into technology bands • 5 Tranches: NFFO-1, NFFO-2, NFFO-3, NFFO-4, NFFO-5 • NFFO-1 (1990) required a minimum contribution of 102 MW from new "renewables" • Contracts made 152 MW but by November 2000 the residual capacity was 144.5 MW. • Fixed Price paid for electricity generated. • Wind had highest guaranteed price of 11p per kWh compared with typical consumer price at time of 6 – 7p and wholesale prices around 3p. This meant that there was a substantial subsidy for wind. • Potential generators had to submit applications for the subsidy, but not all ultimately received planning permission, or alternatively the schemes ultimately failed through lack of finance. • Subsidy was paid until 31st December 1998 – a limit initially placed by the EU 9

  10. Non Fossil Fuel Obligation: NFFO-2 • As with NFFO-1 a fixed price was paid to all generating capacity • NFFO-2 (1991) was further divided the capacity by technology type and the outcome was as indicated in the table below. • The payments under NFFO-2 also expired on 31st December 1998 Note: Because payments started 1 year later, there was effectively 12.5% less subsidy than for NFFO-1 10

  11. NFFO – 3 – January 1995 • As with previous tranches many of the schemes failed through planning permission etc. • Clearance was given from EU for NFFO-3 to extend beyond 1998, and covers period up to 30th November 2014 • Unlike NFFO -1 and NFFO-2, the price paid for renewables was not a fixed price. Each potential supplier had to bid to supply electricity. • Within any one technology band, there were a number of different bids. • Total tranche was 627.8 MW divided between technology bands- successful ones were those which required the least subsidy to provide this amount of installed capacity. • NFFO –Orders 4 and 5 • NFFO orders 4 and 5 were announced in mid 1990s and came into effect in 1996 and 1998 respectively. • Very similar to NFFO-3 and both have a twenty year timescale finishing in 2016 and 2018 respectively. • The bid prices were noticeably lower than for NFFO-3.

  12. Actual Contracts for different NFFO Tranches NFFO Tranche 12

  13. NFFO Status as at end of December 2006/2010 • Overall actual position as opposed to contracted • Many NFFO projects did not get off ground because contracts to supply were made before planning and grid issues had been addressed. • Situation with wind even more dramatic. 13

  14. Renewables Obligation • 1999/2000 UK Government considered different mechanisms to promote renewables following end of NFFO. • NFFO 1 and NFFO 2 were a form of feed in tariff now used by Germany • NFFO 3, 4, and 5 were a derivative of this - generators bid to supply and cheapest were given a guaranteed price for whole of life of project up to 20 years. • Other mechanisms considered • Climatic Change Levy (CCL) goes a small way to encouraging renewables, but only applies to businesses and is at a fixed rate of 0.43p per kWh. • Charge was neutral to businesses overall as there was a rebate for the Employers National Insurance Contribution. Energy Efficient business with large staff numbers benefitted. • Direct Grants for Renewable Energy Projects • Energy Taxes/Emissions Trading • Renewable Obligation – targets set for each year and a mechanism of payments for failure to comply.

  15. On whom should Obligation Fall Generators System Operator (National Grid) Distributed Network Operator Supplier Consumer For various reasons the obligation fell on Suppliers For an enhanced move towards low carbon an obligation on large businesses may be more effective but retaining obligation on suppliers for small businesses and domestic market. >> An integrated renewable obligation ????????? Decision taken that only Suppliers should be Obligated Renewables Obligation

  16. Requires all suppliers to provide a minimum percentage of electricity from Eligible (New) Renewables. Until 31st March 2010 Each 1 MWh generated by renewable qualified for a Renewable Obligation Certificate (ROC) From April 1st 2010 technologies were banded so some technologies got more than, and some less than, 1 ROC per MWH Obligation increases each year – currently it is ~ 12.4% of electricity supplied to consumers. Accounting Period is 1st April – 31st March Compliance can be achieved by: Either Generating sufficient renewable energy to get required number of ROCs Purchase ROCs from another generator Pay a Buy – Out Fine Buy-Out set initially at £30 / MWh but indexed linked each year. This is decided by OFGEM usually in January preceding accounting period and is currently (2012-13) set at £40.71 Renewables Obligation

  17. Renewables Obligation The percentage obligation was initially set as far as 2010 – 2011, but later extended to 2015 – 2016. The scheme has now been extended to 2037, but with a maximum duration of 20 years for any scheme Buy Out Price is increased annually by OFGEM and is approximately equal to CPI. Total Buy Out market has a value of around £300M+ but fell to ~£120M in 2011-2012 * Original declared figures – situation more complex with banding 17

  18. Renewables Obligation Proportion generated by each technology 2011 - 2012 Proportion generated by different technologies. Some were very small amounts – see table Note: Since 2009, most small scale hydro, wind and photovoltaic RO generation has been transferred to FITs Link to ROC_Register

  19. Renewables Obligation 2011 - 2012 Load Factors 2011 - 2012 Load Factors 2009 - 2010

  20. Renewable Obligation Banding and changes post 2013

  21. Renewable Obligation Banding and changes from 2013

  22. Renewable Obligation Banding and changes from 2013 • The Renewable Obligation will close for new entrants on 31st March 2017, and subsequently all new entrants will be subject to Electricity Market Reform Regulations. • Existing Renewable generators can opt into EMR if they wish. • From 2014 – 2017 – New generators can opt for either RO or EMR.

  23. Renewable Obligation Certificates Notifies OFGEM of compliance -i.e. ROCs or pays FINE Notifies Regulator how much generated. ROC’s issued FINES recycled to holders of ROCs in proportion to number of ROCs held. Sells Electricity with or without ROCs Supplier Buys ROCs from Trader Sells ROCs to Trader The Regulator OFGEM Renewable Generator SUPPLIERS Trader and Brokers Because of recycling, ROCs have value greater than their nominal face value

  24. Incentives under the Renewable Obligation Prices per kWh • Several benefits to generator (e.g. wind) • Whole sale price of Electricity • Value of the Renewable obligation Certificate • Mark up price arising from Buy- Out Fines • Other small benefits • BUT if target is met – ROC certificates become worthless • Overall value might be up to 10p but could be much less • At highest level of incentive – i.e. actual current value of ROC ~ 4.2p cost for reducing 1 tonne of CO2 ~ £78 per tonne Recycled Fines 1.0 – 1.5p But only 0.338p in 2011-12 (announced 4/10/2012) Wholesale Price Average 2012 ~4.5p Jan 2011 4.950p cf Jan 2010 4.521p ROC Certificate 3.869p [2011-12 value] 4.071p 2012/13

  25. The Value of the ROC Market The Figures in the “Value of ROC Market” are slightly lower than predicted for data because of non-payment by companies who ceased trading. This figure amounts to around £5M a year.

  26. The Value of the ROC Market ** After the introduction of banding, the Obligation is now determined in terms of ROCs, rather than MWH as previously The Figures in the “Value of ROC Market” are slightly lower than predicted for data because of non-payment by companies who ceased trading. This figure amounts to around £5M a year.

  27. An Example what is likely value by March 2010 Buy out price for 2009 – 2010 £37.19 per MWh Estimated demand is 360 TWh Obligation is 10.4% Requirement from renewables is 360*0.104 TWH = 37440000 MWh At April 1st 2008 there were6250 MWinstalled having an average load factor over all technologies of 30%. In 2009 – 2010 will generate 6250*8760*0.3 = 16425000MWh Assume 1500 MWinstalled in 2008 – 2009 At same load factor will generate 3942000 MWh in 2009 – 2010 Assume2500 MWinstalled mid way through 2009 - 2010 At same load factor will generate 3285000 MWh in 2009 – 2010 Total generated by renewables = 23652000 MWh A shortfall of13788000 MWhon which Buy Out would be payable ROC Market: How total value of ROCs is estimated Simplified Analysis pre banding NOTE: Simplified Version – assuming all technologies have same load factor

  28. shortfall of 13788000 MWh on which Buy Out would be payable Buy Out Price: £37.19 Total value of Buy Out Fund = £512781235 ROCs presented = 23652000 MWh Recycled value =£21.68 per ROC Total value of ROC = £58.87 If 5000 MW were commissioned instead of 2500 in 2009 – 2010 Total Buy Out Fund would be£390610771 Recycled Value per ROC would be £14.50 Total Value of ROC = £51.69 Note: with banding analysis is a little more complicated. What happens if generation exceeds compliance level? ROC Market: How total value of ROCs is estimated

  29. ROC Market – the Cliff Edge Problem 12993 MW Buy Out Price Target could be exceeded in particularly favourable weather conditions. Buy Out Fund would have no money in it and ROCs would become worthless leading to instability in price.

  30. Banding System was introduced from 1st April 2009. Reference projects such as on-shore wind will continue to get 1 ROC per MWh, Technologies such as offshore wind get 2.0 ROCs per MWh, Solar PV, advanced gasification Biomass get 2.0 ROCs per MWh, Co-firing generates 0.5 ROCs per MWh With no banding: incentive only to exploit established technologies Banding will enhance returns for developing technologies. If targets are kept the same, it is easier to achieve targets and “Cliff Edge” Problem could become acute. Targets for a given % of renewables in terms of MWh will not be met under current legislation if there is an upward drift in banding. Only if reduced ROCs from co-firing balance enhanced ROCs from newer technologies will system remain stable. Developments in the Renewables Obligation

  31. Setting the Level of the Renewable Obligation (1) • Until 2009, there was exact parity between the number of MWH generated and the ROCs issued. • With banding, the situation became more complex and to avoid the Cliff Edge Problem a headroom calculation system was introduced as an alternative to a Fixed percentage • Specific procedures have varied from year to year – see Renewables section of Module Web Page for specific details of a particular year. • Example – setting level for 2013-14 as recently published – 28th Sept 2012 • Target for 2013-14 …………..13.4% of electricity supplied by LICENSED SUPPLIERS should be from eligible Renewable Sources - (slightly different in Northern Ireland) – • >>>>>>>>>Equates to 0.134 ROCs per MWH, • Some renewables generate more ROCs than others and some less. • Could result in proportionally more or less renwables than target depending on average banding level

  32. Setting the Level of the Renewable Obligation (2) • Two Calculations needed: • FIXED TARGET – based on a fixed target of0.134 ROCs per MWh • HEADROOM TARGET - a ROC Target based amount of renewable electricity expect to be generated uplifted by 10% headroom • This approach takes into account • existing and projected capacity due to come on stream • The relevant banding of each Technology • The actual load factors as achieved in previous year. • The actual target for a given year is the higher of (A) and (B) • For 2013/14 based on the predicted demand, the number of ROCs under calculation A would be 40 million, whereas under calculation B it would be 61.5 million. • Difference in the two figures is much larger than in previous years because of increasing amounts of offshore wind (which generated 2 ROCs per MWH) coming on line

  33. Setting the Level of the Renewable Obligation (3) • More Specifics for 2013/14 calculations • FIXED TARGET – based on a fixed target of0.134 ROCs per MWh • The projection for total RELEVANT UK Electricity supplied in the year from DECC, National Grid and others is 302.7 MWh – giving a fixed requirement of 40 Million ROCs • B) HEADROOM TARGET (B) is greater than (A) and thus applies - equivalent to a target of 0.206 ROCs per MWH

  34. Setting the Level of the Renewable Obligation (4) Load Factors used in 2013/14 to determine ROC Target

  35. Feed in Tariffs • Unlike Renewable Obligation, a fixed amount per unit generated is paid and is relevant for small generators • Introduced from April 1st 2010 as RO system was overly bureaucratic for small generators. Payment rates depend on size of scheme, date of installation and technology. • e.g. for small scale retro-fitted solar scheme (<4 kW) fitted before March 3rd 2012, the feed in generation tariff payment is currently 45.4p per kWh (with an additional 50% of the export tariff at 3.2p per kWh). • These prices are index linked to CPI and TAX FREE • This amounts to a renewable incentive of ~42p per kWh and £778 per tonne of CO2 saved. ( assuming a wholesale price of ~ 5p) • This is ~9 times the subsidy for onshore wind generation under the ROC scheme

  36. Feed in Tariffs – Introduced 1st April 2010 • Tariffs are index linked each year for existing generators only new generators were affected by revised prices. • Tariffs also available for hydro, anaerobic digestion and mini CHP.

  37. Feed in Tariffs – Example for PV Payment for tariffs will be from a levy on Utility Companies which MAY see a cumulative rise in bills of around £1 billion or more. In addition there is a payment of 3.2p per kWh for any electricity exported as opposed to consumed on premises. BUT an export meter is needed to identify this. Householder will save on imported electricity at ~ 13 – 14p per kWh, so optimum financial model may not be to generate as much as possible i.e. for each unit generated and consumed it is worth 45.4** + 13 = 58.4p /kWh for each unit exported it is worth 45.4** + 3.2 = 48.6 p/kWh If no export meter is fitted for domestic consumers it is deemed that 50% of generation will be exported. i.e. On average each unit is 45.4 + 0.5 *3.2 = 47.0 p/kWh plus 0.5*13 (saved) - i.e. overall approx: 53.5p/kWh ** For installations registered before 03/03/2012 37

  38. Installations under Feed In Tariff Scheme ( to 17/10/2012) • The annual output from all PhotoVoltaic installed is ~ 42GWh – the same output as 9 modern 2 MW wind turbines. • 1 turbine has same output as 2000 – 2500 domestic PV arrays

  39. Growth in Installations under Feed In Tariff Scheme Nop7/10/2012) Note: considerable increase in rate of installation – this led to emergency reviews and earlier reduction in tariffs than originally planned – driven also by a 50%+ reduction in installation costs

  40. Feed in Tariffs – Emergency Reviews The Feed-In Tariff scheme was inherited from proposals from last Government and first indications that changes would take place came in Comprehensive Spending Review in October 2010. The Government will reform the electricity market, so that it attracts the private sector investment necessary to meet the UK’s energy security and climate change objectives, including the investment in nuclear, carbon capture and storage and renewable technology. In addition to supporting the carbon price, this will also assess the role that revenue support mechanisms (such as Feed-In Tariffs), capacity mechanisms and emission performance standards could play. For complete information see Section 4 of http://www.hm-treasury.gov.uk/d/nationalinfrastructureplan251010.pdf

  41. From the National Infra-Structure Plan 2010 following Comprehensive Spending Review The Government will assess proposals against the criteria of cost-effectiveness, affordability and security of supply; • to ensure that regulation of national electricity networks enables the investment needed in transmission infrastructure to connect new low-carbon generation, such as nuclear power stations and offshore and onshore wind turbines; • maintain the Feed-In-Tariffs to support investment in emerging small-scale generation technologies in electricity, saving £40M by improving their efficiency, and complement this with the Renewable Heat Incentive to reward ground-source heat pumps and other renewable heat sources, while making efficiency savings of 20% by 2014-15 compared with the previous government’s plans. For complete information see Section 4 of http://www.hm-treasury.gov.uk/d/nationalinfrastructureplan251010.pdf

  42. From the National Infra-Structure Plan 2010 following Comprehensive Spending Review The Government will (para 4.18): • Support investment in low carbon energy supply by: maintaining Feed-In Tariffs for small-scale generation, funded through an obligation on electricity suppliers equating to a levy of almost £900 million over the period to 2014-15. At the same time, the efficiency of Feed-In Tariffs will be improved at the next formal review [2012], rebalancing them in favour of more cost effective carbon abatement technologies. Domestic PV ~ £750 per tonne saved (till 02/03/2012) now ~£210 Onshore Wind ~ £ 95 per tonne saved Improved insulation < £25 per tonne saved. – see also issues relating to Feed In Tariffs in Germany Equivalent to £36 per household over 5 years For complete information see Section 4 of http://www.hm-treasury.gov.uk/d/nationalinfrastructureplan251010.pdf

  43. Feed in Tariffs and recent changes following consultations • Export Tariff – solar installations before 01/08/2012 and all other installations 3.20 p/kWh otherwise 4.5 p/kWh – assumed at 50% of generation unless metered • Higher Rate for Individual Domestic Properties achieving Energy Standard • Medium Rate for multiple community schemes • Lower Rate for domestic properties not achieving Energy Standard 43

  44. Renewable Heat Incentive - Domestic Domestic Installations – as originally proposed - implementation delayed successively – latest proposed date is Spring 2014. Originally Government – proposed deeming of heat, then required metering. Have returned to deeming but with an option that if one installs metering then an additional payment of £200 - £230 per annum will be paid.

  45. Renewable Heat Incentive from 26/11/11 for Non-Domestic Installations • Original target date for implementation – 1st April 2011 was deferred until November 2011 for large installations and April 2013 for domestic installations. Tier 1 applies annually up to the Tier Break, Tier 2 above the Tier Break. The Tier Break is: installed capacity x 1,314 peak load hours, i.e.: kWth x 1,314

  46. Renewable Heat Incentive • To achieve a 15% Renewable Energy Target by 2020 will require tackling heat (40+% of total energy demand) in addition to transport and electricity. • RHI aims to tackle this for heat pumps, biomass boilers, solar thermal • Problem of metering. Government suggests “Deeming” for small installations - would be open to abuse as it does not account for behaviour

  47. Renewable Heat Incentive: from April 2013 • Renewable Heat Incentive will provide support via an payment for each unit of renewable heat generated. • Scheme has been delayed, now scheduled to start in April 2013 • All eligible installations installed after 15th July 2009 will qualify • Consultation launched on 20th Sept 2012 to decide on actual tariffs paid. Because of delay, one off vouchers are available for householders which must be redeemed by 31st March 2013 or expiry of voucher.

  48. Renewable Transport Fuel Obligation (RTFO) • Came into force 1st April 2008 • EU Directive 2003 • Consultation Document April 2007 • See also UEA’s response on WEB • Ambition to save 1 Mtonnes CO2 by 2010/2011 Financial year UK Target (by volume) 2008 – 09 2.75 % 2009 – 10 3.5 % 2010 – 11 5 % Obligation on Suppliers as with Renewables Obligation Note: EU requirement is for 5.75% by Energy Content Represents 8% by volume. Energy content per litre for bioethanol is very different from energy content of petrol

  49. RTFO mechanism Supplier meets RTFO from sales No Supplier buys certificates or pays fee Pays fee Yes Buys certificates Supplier keeps/sells extra certificates Sells certificates Certificates sold and bought Buy-out fund pool Keeps certificates Reconciliation: Suppliers with certificates receive buy-out fund pool money

  50. The level of the obligation? • Calculated as percentage of volume of fossil fuel sales, rather than of total sales of all fuels • 5 % of total fuels represented as 5.2651 % of fossil fuel sales • Reduces UK commitment further • Reason • Duty paid in terms of volume • Need to switch to energy based pricing • Would make comparison between petrol, diesel and biofuels more rational • Maximum 5 % by volume additive is already permitted in EN-standard petrol and diesel fuels - • Warranty issues • Unlike RO, where recycled money is used in UK, recycled RTFO money is likely to go abroad

More Related