GLAST LAT Tracker
Download
1 / 13

GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A - PowerPoint PPT Presentation


  • 109 Views
  • Uploaded on

GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A. Luca Latronico INFN-Pisa [email protected] Relevant Documents. LAT-PS-01801 Integration of TMCM and SSD Ladders onto Tracker Trays

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A' - aya


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

GLAST LAT Tracker

Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A

Luca Latronico

INFN-Pisa

[email protected]


Relevant documents
Relevant Documents

LAT-PS-01801 Integration of TMCM and SSD Ladders onto Tracker Trays

released – MRB on wire-bonds encapsulation removal requires sigantures approval

LAT-PS-03534 Single Tray Electrical Test Plan

released

Production company: G&A Engineering, Carsoli-Oricola (AQ)


Assembly and test flow chart

INFN provides G&A with tray panels, TMCMs, ladders, (and their relative locations on the tray) + Nusil adhesives

Alignment jig (WS-B1) provides:

TMCM planarity

Pitch adapter planarity

Bonding pads alignment (HV and shield pads)

Dry assembly test to check TMCM connectors clearance

Adhesive distribution (WS-B2)

Assembly of TMCM onto tray (WS-B3)

Metrology (WS-B4)

Wire bonding (WS-B5)

Electrical tests (WS-B6)

Current production rate ramping up:

need to match CC pocket and MCM connector depth

extra screening on TMCM pitch adapter (missing connections on signal strips and HV lines – PA debondings)

alignment jig

Assembly and test flow-chart

WS-A Material receiving

and inspection

WS-B TMCM Integration


Assembly and test flow chart1

Ladder test (WS-C1) their relative locations on the tray) + Nusil adhesives

Tray Z positioning under CMM (WS-C2)

50m wrt nominal position

Ladder positioning on the bridges (WS-C3)

Alignment from bridge itself used as reference and excellent alignment of SSD inside ladder (~2 mm RMS)

Glue deposition (WS-C4)

19 spots of siliconic glue/SSD

4 spots conductive glue + 1 unbroken line across ladders

Ladder assembly (WS-C5)

Ladder metrology (WS-C6)

Ladder height 0.250.1 mm

Ladders relative parallelism of 0.1 mm

Wire bonding (WS-C6)

Destructive pull tests on coupons (>5g each)

Visual inspection

Functional test by INFN with tray inside box

LAT-PS-03534

DRB and shipping to INFN

Ladder assembly tools

Assembly and test flow-chart

WS-C Ladders integration

WS-D Final disposition


Availability of components and tools
Availability of components and tools their relative locations on the tray) + Nusil adhesives

  • Bare panel trays after TVAC test in Roma2

    • 27 trays available – planned supply is 4trays/day

  • SSD Ladders from G&A and Mipot

    • ~1400 ladders available - 400 more from G&A (200 to test, 200 being built) – 900 will be built from Mipot asap

  • MCM from SLAC through quick functional verification at INFN-Pisa

    • Currently 38+32

    • Could match 14 trays (26 TMCMs) from first lot of 38 because of connector stick-out issue

    • 6 TMCMs sent back to SLAC for PA debondings

  • Nusil at G&A for ~3/4 of tray production

  • G&A tools

    • TMCM alignment tools: 5

    • Ladder integration tools (tray alignment + ladder bridges): 6

    • CMM: 2 (1 for alignments, 1 for metrology)

    • Glue dispenser: 2

    • wire-bonder: 2

    • 2 working shifts per day to grant production rate of 4 trays/day

  • EGSE for functional tests

    • 1 full EGSE system installed at G&A and operated by INFN


Data exchange with infn pisa
Data exchange with INFN-Pisa their relative locations on the tray) + Nusil adhesives

  • From INFN to GA:

    • List of subparts (ladders and TMCM) from INFN-Pisa

  • From GA to INFN:

    • List of subparts with G&A reference SNs (neede for tray box)

    • Progress of assembly (weekly)

  • Quality Assurance

    • Rely on G&A certified QA program for internal activity

    • Handle major NCR notified from G&A (MARECO) with Pisa system


Tower 0 tray production
Tower 0 tray production their relative locations on the tray) + Nusil adhesives

  • 14 complete trays assembled (27 TMCMs and SSD Ladder planes)

    • 23 Si layers were within specs

    • 4 Si layers had short for problems related to bias circuit delamination

  • All went through thermal tests

    • 4 Si layers (bottom side of heavy trays) had many disconnected channels because of CTE mismatch impact on wire-bond encapsulation  MRB on wire-bond encapsulation

  • 23 SSD layers operated successfully up to now


Metrology of ladders alignment

y their relative locations on the tray) + Nusil adhesives

x

L02

L02

L03

L01

silicon #1

silicon #2

silicon #3

silicon #4

Pin 1

Pin 3

L11

L13

L12

MCM side

L23

L21

L22

Pin 2

Pin 4

L31

L33

L32

Metrology of ladders alignment

Metrology: with a CMM with interchangeable mechanical-optical heads, the positions of 12 “C” markers, 3 for each ladders, and the positions of the MCM alignment pins are measured on both sides of the tray.


Results ladders alignment
Results – ladders alignment their relative locations on the tray) + Nusil adhesives


Functional test results leakge current
Functional test results – leakge current their relative locations on the tray) + Nusil adhesives

079MID front: 1.67 uA @ 150 V

079MID back: 1.85 uA @ 150 V

050MID front: 2.02 uA @ 150 V

050MID back: 1.77 uA @ 150 V


Functional test results trigger rates vs threshold
Functional test results – trigger rates vs threshold their relative locations on the tray) + Nusil adhesives

079MID back

079MID front

050MID front

050MID back


Functional tests results bad channels
Functional tests results – bad channels their relative locations on the tray) + Nusil adhesives

  • Total number of bad channels well within specs (16 max)

  • High reliability of PA screening test on TMCM

  • High yield of wire-bonding


Conclusions
Conclusions their relative locations on the tray) + Nusil adhesives

  • Assembly and test procedures well tuned and tested on EM trays and tower 0

  • G&A moving rapidly to planned production rate

  • High yield of assembly so far

    • > 100 ladders glued and wire-bonded with no failures and well within specs

  • Tower A production well within specs

    • Leakage current

    • Noise and thresholds performance

    • Bad channels


ad