Latest Developments on the E mbedded A ssembly Sy stem Power Supply for LHC Experiments

Latest Developments on the E mbedded A ssembly Sy stem Power Supply for LHC Experiments. Giovanni GRIECO CAEN SpA g.grieco@caen.it 9th Topical Seminar on Innovative Particle and Radiation Detectors 23 - 26 May 2004   Siena, Italy. Summary. Background / previous CAEN HV/LV activities

Download Presentation

Latest Developments on the E mbedded A ssembly Sy stem Power Supply for LHC Experiments

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Latest Developments on the Embedded Assembly System Power Supply for LHC Experiments Giovanni GRIECO CAEN SpAg.grieco@caen.it 9th Topical Seminar on Innovative Particle and Radiation Detectors23 - 26 May 2004   Siena, Italy

  2. Summary • Background / previous CAEN HV/LV activities • Birth of the EASY System • EASY specifications • EASY modules • EASY integration in DCS Latest Developments on the EASY Power Supply for LHC Experiments

  3. Background • CAEN’s Power Supplies R&D activities in the last 8 years: • SY1527/2527 family • OPC Server for the SY1527/2527 • SASY2000 for Radiation Tolerant and Magnetic Field solutions  tested working devices up to: • 7 kGauss • 1*1011 p/cm2 TD - 15 kRadTID • 2*1012 n/cm2 TD • Result: • existence of a series of building blocks for a new power supply concept Latest Developments on the EASY Power Supply for LHC Experiments

  4. EASY 3000/4000 First COTS rad-tolerance tests (ENEA - La Casaccia) SASY 2002 (CMS Tracker PS Proto)tested in Magnetic field in CERN SASY 2002 (CMS Tracker PS Proto) tested under Radiation in LLN Tests with p and n in Louvain-la-Neuve of A877( CMS Muon Chambers) SASY 2000tested in Magnetic field in CERN Start of Special material research SASY 2000 tested under Radiation in LLN New design (Patented) for a family of High and Low voltage DC/DC converters First SASY 2000 functional prototype Today Feb ‘97 Sept 02 Aug 02 May ‘99 May 03 Apr 00 Jul 03 Nov 01 May 02 Hostile Area Experience Milestones Latest Developments on the EASY Power Supply for LHC Experiments

  5. Why the EASY ? • The LHC experiments need common solutions: • Reduce R&D costs (Hardware & Software) • Reduce Hardware/Software proliferation: • Use of the same crates for all Sub-detectors • Use of the same modules where possible • Use of a Common Control System • Reduce Maintenance costs: • Use of Common spare units • CAEN proposes a “catalog” approach with a limited set of modules Latest Developments on the EASY Power Supply for LHC Experiments

  6. System Philosophy Latest Developments on the EASY Power Supply for LHC Experiments

  7. Standalone RackMount Optional When NO magnetic field is present EASY3000/EASY4000 Radiation & Magnetic Field EASY 3000 Latest Developments on the EASY Power Supply for LHC Experiments

  8. EASY Main Features • Full integration in SY1527/SY2527 (it appears as a single SY1527 board) • 48V DC input • 21 slots per crate • 3 kW Maximum Output Power • Magnetic field capability: 2 kGauss • Expected rad.tol.: 1*1011 p/cm2 TD 2*1012 n/cm2 TD 15 kRadTID Latest Developments on the EASY Power Supply for LHC Experiments

  9. EASY Modules Latest Developments on the EASY Power Supply for LHC Experiments

  10. A3009 - A3016 • Reversible polarity • VMon and VSet accuracy +/- (30mV + 3% Vout) • IMon and ISet accuracy +/- (50mA + 3% Iout) • Ripple < 20mVpp (10Hz-15MHz) • VMax & IMax by trimmer per ch. • Channel alarms: • Load and Connector Over-Voltage, • Over-Current, Over-Temperature, Over-Power • On/off per Ch. • LDR trimmer on the board panel • Board enable (interlock) • 48V Service local & remote on/off • DB50 connectors Latest Developments on the EASY Power Supply for LHC Experiments

  11. A3025 – A3050 – A3100 • Reversible polarity • VMon and VSet accuracy +/- (30mV + 3% Vout) • IMon and ISet accuracy +/- (50mA + 3% Iout) • Ripple < 20mVpp (10Hz-15MHz) • VMax & IMax by trimmer per ch. • Channel alarms: • Load and Connector Over-Voltage, • Over-Current, Over-Temperature, Over-Power • On/off per Ch. • LDR trimmer on the board panel • Board enable (interlock) • 48V Service local & remote on/off • Hex head bolt connector (A3050, A3100) Latest Developments on the EASY Power Supply for LHC Experiments

  12. A3507 - A3540 – A3512 • Polararized Floating Channels • VMon and VSet accuracy (A3540 & A3512) +/- (2V + 0.1% Iout) (A3506) +/- (1V + 0.1% Iout) • IMon and ISet accuracy(A3540 & A3512) +/- (2uA + 1% Iout) (A3507) +/- (5uA + 1% Iout) • Ripple (A3540 & A3507) < 20 mV (10Hz-15MHz) (A3512) < 100 mV (10Hz-15MHz) • VMax & IMax by trimmer per board • Channel alarms: Over-Voltage,Over-Current, Over-Temperature • On/off per Ch. & Board enable (interlock) • 48V Service local & remote on/off • SHV or CPE(A3512) HV connectors Latest Developments on the EASY Power Supply for LHC Experiments

  13. First EASY module: A4601H/F • Developed for CMS Tracker • Can be used in hostile areaor in counting room • Currently under test in CAEN Latest Developments on the EASY Power Supply for LHC Experiments

  14. EASY Integration • Controlled by SY1527/SY2527 power supplies • Full integration with the software developed for SY1527/SY2527: • OPC Server • Wrapper libraries (Linux/Win32) Latest Developments on the EASY Power Supply for LHC Experiments

  15. 200 Downloads from CAEN web site (25% by CERN) CAEN delivers the 1° SY1527 to CERN CAEN and IT/CO start the collaboration Presentation of the CAEN OPC Server rel. 2.0 new features Presentation of the CAEN OPC Server project to the JCOP Meeting Integration of SY1527 into the JCOP Framework Permanent Test Bench (CAEN PS + OPC) at IT/CO Labs OPC Server rel. 1.0 (SY1527 via TCP/IP) Mar 99 Oct 99 May 00 Sep 00 Nov 00 Sep 01 Jan 02 Today CAEN OPC Server Milestones Latest Developments on the EASY Power Supply for LHC Experiments

  16. OPC SERVER EASY EASY EASY DCS + EASY EASY EASY • CAN Bus based link • Ad-hoc protocol • Speed and reliability • No interoperability issues • Can work in hostile area EASY Architecture Latest Developments on the EASY Power Supply for LHC Experiments

  17. Channel 00 Channel 01 Channel 02 … Board 01 - Channel 000 Board 01 - Channel 001 Board 01 - Channel 002 Board 01 - Channel 003 Board 01 - Channel 004 Board 01 - Channel 005 Board 01 - Channel 006 Board 01 - Channel 007 Board 01 - Channel 008 Board 01 - Channel 009 Board 01 - Channel 010 Board 01 - Channel 011 Board 01 - Channel 012 Board 01 - Channel 013 Board 01 - Channel 014 Board 01 - Channel 015 Board 01 - Channel 016 Board 01 - Channel 017 … Channel 03 Channel 04 Channel 05 EASY 3000 Channel 06 Channel 07 Channel 08 Channel 09 Channel 10 Channel 11 Channel 12 Channel 13 Channel 14 EASY 3000 Channel 15 Channel 16 Channel 17 EASY Channels Representation Latest Developments on the EASY Power Supply for LHC Experiments

  18. A1676 Branch Controller • Single slot on SY1527/SY2527 systems: • 16 boards per SY1527 • 6 boards per SY2527 • Up to 6 independent EASYs • CANBus based bus protocol • Up to 720 indipendent ch. per branch • Up to 11.520 indipendent ch. per system Latest Developments on the EASY Power Supply for LHC Experiments

  19. EASY Module Features • Local microcontroller • Firmware remotely upgradable • Hardware Imax • Per low voltage channel: • Independent ON/OFF • Vmon (Connector and Load) • Imon • Vset (Software or Hardware) • Programmable Trip • Sense wires • Status Signals Latest Developments on the EASY Power Supply for LHC Experiments

  20. SY1527 / SY2527 (front view) • Modular and Expandable • Flexible: HV, LV & branch controller boards • Reliable • Remote Firmware upgrading & Maintenance SY1527 SY2527 Latest Developments on the EASY Power Supply for LHC Experiments

  21. 3GND 3GND 3GND 3GND DB09 1GND 2GND 3GND 4GND 5GND SY1527 / SY2527 (rear view) SY1527 Branch Controller SY2527 Branch Controller Latest Developments on the EASY Power Supply for LHC Experiments

  22. SY1527/SY2527 Connectivity Latest Developments on the EASY Power Supply for LHC Experiments

  23. Conclusions • CAEN has completed all developments in Magnetic Field and Radiation • Integration in DCS (OPC Server + SY1527) is well established and already in use • The architectures of the EASY System and modules are completely defined Latest Developments on the EASY Power Supply for LHC Experiments