ENERGY PERFORMANCE CONTRACTING PROGRAM For Equipment, Design, &Installation of “Energy and Water Upgrades” at University of Massachusetts Lowell Lowell , MA . Program Goals & Objectives. EOLWD. Project Overview – Energy Analysis. Accelerated Energy Program-Executive Order 484

astrid
Download Presentation

Program Goals & Objectives

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ENERGY PERFORMANCE CONTRACTING PROGRAMFor Equipment, Design, &Installationof “Energy and Water Upgrades”at University of Massachusetts LowellLowell, MA

  2. Program Goals & Objectives EOLWD

  3. Project Overview – Energy Analysis • Accelerated Energy Program-Executive Order 484 • Energy reduction 25% • Project simple payback 15 – 20 years • 35 campus buildings (2.8 million SF) over 3 campuses were assessed to determine possible energy conservation measures (ECM’s) • Inspection of 2 boiler plants

  4. Project Overview – 30% Design • Energy Audit Identified 280 ECM’s • Start of 30% Design ~160 ECM’s • Finished of 30% Design ~150 ECM’s • $2.8 M Replacement of South Campus Boilers • $3.4 M Solar Thermal and Photovoltaic • Grant for 50% of the Solar Thermal Projects • $6.7 M Air Handling Unit Replacement/Upgrades • 20 Buildings with Lighting Projects (Replacement/Controls)

  5. Comparison (Utility costs based upon Updated FY-2014 rates)

  6. Summary of ECM’s

  7. UMASS Lowell Total Energy Reductions

  8. Opportunistic Replacements(No Energy Savings)

  9. Economics (Including Alternates*)

  10. Alternates Projects

  11. Economics (W/O Alternates)