St. Croix: Minnesota Approach Design-Build S.P. 5203-85. Request for Qualification Project Informational Meeting September 10, 2012. Kick-off Meeting Outline Welcome / Introduction Project Overview Procurement RFQ Overview (Modifications) Addendums / Clarifications. Disclaimer.

asher
Download Presentation

St. Croix: Minnesota Approach Design-Build S.P. 5203-85

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St. Croix: Minnesota Approach Design-BuildS.P. 5203-85 Request for Qualification Project Informational Meeting September 10, 2012

  2. Kick-off Meeting Outline Welcome / Introduction Project Overview Procurement • RFQ Overview (Modifications) • Addendums / Clarifications

  3. Disclaimer What is discussed today is informational only, meant to assist interested teams in the pursuit of this project. The ultimate requirements will be included in the Request for Qualifications (RFQ) & Request for Proposals (RFP). Addendums and clarifications may be issued for the RFQ. There may be changes to the scope between now and the time the RFP is issued.

  4. Project Overview

  5. Project Procurement

  6. RFQ Overview Schedule RFQ Question Deadline September 21 SOQ Due Date October 1 Issue RFP October 15 – Nov 1 Tech Proposals Due February 1 Letting February 15 Anticipated NTP 1 April 1

  7. Communication Peter Davich sole point of contact Must let Peter know if you want to receive addendum or clarifications • Addendum #1 and Clarification #1 posted to website E-mail SOQs to Peter

  8. Conflicts of Interest Firms listed in Section 2.7 are confirmed conflicts of interest Not an all inclusive list • Need to follow MnDOT Design-Build Approach to Conflict of Interest Different Appendix C Requirements • Do not need to provide all contracts with MnDOT • Include contract relationships with MnDOT and other key stakeholders within the Project and a 3 mile radius since 2002.

  9. Submittal Requirements No 11 x 17 pages Watch your font sizes!! Resumes • Level A – Managers (2 pages) • Level A – Tech Leads (1 page) • Level A – Tech Specialists (1 page) • MnDOT will not evaluate other resumes (Level B, Value Added)

  10. Project Information http://www.dot.state.mn.us/designbuild/stcroix/index/html